CE6106-Project Management | Assignmenthelp
2.What are their options here? Perhaps you will need to do a full
3.stakeholder analysis as part of scoping this project (or projects)?
4.What project organisational structure would you recommend?
5.What is your outline project plan?
7.How will you maintain control of the time and costs of the project?
Answer:
Project purpose
The purpose of the report is developing a charter so that it can convince the stakeholders that this project manager will be the optimum option for betterment of the restaurant. The report had developed an in depth project plan along with the project details. The project manager is proposing the different project plan along with the project schedule, budget and resource allocation. There are other competitors in queue so it is essential to provide justifications for choosing this project manager over other interviewees.
Project description
The major shareholders of the project are Salvo, Ingrid and Livia who have invested in leasing a greasy spoon cafe in Lower Marsh market. Three of them have graduated from national Bakery School which is one of the most famous universities in the world. The cafe that they are leasing has certain issues which will have to sorted if the organization to sustain in the market. The Cafe is relatively small consisting only fifteen tables, there are spaces of keeping extra tables on the courtyard and some on the streets. The cafe had been a vegan cafe and it would be tough for them to convert the cafe into something suitable for their business idea. Therefore, they need help of a project manager that can effectively transform the cafe and give it a new look, decor and ambience. The shareholders want to use PRINCE2 which deals with project measurement and control so the project manager will have to develop a project management plan using Prince2 method.
Project Scope statement
Project scope statement will define the objectives, deliverables and milestones that is necessary for successful execution of the project (Kerzner and Kerzner 2017). The project scope statement in this project will consist of refurbishing a vegan cafe into a condition that is operable and sustainable.
Stakeholders
Stakeholders are the parties which either influence the success of the project or are influenced by the success of the project (Bentley 2015). The key stakeholders in this project are as follows:
- Salvo: Salvo is one of the shareholders of the cafe and
expertises in kitchen activities. Salvo will look after the kitchen renovation and installation of equipments and overall project performance. - Livia: Livia is another partner of the cafe who will look after the operation of the cafe along with managing the quality of food in the cafe,
- Project Manager:The project manager is the key stakeholder for reaching the desired outcome. The project manager develops the plan according to the requirement of the stakeholders and distributes tasks to different members of the project team.
- Interior designer:The interior designer will design the cafe to modify the decor of the cafe and give it a modernized look. The interior designer will identify ways of using the available space in a better way.
- Labours:The labours will do the manual work which will include painting and designing. The labours are important stakeholders as they will do the majority of the work by following the instructions of the other team members.
- Technical engineers:The technical engineers will take care of the technical aspect of the cafe which will include electrical and electronic requirements of the cafe.
Project objectives
Project objective will consist of the goals and the expected outcomes which the shareholders wants to achieve from the project (Fleming and Koppelman 2016). The objectives of the current project are described below:
- Reinventing the interior of the cafe
- Proper utilization of the cafe space to increasing seating capacity
- Installation of necessary equipments
- Promoting the restaurant
- Monitoring and controlling the cafe’s processes in order to maximize the output and minimize the cost of production
Project requirements
Project requirement will define the different tasks that must be completed in order to complete that phase and succeed (Harrison and Lock 2017). This will enable the project team to understand the tasks that have to be done and the way it can be achieved. This will also facilitate in aligning the resources used in the project along with the tasks. The project requirements are described below:
- Applying changes to the cafe to suit the needs of the stakeholders
- Technical requirements
- Analyzing customer needs and develop marketing plan
- Implement the marketing plan
Project constraints
Time and cost are the main constraints for this project where the project has to be completed using optimal techniques so that cost and time can be optimized (Shiohama et al. 2016). Moreover, the available space is a big constraint for the project and the project team will have to use the space effectively to reach economies of scale.
Project assumptions
The main assumption of this project is as follows:
- The stakeholders have clear idea about the different phases of the project and they have fully authorized the execution of this project.
