Urgenthomework logo
UrgentHomeWork
Live chat

Loading..

7308ENG The Foundation Engineers

24 Download 📄 1 Pages / 134 Words

Foundation engineers are often challenged by the existence of soft compressible soils at the construction site. The a soil profile with a silty sand (?= 15 kN/m3; ?sat=17 kN/m3) underlain by high?plasticity clay (?sat=17 kN/m3) and a peat layer (?sat=16kN/m3), followed by dense sand. To expedite consolidation and minimize future settlement, an additional 2?m?thick fill material, compacted to a unit weight of 19 kN/m3, will be placed on top of the silty sand layer. The plan area of the fill is 10 m X 10 m. The fill load will be left in place for 2 years, after which construction will begin with the fill becoming part of the permanent foundation. Undisturbed samples collected from the clay and organic layers had the following properties: 


1. Estimate the total consolidation settlement under the action of the fill load. Consider both the clay and peat layers to be normally consolidated. 
2. Estimate the time for 99% primary consolidation in each layer. Are the layers singly or doubly drained? Explain. 
3. Estimate the secondary compression in each layer. 
4. What will be the total settlement after 2 years? 
5. Determine the effective stress at point A three months after the application of the fill load. 

Question 4: 
Calculate the settlement of the 3?m thick clay layer (see the following figure) that will result from the load (Q=4000 kg) by a 2?m square footing. The clay is normally consolidated. Using the weight average method to calculate the average increase of effective pressure in the clay layer. 
The weight average method is 

Question 5: 
The results of a standard proctor test are given in the following table. 
1. Determine the maximum dry unit weight of compaction and the optimum moisture content. Given: mold volume=953.3 cm3. 
2. Determine the void ratio and the degree of saturation at the optimum moisture content. Given: Gs=2.68.

Answer:

  1. Hydraulic conductivity

Kv =

Substitution of H = 600 mm, H1 = H2 = H3 = 200 mm K1 = 5 * 10-3, K2 = 4.2 *10-2 and K3 = 3.96 * 10-4

Determine the quantity of water flowing through the sample per hour.

Kv =

= 1.076 * 10-3 cm/sec

Quantity of water flowing through the sample

q = Kv*i*A

= Kv*i*

i is the hydraulic gradient, A = cross section area of soil

substitute 47/60 for I and d = 15 cm

q = 1.076 * 10-3 * 47/60 *

= 0.1489 cm3/sec

= 536.04 cm3/hr

The quantity of water flowing through the sample per hour = 536.04 cm3/hr

b)

Calculate when x = 0

Pressure head is zero, because above the datum line Y – Y there is no water pressure

The value of Z is -220 mm

Calculate the total head at entrance and exit of each layer using the equation

h =

Elevation head is Z, pressure head is

h = 0 + 470

= 470 mm

Therefore, the total head is 470 mm

Calculate when x = 200 mm

Pressure head is zero, because above the datum line Y – Y there is no water pressure

The value of Z is -220 mm

Calculate the total head at entrance and exit of each layer using the equation

h =

here, elevation head is Z, pressure head is

Equate the discharge velocities

Kv = K1 * i1

(1.076 * 10-3) * 47/60 = 0.005*

0.00084 = 2.5 * 10-5

h = 470 – 33.7

= 436.29 mm

Calculate the value of

 = 436.29 + 220

 656.29 mm

 the total head is 656.29 mm

Calculate when X = 400 mm

Pressure head is zero because the datum line Y – Y there is no water pressure

The value of Z is -220 mm

Equate the discharge velocities

Kv = K1 * i1

1.076 * 10-3 * 47/60 = 0.042 *

0.00084 = 2.1 * 10-5

h = 436.29 – 4

= 432.29 mm

Calculate the value of

 = 432.29 + 220

 652.29 mm

 the total head is 652.29 mm

Calculate when x = 600 mm

Pressure head is zero because the datum line Y – Y there is no water pressure

The value of Z is -220 mm

Equate the discharge velocities

Kv = K1 * i1

1.076 * 10-3 * 47/60 = 0.00039 *

0.00084 = 1.95 * 10-4

h = 436.29 – 432.24

= 0 mm

Calculate the value of

 = 0 + 220

 200 mm

d) discharge velocity = ki

k = hydraulic conductivity of the soil and I hydraulic gradient

k = 0.001076

v = 0.001076 * 47/60

= 0.000843 cm/sec

Calculation of the seepage velocity by using the equation

Vs = V/n

For soil I

V = 0.000843 and n = 0.5

Vs = 0.000843/0.5

= 0.00168 cm/sec

For soil II

V = 0.000843 and n = 0.6

Vs = 0.000843/0.6

= 0.0014 cm/sec

For soil III

V = 0.000843 and n = 0.33

Vs = 0.000843/0.33

e)

calculation of the height in A

height = (pressure head at X)200 mm

= 656.29 mm

Therefore, the height of water in A is 656.29 mm

Calculate the height of water in B

height = (pressure head at X)400 mm

= 652.29 mm

Therefore, the height of water in A is 652.29 mm

Q2)

