CME101 Construction and Installation Sequence
Answer:
TOPIC 3
- Construction and installation sequence
- Site clearing
Firstly, bring all the required machinery to site. Such machineries would include: excavators, rock drills, compacting machine among others. Bulldozers are to be used where vegetation is thick and matured. Properly de-stump the site and remove trees nearby that are likely to affect the building structural integrity. Undertake proper landscaping.
- Hording
This is to be done for safety of the general public and safety of the assets within the site. Also set up offices for effective construction management.
- Excavation
Trenches are to be dug out a width of 450mm for the strip footing placement all round the building. These are shallow trenches hence no need for temporary reinforcement.
- Waterproofing
During footing placement, ensure sound waterproofing is attained. There is a special material for waterproofing, commonly used is PVC cover material.
- Footing and ground slab establishment
- Level the ground and blind it.
- Set up the slab formwork.
- Assemble the reinforcement bars.
- Batch the concrete onto the formwork and reinforcement to produce a strip footing otherwise known as column base.
- Erect column formwork, reinforcement bars and concrete them.
- Cure slabs for 14 days.
- Erect beam formwork.
- Erect the beam reinforcement bars.
- Erect formwork for the slab
- Assemble slab reinforcement bars and fix with beam reinforcement bars.
- Services
Electricity will be supplied to the site for powering of simple electric appliances and for lighting at night.
- Inspection
Inspect the quality of precast concrete. They must be able to bear the loadings once installed. Check for cracks and replace immediately1.
- Site benchmarking
The site establishment must be benchmarked with the ideal constructions as stipulated in the various Australian standards and code of construction.
- Compaction
Once footings are sunk, the ground must be stabilized and firmed using a compaction machine.
- Termite protection
Since these are brick walls and the footing is wholly concrete, there will be no need for termite protection. However, as a cautionary measure, just before sinking the footings, apply appropriate chemical within and around the base.
- Slump test
Undertake the test during excavation and landscaping
- Wall establishment
- Set out on the ground.
- Prepare a masonry wall footing that is slightly bigger than the block (by at least 100mm on each side).
- Apply about 10mm thick mortar layer after wetting the foundation.
- Place a block on the mortar and check for alignment.
- Continue on till the first course (layer of bricks) is done.
- Repeat steps 3 to 5 for the subsequent courses of bricks.
- Add a steel strip every three or four courses of bricks.
- Plaster the brick wall faces
- Curing time
Allow curing time at minimum of 28 days (this is the standard time).
References
Murty, C. V. R., et al. "Reinforced concrete structures." Earthquake spectra 18.S1 (2002): 149-185
Nawy, Edward. Reinforced concrete: A fundamental approach. (2000).
Buy CME101 Construction and Installation Sequence Answers Online
Talk to our expert to get the help with CME101 Construction and Installation Sequence Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.