- The purpose and objective of the project has been clearly communicated to all the team members in order to maintain the objectivity
Project deliverables
The project deliverables will define the different phases of the study consisting of the outcomes that will have to be achieved for successful implementation of the project (Chow, Woodford and Lambe 2014). This will consist of both the inputs and outputs of the project. The project deliverables for the current study have been defined below:
Task Name |
Duration |
Start |
Finish |
Restaurant renovation plan |
28 days |
Wed 5/2/18 |
Fri 6/8/18 |
1.0 Interior design |
6 days |
Wed 5/2/18 |
Wed 5/9/18 |
2.0 Restaurant equipments and accessories |
3 days |
Mon 5/7/18 |
Wed 5/9/18 |
3.0 Process Implementation |
10 days |
Thu 5/10/18 |
Wed 5/23/18 |
4.0 kitchen and other equipments |
4 days |
Thu 5/10/18 |
Tue 5/15/18 |
5.0 Marketing and promotion |
7 days |
Wed 5/16/18 |
Thu 5/24/18 |
6.0 Monitor and Control |
11 days |
Fri 5/25/18 |
Fri 6/8/18 |
Project milestones
The project progress is marked through the timeline and the event defining the progress will consist of tasks having nil duration (Frank, Koenig and Srivastava 2017). The project can be made successful by defining the key milestones effectively so that the project can be executed in a better way. In the current project, the key milestones are depicted below:
Task Name |
Duration |
Start |
Finish |
1.7 Milestone 1: Interior design specification prepared |
0 days |
Wed 5/9/18 |
Wed 5/9/18 |
2.8 Milestone 2: Restaurant equipments and accessories identified |
0 days |
Wed 5/9/18 |
Wed 5/9/18 |
3.5 Milestone 3:Internal renovation completed |
0 days |
Wed 5/23/18 |
Wed 5/23/18 |
4.5 Milestone 4: Kitchen equipments added |
0 days |
Tue 5/15/18 |
Tue 5/15/18 |
5.6 Milestone 5: Marketing and promotion completed |
0 days |
Thu 5/24/18 |
Thu 5/24/18 |
6.5. Milestone 6: Control phase completed |
0 days |
Fri 6/8/18 |
Fri 6/8/18 |
Summary schedule
The summary schedule will provide a broad view of the different tasks that has to be performed at each stage of the project along with the timeframe of each of the task. Therefore, the project schedule will ensure that each of the tasks is being performed within the given timeframe. The overall duration for renovating the restaurant is 79 and the project commences on 2nd may, 2018 and will finish in 8th May, 2018.
Task Name |
Duration |
Start |
Finish |
Restaurant renovation plan |
28 days |
Wed 5/2/18 |
Fri 6/8/18 |
1.0 Interior design |
6 days |
Wed 5/2/18 |
Wed 5/9/18 |
1.1 Identify the changes required for modernization |
1 day |
Wed 5/2/18 |
Wed 5/2/18 |
1.2 Develop requirements for internal renovation |
1 day |
Thu 5/3/18 |
Thu 5/3/18 |
1.3 Discuss with the stakeholders |
1 day |
Fri 5/4/18 |
Fri 5/4/18 |
1.4 Modify the requirements if needed |
1 day |
Mon 5/7/18 |
Mon 5/7/18 |
1.5 Document specifications |
1 day |
Tue 5/8/18 |
Tue 5/8/18 |
1.6 Deploy the specifications |
1 day |
Wed 5/9/18 |
Wed 5/9/18 |
1.7 Milestone 1: Interior design specification prepared |