The plane stress in XY plane, z = 0 and ZX = XZ =ZY =YZ = 0

Sum forces in the x1 direction

1*A*sec

Sum forces in the y1 direction

x1y1 *A*sec

xy = yx, simplified

1 = x*cos2+ y*sin2+ 2*xy*sin

x1y1 = -(xy) sin + xy(cos2

Using the trigonometric identities

sin

1 =

1face, substitution of

[2 + xy2

Cos2

Sin2

Substituting for R and rearranging

Larger principles

  1. Settlement of clay layer due to one dimensional consolidation

Sc-clay =

Cc compression index

0 is the effective overburden pressure

Bearing capacity of clay

q =

where

q = 19 * 2 = 38 kN/m2

calculation of m1

m1 = L/B

L = B = 10 m

m1 = 10/10 = 1

Calculation of value of b

b = B/2

B = 10 m

b = 10/2 = 5 m

consider a clay layer of different depths from fill load = z

let z = 4, 6, 8

for z = 4

n1 = z/b

b = 5m and z = 4

n1 = 4/5

 = 0.8

Tabulate the value for different z and calculate the increase in effective stress

m1

Z (m)

b = B/2


n1 = z/b

q

I4

1

4

5

0.8

38

0.8

30.4

1

6

5

1.2

38

0.606

23.02

1

8

5

1.6

38

0.449

17.06

0 = 2 * 15 + 2*17 + 4/2 *18 –[(2 +2) *9.81]

Calculate the settlement of clay layer due to one dimensional consolidation

e0 = 1.1, , Cc = 0.36

Sc-clay =

 =

= 0.096 m

Calculation of the settlement of peat layer

Sc-clay =

Cc compression index

0 is the effective overburden pressure

Bearing capacity of clay

q =

where

q = 19 * 2 = 38 kN/m2

calculation of m1

m1 = L/B

L = B = 10 m

m1 = 10/10 = 1

Calculation of value of b

b = B/2

B = 10 m

b = 10/2 = 5 m

consider a clay layer of different depths from fill load = z

let z = 8, 9, 10

for z = 8

n1 = z/b

b = 5m and z = 8

n1 = 8/5

 = 1.6

Tabulate the value for different z and calculate the increase in effective stress

m1

Z (m)

b = B/2

n1 = z/b

q

I4

1

8

5

1.6

38

0.449

17.06

1

9

5

1.8

38

0.388

14.74

1

10

5

2.0

38

0.336

12.76

 Calculate the settlement of peat layer due to one dimensional consolidation

e0 = 5.9, , Cc = 6.6, H = 2 m

Sc-clay =

 =

= 0.136 m

Sc = Sc-clay + Sc-peat

Sc = 0.096 + 0.136

= 0.232 m

Total consolidation settlement = 0.232 m

  1. b)

calculation of time for 99% primary consolidation using the formula

t99-clay =

Here,the maximum drainage path is Hdr,the time factor is T99, and the coefficient of consolidation is cv.

For the clay layer, a drainage condition is assumed since the top is silty sand which has a high permeability and the bottom is a peat layer has a high void ratio and considerable permeability.

For double drainage condition,

Hdr=

=2m

=200cm

For 99% degree of consolidation.

Variation of Tv with U. T99=1.781.

Substitute 200cm for Hdr. 1.781 for T99. And 0.003cm2/sec for Cv.

t99-peat=

23,746,666s*

=275 days

Hence,the time for 99% primary consolidation for clay is 275 days

Calculation of the time 99% primary consolidation

t99-clay =

for the peat layer assume a single drainage

Substitute 200cm for Hdr. 1.781 for T99. And 0.025 cm2/sec for Cv.

t99-peat=

2,849,600s*

=33 days

Hence,the time for 99% primary consolidation for clay is 33 days

Secondary compression in clay

Sc-clay = C’a*Hlog[t2/t1]

