CE6106-Project Management | Assignmenthelp

Salvo, Livia and Ingrid are three graduates of the world-famous National Bakery School (NBS) at London South Bank University. Livia’s family own an Italian restaurant in Soho. In fact, it was her father’s Cannoli Siciliani that inspired her to study at NBS. Until now, the three friends have been successfully running a lunchtime food stall in Lower Marsh market, Waterloo, serving savoury and sweet pastries. Also, sometimes their friends Pushpa and Olu help out on the stall.
Recently, an opportunity has come up to take over the lease of café premises in Lower Marsh. It had been a ‘greasy spoon’ café in the olden days, but as a vegan café it is popular during weekday lunchtimes with the Christian Aid office staff down the street. The café is quite small, with just fifteen tables inside and maybe space for a further five tables in the courtyard at the back. Since Lower Marsh is more or less pedestrianised, it may also be possible to have some tables outside in the street. The street frontage faces north-west.
Salvo and Ingrid are keen to take it on, but Livia is not so sure. How would the Cannoli, Osso di Morto, Triofo di Gola and Frutta Martorana that she knows and loves – not to mention Minni di Sant Aita - fit in with a vegan café? In any case, she has long wanted to have her own Italian pasticceria closer to the University of the Arts in the up-and-coming Elephant & Castle district. Yes, it’s a Spanish and Colombian area, but she feels very much more at home there.
Anyway… the three friends have decided to seek professional advice to help them with their plans and, if they decide to go ahead, to be their project manager in developing the café (or the pasticceria – or both).
Oh, I nearly forgot: Salvo is from Florence and has heard about a project management method (or was it a ‘methodology’?) called PRINCE2. He thinks it has something to do with his compatriot, Niccolo Machiavelli. By the way, Salvo and Livia may be ‘an item’.
You have been recommended to them for the project manager role, but there are others on the short list, including some very experienced small business consultants.
1.How will you convince them you are the person they need?
2.What are their options here? Perhaps you will need to do a full
3.stakeholder analysis as part of scoping this project (or projects)?
4.What project organisational structure would you recommend?
5.What is your outline project plan?
6. What risks do you foresee?
7.How will you maintain control of the time and costs of the project?

Answer:

Project purpose

The purpose of the report is developing a charter so that it can convince the stakeholders that this project manager will be the optimum option for betterment of the restaurant. The report had developed an in depth project plan along with the project details. The project manager is proposing the different project plan along with the project schedule, budget and resource allocation. There are other competitors in queue so it is essential to provide justifications for choosing this project manager over other interviewees.

Project description

The major shareholders of the project are Salvo, Ingrid and Livia who have invested in leasing a greasy spoon cafe in Lower Marsh market. Three of them have graduated from national Bakery School which is one of the most famous universities in the world. The cafe that they are leasing has certain issues which will have to sorted if the organization to sustain in the market. The Cafe is relatively small consisting only fifteen tables, there are spaces of keeping extra tables on the courtyard and some on the streets. The cafe had been a vegan cafe and it would be tough for them to convert the cafe into something suitable for their business idea. Therefore, they need help of a project manager that can effectively transform the cafe and give it a new look, decor and ambience. The shareholders want to use PRINCE2 which deals with project measurement and control so the project manager will have to develop a project management plan using Prince2 method.

Project Scope statement

Project scope statement will define the objectives, deliverables and milestones that is necessary for successful execution of the project (Kerzner and Kerzner 2017). The project scope statement in this project will consist of refurbishing a vegan cafe into a condition that is operable and sustainable.

Stakeholders

Stakeholders are the parties which either influence the success of the project or are influenced by the success of the project (Bentley 2015). The key stakeholders in this project are as follows:

  • Salvo: Salvo is one of the shareholders of the cafe and

    expertises in kitchen activities. Salvo will look after the kitchen renovation and installation of equipments and overall project performance.
  • Livia: Livia is another partner of the cafe who will look after the operation of the cafe along with managing the quality of food in the cafe,
  • Project Manager:The project manager is the key stakeholder for reaching the desired outcome. The project manager develops the plan according to the requirement of the stakeholders and distributes tasks to different members of the project team.
  • Interior designer:The interior designer will design the cafe to modify the decor of the cafe and give it a modernized look. The interior designer will identify ways of using the available space in a better way.
  • Labours:The labours will do the manual work which will include painting and designing. The labours are important stakeholders as they will do the majority of the work by following the instructions of the other team members.
  • Technical engineers:The technical engineers will take care of the technical aspect of the cafe which will include electrical and electronic requirements of the cafe.