0 days |
Wed 5/9/18 |
Wed 5/9/18 |
2.0 Restaurant equipments and accessories |
3 days |
Mon 5/7/18 |
Wed 5/9/18 |
2.1 Identify the furniture required |
1 day |
Mon 5/7/18 |
Mon 5/7/18 |
2.2 Lighting requirements |
0.5 days |
Mon 5/7/18 |
Mon 5/7/18 |
2.3 Décor items |
1 day |
Mon 5/7/18 |
Mon 5/7/18 |
2.4 POS installation |
1 day |
Mon 5/7/18 |
Mon 5/7/18 |
2.5 Security requirements |
1 day |
Mon 5/7/18 |
Mon 5/7/18 |
2.6 Document specifications |
1 day |
Tue 5/8/18 |
Tue 5/8/18 |
2.7 Send for approval |
1 day |
Wed 5/9/18 |
Wed 5/9/18 |
2.8 Milestone 2: Restaurant equipments and accessories identified |
0 days |
Wed 5/9/18 |
Wed 5/9/18 |
3.0 Process Implementation |
10 days |
Thu 5/10/18 |
Wed 5/23/18 |
3.1 Renovation of the café |
5 days |
Thu 5/10/18 |
Wed 5/16/18 |
3.2 Identify any deviation |
2 days |
Thu 5/17/18 |
Fri 5/18/18 |
3.3 Make changes |
3 days |
Mon 5/21/18 |
Wed 5/23/18 |
3.4 implement the changes |
3 days |
Mon 5/21/18 |
Wed 5/23/18 |
3.5 Milestone 3:Internal renovation completed |
0 days |
Wed 5/23/18 |
Wed 5/23/18 |
4.0 kitchen and other equipments |
4 days |
Thu 5/10/18 |
Tue 5/15/18 |
4.1 kitchen supplies |
2 days |
Thu 5/10/18 |
Fri 5/11/18 |
4.2 Kitchen equipments installation |
2 days |
Thu 5/10/18 |
Fri 5/11/18 |
4.3 office equipments |
1 day |
Mon 5/14/18 |
Mon 5/14/18 |
4.4 uniforms |
1 day |
Tue 5/15/18 |
Tue 5/15/18 |
4.5 Milestone 4: Kitchen equipments added |
0 days |
Tue 5/15/18 |
Tue 5/15/18 |
5.0 Marketing and promotion |
7 days |
Wed 5/16/18 |
Thu 5/24/18 |
5.1 Developing content and logo |
3 days |
Wed 5/16/18 |
Fri 5/18/18 |
5.2 Menu layout and printing |
1 day |
Wed 5/16/18 |
Wed 5/16/18 |
5.3 promotion |
7 days |
Wed 5/16/18 |
Thu 5/24/18 |
5.4 P.R. selection |
7 days |
Wed 5/16/18 |
Thu 5/24/18 |
5.5 Advertising |
7 days |
Wed 5/16/18 |
Thu 5/24/18 |
5.6 Milestone 5: Marketing and promotion completed |
0 days |
Thu 5/24/18 |
Thu 5/24/18 |
6.0 Monitor and Control |
11 days |
Fri 5/25/18 |
Fri 6/8/18 |
6.1 Defining the performance indicators |
1 day |
Fri 5/25/18 |
Fri 5/25/18 |
6.2 Monitor and Measure performance |
3 days |
Mon 5/28/18 |
Wed 5/30/18 |
6.3Identify scope creep |
3 days |
Thu 5/31/18 |
Mon 6/4/18 |
6.4 Control deviation |
4 days |
Tue 6/5/18 |
Fri 6/8/18 |
6.5. Milestone 6: Control phase completed |
0 days |
Fri 6/8/18 |
Fri 6/8/18 |
Gantt chart
Work Breakdown Structure
Project budget
Project budget will define the overall budget of the project along with the cost of each task along with the resources that has been allocated to them (Klingebiel and Rammer 2014). The budget for this budget is the forecasted which has been developed by taking into account the optimal conditions. The budget for the current project is described in the table below and also highlights the slack in each of the tasks. The business plan developed for the project will be sent to potential investors and banks. The business plan will consist of the cash flow statement, budget and break even analysis. This will facilitate in gaining potential investors from the market.