C’a secondary compression index , t1 = initial time, t2 = final time

primary = cC*log[

Cc = 0.36, 0 = 60.76 kN/m2,

primary =0.36*log[

= 0.36 *0.1407

= 0.0506

Computation of void ratio of clay

ep = e0 - primary

substitution e0 1.1, primary =0.0506

ep = 1.1 – 0.0506

= 1.049

Calculation of the primary compression index

C’a =

Ca = 003, ep = 1.049

C’a =

= 0.0146

Substitution of C’a = 0.0146, H = 4 m, t1 = 275 days , t2 = 365 day

Ss-clay = 0.0146 * 4*log[

= 0.0247

Computation of secondary compression in peat layer

Ss-peat = C’a*H*log[t2/t1]

C’a secondary compression index , t1 = initial time, t2 = final time

primary = cC*log[

Cc = 6.6, 0 = 83.33 kN/m2, , e0 = 5.9

primary =6.6*log[

= 6.6 *0.071

= 0.468

Computation of void ratio of clay

ep = e0 - primary

substitution e0 5.9, primary =0.468

ep = 5.9 – 0.468

= 5.432

Calculation of the primary compression index

C’a =

Ca = 0.263, ep = 5.432

C’a =

= 0.0408

Substitution of C’a = 0.0408, H = 2 m, t1 = 365 days , t2 = 33 day

Ss-clay = 0.0408 * 2*log[

= 0.109

d)

S = Sc + Sc-clay + Sc-peat

Sc = 0.232, Sc-clay = 0.0247 and Sc-peat = 0.109

S= 0.232 + 0.0247 + 0.109

= 0.365 m

  1. e) calculation of time factor in three months

Tv =

Time = t, Cv = coefficient of consolidation, Hdr = maximum drainage path

t = 3 months , Cv = 0.003 cm2/sec, , Hdr = 200 cm

Tv =

= 0.5832

Hdr = 4/2 = 2 m , since the c lay layer is a double drainage

= 200 cm

Calculation of degree of consolidation

Calculate the ratio of = z/Hdr

Hdr = 2 m, z = 3 m

z/Hdr = 3/2 = 1.5

Variation of Uz with Tv and z/Hdr

Uz = 0.85

Computation of excess pore water pressure at point A

uz = (1 – Uz)u0

 = (1 – 0.85)*23.25

= 0.15 * 23.25

= 3.4875 kN/m2

Calculate the increase in effective stress after 3 months

0 - uz

z = 3.4875 kN/m2 and u0 = 23.25 kN/m2

0 - uz

= 23.25 – 3.4875

= 19.76 kN/m2

Effective stress at point A on clay layer

0 = 2 *15 +2*17+3*18 – (2+3)9.81

Final effective stress after 3 month

0 = 0 +

0 = 68.95 kN/m2,

0 = 0 +

 = 68.95 + 19.76

= 88.71 kN/m2

Q4)

Q = 200 kips

10 ft = 3

100 pcf = 15.72

120 pcf = 18.87

110 pcf = 17.3

Z = from footing to centre of clay layer

= 2 + 3 +2 = 7 m

 = 484.44 N/m2

Settlement

Ss =

H = 3 m

Cc = 0.009(LL-10)

= 0.009(40 -10) = 0.27

e0 = 1.0

0 = [(15.72 *2) + (18.87*3)+(17.3*2)]-[9.81 * 4.5]

= 78.505 kN/m2

Ss =

=

= 2.164 *10-3 m

Q5)

Trial no.

Weight of moist soil in N

Moisture content (%)

1

16.48

9.9

2

16.78

10.6

3

17.36

12.1

4

17.95

13.8

5

18.25

15.1

6

18.44

17.4

7

18.34

19.4

8

18.15

21.2

Moist unit weight

Substituting = 16.48 * 10-3 kN for W and 953.3 *10-6 m3

29 kN/m3

Determination of dry unit weight = d =

= 15.73 kN/m3

Table of moist unit weight and dry unit weight values

V in cm3

Weight of moist soil in N

Moisture content (W) (%)

d in kN/m3

953.3

16.48

17.29

9.9

15.73

953.3

16.78

17.60

10.6

15.91

953.3

17.36

18.21

12.1

16.24

953.3

17.95

18.83

13.8

16.55

953.3

18.25

19.14

15.1

16.63

953.3

18.44

19.34

17.4

16.47

953.3

18.34

19.24

19.4

16.11

953.3

18.15

19.04

21.2

15.71

From the graph

The maximum dry unit weight = 16.64 kN/m3

Optimum moisture content = 15.0%

The void ratio € using the dry unit weight

s is the specific gravity of soil

16.64 =

1 + e = 1.58

e = 0.58

finding the degree of saturation (S)

Substitute 15.0% for W, Gs = 2.68, e = 0.58

S = *100

= 69.31%


Buy 7308ENG The Foundation Engineers Answers Online

Talk to our expert to get the help with 7308ENG The Foundation Engineers Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for 7308ENG The Foundation Engineers Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.