Project objectives

Project objective will consist of the goals and the expected outcomes which the shareholders wants to achieve from the project (Fleming and Koppelman 2016). The objectives of the current project are described below:

  • Reinventing the interior of the cafe
  • Proper utilization of the cafe space to increasing seating capacity
  • Installation of necessary equipments
  • Promoting the restaurant
  • Monitoring and controlling the cafe’s processes in order to maximize the output and minimize the cost of production

Project requirements

Project requirement will define the different tasks that must be completed in order to complete that phase and succeed (Harrison and Lock 2017). This will enable the project team to understand the tasks that have to be done and the way it can be achieved. This will also facilitate in aligning the resources used in the project along with the tasks. The project requirements are described below:

  • Applying changes to the cafe to suit the needs of the stakeholders
  • Technical requirements
  • Analyzing customer needs and develop marketing plan
  • Implement the marketing plan

Project constraints

Time and cost are the main constraints for this project where the project has to be completed using optimal techniques so that cost and time can be optimized (Shiohama et al. 2016). Moreover, the available space is a big constraint for the project and the project team will have to use the space effectively to reach economies of scale.

Project assumptions

The main assumption of this project is as follows:

  • The stakeholders have clear idea about the different phases of the project and they have fully authorized the execution of this project.
  • The purpose and objective of the project has been clearly communicated to all the team members in order to maintain the objectivity

Project deliverables

The project deliverables will define the different phases of the study consisting of the outcomes that will have to be achieved for successful implementation of the project (Chow, Woodford and Lambe 2014). This will consist of both the inputs and outputs of the project. The project deliverables for the current study have been defined below:

Task Name

Duration

Start

Finish

Restaurant renovation plan

28 days

Wed 5/2/18

Fri 6/8/18

1.0 Interior design

6 days

Wed 5/2/18

Wed 5/9/18

2.0 Restaurant equipments and accessories

3 days

Mon 5/7/18

Wed 5/9/18

3.0 Process Implementation

10 days

Thu 5/10/18

Wed 5/23/18

4.0 kitchen and other equipments

4 days

Thu 5/10/18

Tue 5/15/18

5.0 Marketing and promotion

7 days

Wed 5/16/18

Thu 5/24/18

6.0 Monitor and Control

11 days

Fri 5/25/18

Fri 6/8/18

Project milestones

The project progress is marked through the timeline and the event defining the progress will consist of tasks having nil duration (Frank, Koenig and Srivastava 2017). The project can be made successful by defining the key milestones effectively so that the project can be executed in a better way. In the current project, the key milestones are depicted below:

Task Name

Duration

Start

Finish

1.7 Milestone 1: Interior design specification prepared

0 days

Wed 5/9/18

Wed 5/9/18

2.8 Milestone 2: Restaurant equipments and accessories identified

0 days

Wed 5/9/18

Wed 5/9/18

3.5 Milestone 3:Internal renovation completed

0 days

Wed 5/23/18

Wed 5/23/18

4.5 Milestone 4: Kitchen equipments added

0 days

Tue 5/15/18

Tue 5/15/18

5.6 Milestone 5: Marketing and promotion completed

0 days

Thu 5/24/18

Thu 5/24/18

6.5. Milestone 6: Control phase completed

0 days

Fri 6/8/18

Fri 6/8/18

Summary schedule

The summary schedule will provide a broad view of the different tasks that has to be performed at each stage of the project along with the timeframe of each of the task. Therefore, the project schedule will ensure that each of the tasks is being performed within the given timeframe. The overall duration for renovating the restaurant is 79 and the project commences on 2nd may, 2018 and will finish in 8th May, 2018.

