From the plans in Project 1, take off and extend the following quantities of materials/tasks:

  1. Bored excavation for 300mm diameter piers. (Hint: measure in lineal metres and refer to structural detail. To determine piers number, locate one at every corner/beam intersection, then space between these at 1800 max.)
  2. Bulk excavation to prepare site generally (but not the excavation for slab beams which is known as ‘detailed excavation’) Measure in m3 un-bulked. Allow to excavate 1m beyond the house walls for working space. Determine and state whether any excavated material will be required to be used as ‘fill’ and state the amount if fill needed.
  3. N25 concrete to the slab on ground (beams, patio slab and pad footings; but excluding piers as these are typically bored and pored immediately after bulk earthworks)
  4. SL72 reinforcing mesh to ground slabs. Measure the mesh twice:
    1. Nett measure in m2– (when costed, the $ rate per m2 will include an amount for wastage)
    2. The number of sheets required to complete the slab. Note: reinforcing mesh is sold in 6.0m x 2.4m sheets. 2 bar overlaps are typically required resulting in an effective cover of 5.8m x 2.2m with 400mm lap.
  5. The lengths of SL12TM required to complete the construction of the slab on ground. Note: trench mesh comes in 6m lengths. Measure in meters.
  6. The structural steel in tonnes. Measure to 2 decimal places.
  7. The plasterboard required to complete the lining of first floor rooms excluding the wet areas. Measure walls only. Measure the plasterboard twice:
    1. Nett measure in m2. The rate per m2will include a wastage factor.
    2. The number of sheets of plasterboard required to complete the lining of the rooms. Sheet sizes vary – use 1200mm wide sheets x standard lengths, with a horizontal layout.
  8. 66 x 18mm finished DAR primed pine skirting to the first floor rooms. (Hint: measure the skirting considering lengths available to purchase.)
  9. Ceramic floor tiles to the following ground floor rooms:
  • Meals room
  • Kitchen – allow tile to go under the cupboards
  • Foyer/stair area

Answer:

Particulars

Unit

Quantity

SITE PREPARATION AND EARTH


WORKS

Bored excavation

  

Bored excavation for 300 mm diameter piers with a spacing of maximum of 1800 excavation and casting of 40 piers number

m

120

Remove lose material and pumping of water from the base (optional)

m3

 7

Item 2

Excavations

Excavate to formation levels in final trimming and levelling: commencing from stripped levels; not exceeding 1.5 meters deep

m3

377.02935

Use of excavated material below 1 m for backfilling with proper compaction

m3

125.68

Disposal of the excavated materials from the site location

m3

251.3

Ditto 1.5 m but not exceeding 3m

m3

174.77

Ditto 3.0 m but not exceeding 4.5m (provisional)

m3

174.77

Excavate trenches for wall foundations: commencing from reduced level: not exceeding 1.5 metres deep

m3

180.5

Excavate pits for column bases : commencing from reduced level : not exceeding 1.5 metres deep

m3

98.75

Casting of concrete N25

  

Stepped foundations

m3

33.20

Columns

m3

50.23

Ground floor slab

m3

26.22

Provision of SL72 reinforcing mesh to ground floor and placing it

  

Double wire mesh provisions and placement plus wastage

M2

360.00

Procurement of sheets for the slab cover

No.

30

Provision of the trench mesh SL12TM for the slab construction at different sections

m

125

Structural steel for the structural concreting

  

Steel for the column

T

382

Steel for the beam

T

408

Slab steel

T

295

Provision and placement of the plasterboard for the lining of the first floor rooms

  

Provision of the double plasterboard on the lining of the walls on first floor

M2

195

Provision of the standard plasterboard sheet at required number

No.

32

primed pine skirting to the first floor rooms

  

Provision of the DAR primed pine skirting to the first floor rooms

M2

190

Primed pine skirting to the first floor rooms

  

Family room ceramic tile tiling

M2

32.75

Tiling of the meal room using ceramic tiles

M2

42

Tiling of the kitchen

M2

24

Tiling of the stair case area

M2

22

FITTINGS

  

High and low level kitchen cupboards : comprising 50 x 30mm wrot camphor frames : 50 x 25mm sawn cypress bearers plugged and screwed : 25mm blockboard doors, shelves, partitions: hardwood lipped on all exposed edges ; all exposed blockboard surfaces faced with mahogany veneer : 100mm brass D-handles, brass piano hinges : and magnetic ball catches to each door : prepare and apply three coats matt polyurethane clear finish to all exposed surfaces unless otherwise stated : (concrete benching measured separately) (as Architects drawing)

  

Low-level kitchen cupboard and worktop unit (overall) size 2100mm long x 600mm wide x 750mm high: comprising one full length shelf : 4No doors in 50 x 50mm frames : 100mm blockwall sides and divisions at 900mm centres : 75mm concrete (class 20/20) top with one layer A98 fabric mesh : formwork ; and polished ceramic tile finish to top and edge

No.

2

WARDROBES AND CUPBOARDS

  

Unit (overall) size 1500mm wide x 600mm wide x 2700mm high : one full height division : one full length shelf : 4No drawers size 450mm wide x 485mm deep x 100mm high : 3No high level cupboard doors and 3No wardrobe doors: 2 No 25mm diameter chromium plated hanging rails 900mm long with brass cup end fixing brackets ; 2no shoe racks 500mm long

No.

3

Ditto (overall) size 2000mm wide x 600mm deep x 2700mm high ; 4No high level and 4No wardrobe doors : 4No drawers size 960mm wide x 435mm deep x 100mm high ; 2No 960mm long 20mm diameter hanging rails with timber end fixing brackets : 2No shoe racks 960mm long

No.

2

Ditto (overall size 330mm wide x 600mm deep x 2700mm high : 4No wardrobe doors and 6No high level doors : ditto but 1200mm wide x 600mm deep reading top (ms)

No.

1

FLOOR FINISHES

  

Cement and sand (1:4) trowelled beds : on concrete : to

  

32mm Floors : finished to receive ceramic tile flooring

m2

80

38mm Floors : finished to receive PVC floor tiles

m2

150


Buy CPCCBC4004A Identify and Produce Estimated Costs Construction-The Stru Answers Online

Talk to our expert to get the help with CPCCBC4004A Identify and Produce Estimated Costs Construction-The Stru Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for CPCCBC4004A Identify and Produce Estimated Costs Construction-The Stru Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.