Task Name |
Resource Names |
Cost |
Total Slack |
Restaurant renovation plan |
$14,620.00 |
0 days | |
1.0 Interior design |
$1,728.00 |
0 days | |
1.1 Identify the changes required for modernization |
Livia, Project Manager, Salvo |
$320.00 |
0 days |
1.2 Develop requirements for internal renovation |
Project Manager, interior designer, Livia, Salvo ,technical engineers |
$504.00 |
0 days |
1.3 Discuss with the stakeholders |
Livia, Project Manager, interior designer, Ingrid, Salvo |
$560.00 |
0 days |
1.4 Modify the requirements if needed |
Project Manager |
$160.00 |
22 days |
1.5 Document specifications |
interior designer, technical engineers |
$184.00 |
22 days |
1.6 Deploy the specifications |
$0.00 |
22 days | |
1.7 Milestone 1: Interior design specification prepared |
$0.00 |
22 days | |
2.0 Restaurant equipment’s and accessories |
$668.00 |
0 days | |
2.1 Identify the furniture required |
interior designer, Salvo |
$200.00 |
0 days |
2.2 Lighting requirements |
interior designer |
$60.00 |
0.5 days |
2.3 Décor items |
interior designer |
$120.00 |
0 days |
2.4 POS installation |
technical engineers |
$64.00 |
0 days |
2.5 Security requirements |
technical engineers |
$64.00 |
0 days |
2.6 Document specifications |
Team Manager |
$80.00 |
0 days |
2.7 Send for approval |
Team Manager |
$80.00 |
0 days |
2.8 Milestone 2: Restaurant equipments and accessories identified |
$0.00 |
0 days | |
3.0 Process Implementation |
$3,920.00 |
12 days | |
3.1 Renovation of the café |
equipment[1],interior designer, labours, technical engineers |
$3,120.00 |
12 days |
3.2 Identify any deviation |
Project Manager |
$320.00 |
12 days |
3.3 Make changes |
interior designer |
$360.00 |
12 days |
3.4 implement the changes |
labours |
$120.00 |
12 days |
3.5 Milestone 3:Internal renovation completed |
$0.00 |
12 days | |
4.0 kitchen and other equipment |
$2,504.00 |
0 days | |
4.1 kitchen supplies |
Livia, Salvo |
$320.00 |
0 days |
4.2 Kitchen equipment installation |
labours |
$80.00 |
20 days |
4.3 office equipment |
labours, technical engineers |
$104.00 |
0 days |
4.4 uniforms |
equipment[1] |
$2,000.00 |
0 days |
4.5 Milestone 4: Kitchen equipment added |
$0.00 |
0 days | |
5.0 Marketing and promotion |
$3,880.00 |
0 days | |
5.1 Developing content and logo |
Ingrid |
$360.00 |
4 days |
5.2 Menu layout and printing |
Marketing equipment[1] |
$1,000.00 |
6 days |
5.3 promotion |
Ingrid |
$840.00 |
0 days |
5.4 P.R. selection |
Ingrid |
$840.00 |
0 days |
5.5 Advertising |
Ingrid |
$840.00 |
0 days |
5.6 Milestone 5: Marketing and promotion completed |
$0.00 |
0 days | |
6.0 Monitor and Control |
$1,920.00 |
0 days | |
6.1 Defining the performance indicators |
Project Manager, Livia, Salvo |
$320.00 |
0 days |
6.2 Monitor and Measure performance |
Project Manager |
$480.00 |
0 days |
6.3Identify scope creep |
Project Manager |
$480.00 |
0 days |
6.4 Control deviation |
Project Manager |
$640.00 |
0 days |
6.5. Milestone 6: Control phase completed |
$0.00 |
0 days |
Resource Plan
The resource plan will define the different resources that are needed along with the individual cost of each of the resources, the total time span of each of the resources along with the overall cost of each resource. The resource plan for the current has been described below:
Name |
Start |
Finish |
Cost |
Remaining Work |
Salvo |
Wed 02-05-18 |
Fri 25-05-18 |
$560.00 |
56 hrs |
Livia |
Wed 02-05-18 |
Fri 25-05-18 |
$480.00 |
48 hrs |
Project Manager |
Wed 02-05-18 |
Fri 08-06-18 |
$2,720.00 |
136 hrs |
interior designer |
Thu 03-05-18 |
Wed 23-05-18 |
$1,620.00 |
108 hrs |
labours |
Thu 10-05-18 |
Wed 23-05-18 |
$440.00 |
88 hrs |
Ingrid |
Fri 04-05-18 |
Thu 24-05-18 |
$3,000.00 |
200 hrs |
technical engineers |
Thu 03-05-18 |
Wed 16-05-18 |
$640.00 |
80 hrs |
Team Manager |
Tue 08-05-18 |
Wed 09-05-18 |
$160.00 |
16 hrs |
Risk management
Type of risk |
Risk Description |
Probability |
Impact |
Risk reduction Strategy |
Contingency Plan | ||||
High |
Medium |
Low |
Performance |
Cost |
Time | ||||
External |
Delay in receiving materials from the suppliers |
yes |
yes |
This can be avoided by developing an effective inventory management plan so that there is no shortage of supplies for executing the project. |
The project team will have to add buffer time to each of the task so that even if there is shortage of inventory, it would not affect the time span of the project. | ||||
External |
Unanticipated issue |
Yes |
yes |
yes |
yes |
There are issues which cannot be anticipate which could consist of changes in rules and regulation in the industry. This can be minimized by keeping clear knowledge about the external environment of the organization. |
The project team will have to develop a risk register which will consist of identifying the external factors that will affect the project. | ||
Internal |
Scope creep |
Yes |
yes |
yes |
yes |
The changes in the deliverables should be accepted at the initial phase of the project so that there is no change in the later stage. Therefore, the product specifications will have to be confirmed before commencing with the other phases. |