Task Name

Duration

Start

Finish

Restaurant renovation plan

28 days

Wed 5/2/18

Fri 6/8/18

1.0 Interior design

6 days

Wed 5/2/18

Wed 5/9/18

1.1 Identify the changes required for modernization

1 day

Wed 5/2/18

Wed 5/2/18

1.2 Develop requirements for internal renovation

1 day

Thu 5/3/18

Thu 5/3/18

1.3 Discuss with the stakeholders

1 day

Fri 5/4/18

Fri 5/4/18

1.4 Modify the requirements if needed

1 day

Mon 5/7/18

Mon 5/7/18

1.5 Document specifications

1 day

Tue 5/8/18

Tue 5/8/18

1.6 Deploy the specifications

1 day

Wed 5/9/18

Wed 5/9/18

1.7 Milestone 1: Interior design specification prepared

0 days

Wed 5/9/18

Wed 5/9/18

2.0 Restaurant equipments and accessories

3 days

Mon 5/7/18

Wed 5/9/18

2.1 Identify the furniture required

1 day

Mon 5/7/18

Mon 5/7/18

2.2 Lighting requirements

0.5 days

Mon 5/7/18

Mon 5/7/18

2.3 Décor items

1 day

Mon 5/7/18

Mon 5/7/18

2.4 POS installation

1 day

Mon 5/7/18

Mon 5/7/18

2.5 Security requirements

1 day

Mon 5/7/18

Mon 5/7/18

2.6 Document specifications

1 day

Tue 5/8/18

Tue 5/8/18

2.7 Send for approval

1 day

Wed 5/9/18

Wed 5/9/18

2.8 Milestone 2: Restaurant equipments and accessories identified

0 days

Wed 5/9/18

Wed 5/9/18

3.0 Process Implementation

10 days

Thu 5/10/18

Wed 5/23/18

3.1 Renovation of the café

5 days

Thu 5/10/18

Wed 5/16/18

3.2 Identify any deviation

2 days

Thu 5/17/18

Fri 5/18/18

3.3 Make changes

3 days

Mon 5/21/18

Wed 5/23/18

3.4 implement the changes

3 days

Mon 5/21/18

Wed 5/23/18

3.5 Milestone 3:Internal renovation completed

0 days

Wed 5/23/18

Wed 5/23/18

4.0 kitchen and other equipments

4 days

Thu 5/10/18

Tue 5/15/18

4.1 kitchen supplies

2 days

Thu 5/10/18

Fri 5/11/18

4.2 Kitchen equipments installation

2 days

Thu 5/10/18

Fri 5/11/18

4.3 office equipments

1 day

Mon 5/14/18

Mon 5/14/18

4.4 uniforms

1 day

Tue 5/15/18

Tue 5/15/18

4.5 Milestone 4: Kitchen equipments added

0 days

Tue 5/15/18

Tue 5/15/18

5.0 Marketing and promotion

7 days

Wed 5/16/18

Thu 5/24/18

5.1 Developing content and logo

3 days

Wed 5/16/18

Fri 5/18/18

5.2 Menu layout and printing

1 day

Wed 5/16/18

Wed 5/16/18

5.3 promotion

7 days

Wed 5/16/18

Thu 5/24/18

5.4 P.R. selection

7 days

Wed 5/16/18

Thu 5/24/18

5.5 Advertising

7 days

Wed 5/16/18

Thu 5/24/18

5.6 Milestone 5: Marketing and promotion completed

0 days

Thu 5/24/18

Thu 5/24/18

6.0 Monitor and Control

11 days

Fri 5/25/18

Fri 6/8/18

6.1 Defining the performance indicators

1 day

Fri 5/25/18

Fri 5/25/18

6.2 Monitor and Measure performance

3 days

Mon 5/28/18

Wed 5/30/18

6.3Identify scope creep

3 days

Thu 5/31/18

Mon 6/4/18

6.4 Control deviation

4 days

Tue 6/5/18

Fri 6/8/18

6.5. Milestone 6: Control phase completed

0 days

Fri 6/8/18

Fri 6/8/18


Gantt chart

Work Breakdown Structure

Project budget

Project budget will define the overall budget of the project along with the cost of each task along with the resources that has been allocated to them (Klingebiel and Rammer 2014). The budget for this budget is the forecasted which has been developed by taking into account the optimal conditions. The budget for the current project is described in the table below and also highlights the slack in each of the tasks. The business plan developed for the project will be sent to potential investors and banks. The business plan will consist of the cash flow statement, budget and break even analysis. This will facilitate in gaining potential investors from the market.