The project team may use agile methodology instead of using the waterfall methodology. This will ensure that the project team to incorporate changes to all stages. | ||
Internal |
Delay in installation of the equipments |
Yes |
yes |
yes |
The delay in installation of the equipment can be reduced by developing an effective communication which will enable them to understand the different phases and aware of the timeframe of each of the tasks. |
The project tae could include a buffer time to each of this phases so that the slack in each of the stages can be effectively used to manage the timeframe. |
Project control
The project control and monitoring will consist of developing an effective quality management plan which will be providing reference systems for monitoring the plan. This will consist of different initiatives such as quality control, developing communication plan, benchmarking and setting up different standards and cost benefit analysis (Binder 2016). This will also consist of developing an effective risk management plan along with defining the quality metrics of the project. The project manager will also have to monitor the over allocation of resources and identify the critical and non critical task to reduce the cost. The allocation of extra resources to the non-critical tasks means that the cost will increase in case of the activity such as 1.4 to 1.6. The increase in resources will not reduce the timeframe of the overall project so this an unnecessary cost for a project of small magnitude. Therefore, the allocation of resources in non-critical tasks will have to be reduced so the budget can be reduced to increase the feasibility of the project.
Policy/Directive/Standard/etc |
Reference |
Comment |
Communication plan |
Meetings |
The communication plan will define the schedule of the meetings that will have to be conducted for developing the management plan effectively. Communicating status of the project and the tasks will be essential for identifying the success of the project. This will also facilitate in team bonding and developing awareness among the stakeholders about their project role. |
Cost of quality |
Quality metrics |
The project manager will have to define metrics for measuring each of the tasks and deliverables which will enable them to benchmark each of the activity. This will consist of defining the required output and constant comparison of the output that is received to develop an effective management of the project. |
Cost benefit analysis |
Project management plan |
The project manager will measure the overall cost of the project and the benefits that can be obtained from the successful completion of the project to define the required output to achieve success. |
Benchmarking |
Scope Creep |
The scope creep is one of the most common phenomenons in a project where there is deviation of output from the original output. The project manager will have to set a baseline for each of the tasks and this can be considered as benchmarking of the tasks in the project. This will ensure that the project team can monitor and control the project requirement without any complexity. |
Conclusion
The project management plan that has been developed cannot be effectively executed without the guidance of the project manager. The project manager will be able to make changes to the tasks and identify whether the tasks are critical and non critical. The understanding of the tasks will enable to manage the schedule effectively and make necessary changes based on the risk factors. Therefore, the importance of the project manager in revamping the cafe is extremely high and the stakeholders should consider this project charter before making their decision.
References
Bentley, C., 2015. The PRINCE2 Practitioner: From Practitioner to Professional. Routledge.
Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.
Chow, A.F., Woodford, K.C. and Lambe, N., 2014. Using project deliverables and project management for timely completion of student projects. Journal of Emerging Trends in Economics and Management Sciences, 5(3), p.323.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Frank, L.H., Koenig, P.R. and Srivastava, S., 2017. Connecting milestones to observable clinical performance through standardized pediatric cardiology rotation evaluations: Report and reflections on a novel pilot project. Progress in Pediatric Cardiology, 44, pp.11-15.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Klingebiel, R. and Rammer, C., 2014. Resource allocation strategy for innovation portfolio management. Strategic Management Journal, 35(2), pp.246-268.
Shiohama, R., Washizaki, H., Kuboaki, S., Sakamoto, K. and Fukazawa, Y., 2016. Investigating the relationship between project constraints and appropriate iteration length in agile development through simulations. International Journal of Computer Applications in Technology, 54(4), pp.311-322.
Buy CE6106-Project Management | Assignmenthelp Answers Online
Talk to our expert to get the help with CE6106-Project Management | Assignmenthelp Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.