Task Name

Resource Names

Cost

Total Slack

Restaurant renovation plan

 

$14,620.00

0 days

1.0 Interior design

 

$1,728.00

0 days

1.1 Identify the changes required for modernization

Livia, Project Manager, Salvo

$320.00

0 days

1.2 Develop requirements for internal renovation

Project Manager, interior designer, Livia, Salvo ,technical engineers

$504.00

0 days

1.3 Discuss with the stakeholders

Livia, Project Manager, interior designer, Ingrid, Salvo

$560.00

0 days

1.4 Modify the requirements if needed

Project Manager

$160.00

22 days

1.5 Document specifications

interior designer, technical engineers

$184.00

22 days

1.6 Deploy the specifications

 

$0.00

22 days

1.7 Milestone 1: Interior design specification prepared

 

$0.00

22 days

2.0 Restaurant equipment’s and accessories

 

$668.00

0 days

2.1 Identify the furniture required

interior designer, Salvo

$200.00

0 days

2.2 Lighting requirements

interior designer

$60.00

0.5 days

2.3 Décor items

interior designer

$120.00

0 days

2.4 POS installation

technical engineers

$64.00

0 days

2.5 Security requirements

technical engineers

$64.00

0 days

2.6 Document specifications

Team Manager

$80.00

0 days

2.7 Send for approval

Team Manager

$80.00

0 days

2.8 Milestone 2: Restaurant equipments and accessories identified

 

$0.00

0 days

3.0 Process Implementation

 

$3,920.00

12 days

3.1 Renovation of the café

equipment[1],interior designer, labours, technical engineers

$3,120.00

12 days

3.2 Identify any deviation

Project Manager

$320.00

12 days

3.3 Make changes

interior designer

$360.00

12 days

3.4 implement the changes

labours

$120.00

12 days

3.5 Milestone 3:Internal renovation completed

 

$0.00

12 days

4.0 kitchen and other equipment

 

$2,504.00

0 days

4.1 kitchen supplies

Livia, Salvo

$320.00

0 days

4.2 Kitchen equipment installation

labours

$80.00

20 days

4.3 office equipment

labours, technical engineers

$104.00

0 days

4.4 uniforms

equipment[1]

$2,000.00

0 days

4.5 Milestone 4: Kitchen equipment added

 

$0.00

0 days

5.0 Marketing and promotion

 

$3,880.00

0 days

5.1 Developing content and logo

Ingrid

$360.00

4 days

5.2 Menu layout and printing

Marketing equipment[1]

$1,000.00

6 days

5.3 promotion

Ingrid

$840.00

0 days

5.4 P.R. selection

Ingrid

$840.00

0 days

5.5 Advertising

Ingrid

$840.00

0 days

5.6 Milestone 5: Marketing and promotion completed

 

$0.00

0 days

6.0 Monitor and Control

 

$1,920.00

0 days

6.1 Defining the performance indicators

Project Manager, Livia, Salvo

$320.00

0 days

6.2 Monitor and Measure performance

Project Manager

$480.00

0 days

6.3Identify scope creep

Project Manager

$480.00

0 days

6.4 Control deviation

Project Manager

$640.00

0 days

6.5. Milestone 6: Control phase completed

 

$0.00

0 days

Resource Plan

The resource plan will define the different resources that are needed along with the individual cost of each of the resources, the total time span of each of the resources along with the overall cost of each resource. The resource plan for the current has been described below:

Name

Start

Finish

Cost

Remaining Work

Salvo

Wed 02-05-18

Fri 25-05-18

$560.00

56 hrs

Livia

Wed 02-05-18

Fri 25-05-18

$480.00

48 hrs

Project Manager

Wed 02-05-18

Fri 08-06-18

$2,720.00

136 hrs

interior designer

Thu 03-05-18

Wed 23-05-18

$1,620.00

108 hrs

labours

Thu 10-05-18

Wed 23-05-18

$440.00

88 hrs

Ingrid

Fri 04-05-18

Thu 24-05-18

$3,000.00

200 hrs

technical engineers

Thu 03-05-18

Wed 16-05-18

$640.00

80 hrs

Team Manager

Tue 08-05-18

Wed 09-05-18

$160.00

16 hrs

Risk management

Type of risk

Risk Description

Probability

Impact

Risk reduction Strategy

Contingency Plan

  

High

Medium

Low

Performance

Cost

Time

  

External

Delay in receiving materials from the suppliers

 

yes

   

yes

This can be avoided by developing an effective inventory management plan so that there is no shortage of supplies for executing the project.

The project team will have to add buffer time to each of the task so that even if there is shortage of inventory, it would not affect the time span of the project.

External

Unanticipated issue

 

Yes

 

yes

yes

yes

 There are issues which cannot be anticipate which could consist of changes in rules and regulation in the industry. This can be minimized by keeping clear knowledge about the external environment of the organization.

 The project team will have to develop a risk register which will consist of identifying the external factors that will affect the project.

Internal

Scope creep

Yes

  

yes

yes

yes

 The changes in the deliverables should be accepted at the initial phase of the project so that there is no change in the later stage. Therefore, the product specifications will have to be confirmed before commencing with the other phases.

 The project team may use agile methodology instead of using the waterfall methodology. This will ensure that the project team to incorporate changes to all stages.

Internal

 Delay in installation of the equipments

Yes

   

yes

yes

The delay in installation of the equipment can be reduced by developing an effective communication which will enable them to understand the different phases and aware of the timeframe of each of the tasks.

 The project tae could include a buffer time to each of this phases so that the slack in each of the stages can be effectively used to manage the timeframe.


Project control

The project control and monitoring will consist of developing an effective quality management plan which will be providing reference systems for monitoring the plan. This will consist of different initiatives such as quality control, developing communication plan, benchmarking and setting up different standards and cost benefit analysis (Binder 2016). This will also consist of developing an effective risk management plan along with defining the quality metrics of the project. The project manager will also have to monitor the over allocation of resources and identify the critical and non critical task to reduce the cost. The allocation of extra resources to the non-critical tasks means that the cost will increase in case of the activity such as 1.4 to 1.6. The increase in resources will not reduce the timeframe of the overall project so this an unnecessary cost for a project of small magnitude. Therefore, the allocation of resources in non-critical tasks will have to be reduced so the budget can be reduced to increase the feasibility of the project.

Policy/Directive/Standard/etc

Reference

Comment

Communication plan

Meetings

The communication plan will define the schedule of the meetings that will have to be conducted for developing the management plan effectively. Communicating status of the project and the tasks will be essential for identifying the success of the project. This will also facilitate in team bonding and developing awareness among the stakeholders about their project role.

Cost of quality

Quality metrics

 The project manager will have to define metrics for measuring each of the tasks and deliverables which will enable them to benchmark each of the activity. This will consist of defining the required output and constant comparison of the output that is received to develop an effective management of the project.

Cost benefit analysis

Project management plan

 The project manager will measure the overall cost of the project and the benefits that can be obtained from the successful completion of the project to define the required output to achieve success.

Benchmarking

Scope Creep

The scope creep is one of the most common phenomenons in a project where there is deviation of output from the original output. The project manager will have to set a baseline for each of the tasks and this can be considered as benchmarking of the tasks in the project. This will ensure that the project team can monitor and control the project requirement without any complexity.

Conclusion

The project management plan that has been developed cannot be effectively executed without the guidance of the project manager. The project manager will be able to make changes to the tasks and identify whether the tasks are critical and non critical. The understanding of the tasks will enable to manage the schedule effectively and make necessary changes based on the risk factors. Therefore, the importance of the project manager in revamping the cafe is extremely high and the stakeholders should consider this project charter before making their decision.

References

Bentley, C., 2015. The PRINCE2 Practitioner: From Practitioner to Professional. Routledge.

Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.

Chow, A.F., Woodford, K.C. and Lambe, N., 2014. Using project deliverables and project management for timely completion of student projects. Journal of Emerging Trends in Economics and Management Sciences, 5(3), p.323.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Frank, L.H., Koenig, P.R. and Srivastava, S., 2017. Connecting milestones to observable clinical performance through standardized pediatric cardiology rotation evaluations: Report and reflections on a novel pilot project. Progress in Pediatric Cardiology, 44, pp.11-15.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Klingebiel, R. and Rammer, C., 2014. Resource allocation strategy for innovation portfolio management. Strategic Management Journal, 35(2), pp.246-268.

Shiohama, R., Washizaki, H., Kuboaki, S., Sakamoto, K. and Fukazawa, Y., 2016. Investigating the relationship between project constraints and appropriate iteration length in agile development through simulations. International Journal of Computer Applications in Technology, 54(4), pp.311-322.


Buy CE6106-Project Management | Assignmenthelp Answers Online

Talk to our expert to get the help with CE6106-Project Management | Assignmenthelp Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for CE6106-Project Management | Assignmenthelp Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.