SIM335 Managing Projects
What problems do you have and what is being done to correct them.
What problems do you anticipate in the future.
Do you need any resources you do not have yet.
Do you need information you do not have yet.
Do you know anything that will give you schedule difficulties.
Any possibility your task will finish early or late.
Will your task be completed under / over / on budget.
Answer:
1) Define the key characteristics of any project.
The key characteristics of the project include the factors that are supportive for the implication of the effective system development operations. The key characteristic factors for the project are,
Exclusive requirements: The requirements of the project are exclusive and it is completely different for each of the project. It is possible that the some of the project activities might be same with other projects. However, most of the requirements are unique for each of the projects.
Client Based: The project activities are aligned with the demands of the project client and it is possible that the project can utilize the alignment of the specific requirements of the client. The client’s final approval is required for the successful completion of the project. Hence, aligning the project based on client’s demand is the primary requirement for the project.
Profit Dependent: The value of the project activities are aligned with value based outcomes in terms of profit acquisition. The integration alignment of project activities would align with the deployment of the effective profit generation for the project investors.
2) What is the Scope Statement for a project? What role does the Work Breakdown Structure (WBS) have in such a statement?
The specific and detailed description of the project deliverables is pointed out in the short scope statement for ensuring that the project objectives are explained clearly. The consideration of the activities would support the simplification of the activities that are capable of integrating the project objectives. The scope statement would help in understanding the success criteria for the project.
Work breakdown structure is the listing of the works required in the project for developing the project activities. The project activities can be summarized into some specific class or work package that would be required for the completion of the project. The work packages would combine for listing the alignment of the specific work development for the project and it is termed as work breakdown structure. The work breakdown structure of the project would support the completion of the project activities. The specific objectives of the project would combine with the alignment of the work packages developed.
3) Using the information below, plot out a full project Gantt chart and identify the critical path. How many days does it ta
ke to complete the project?
The project Gantt chart is given below,
The critical tasks of the project are aàbàdàf and it is shown below,
The project would exhaust a sum total of 19 days for the completion of the project. The project duration summary is given below,
Task |
Duration |
a |
5 |
b |
4 |
d |
3 |
f |
7 |
Total |
19 |
4) What approaches exist to generate a budget for a specific project budget?
The project budget estimation can be achieved using the bottom up approach as it would involve the consideration of the effective documentation forming the alignment of the effective process integration. The budget for the project would be developed using the following steps,
Step 1 |
Calculating the direct cost labour for the project |
Step 2 |
Cost of materials is evaluated and estimated for the project |
Step 3 |
Cost Expense for the transportation is evaluated for the completion of the project |
Step 4 |
Salaries of human resources that would be involved in the project would be calculated |
Step 5 |
Cost expended on the equipments and the software would be considered |
Step 6 |
All cost would be summed for calculating the total expenses of the project |
Step 7 |
An infringement of +10% would be added for developing the total budget for the project |
5) How can project risk arise? Outline the various responses to risk that may be taken within project management.
The project risk can result in forming the alignment of the major issues that would result in forming the problems for the project execution. The implication of the risk analysis would help in sorting out the major problems that the project might face due to the execution of the project activities. The project risk analysis would include the process of identifying the risk, evaluate its impact areas, and develop mitigation strategies for the execution of the project successfully.
Causes of risk |
Risk response plan |
Risk factors can be accidental or deliberate depending upon the causes of the risk. The various causes of the risk include lack of documentation, absence of the resources, lack of proper documentation, unskilled workers, and communication noises, inaccurate estimation, and poor development. |
The response plan for the risk factors would include the development of the risk mitigation planning and it is started with the identification of the risk factors. The impact analysis for the risk would be done for understanding the root causes for the project. The mitigation strategies would be developed for dealing with the issues of the risk factors. |
6) What quality methods (project evaluation, monitoring and control) would you introduce to ensure a project is completed successfully?
The project evaluation, monitoring and control would be deployed in the project for easing the processes of the improved communication and deployment. The following methods would be deployed in the project for ensuring the completion of the project,
Project Evaluation is developed for keeping whether the activities of the project would be completed in the estimated time and budget. The analysis of the project activities would support the implication of the proper documentation and the completion of the project
Monitoring and Control is deployed for making the required modification in the completion of the effective project execution and deployment. The controlling of the project activities would align with the successive formation of the operations.
Task 2
Introduction and Background
The report would be developed for the analysis of the activities and aligning the utilization of the operations for supporting the implication of the improved functional development. The project report would be deployed for easing the processes of forming the utilization of the project management principles. The effective use of the project management principles would be helpful for easing the merger of ABC, PLC, and DEF Ltd. The report would involve the utilization of the techniques of project lifecycle analysis, project management, planning, cost management, quality management, resource management, scope management, and controlling for the merger of the three organizations.
The project is merger acquisition based for the development of the effective support to the utilization of the improved communication and development. The project is titled Merger Acquisition Project for ABC, PLC, and DEF Ltd. The completion of the project would support the utilization of the improved activities. The alignment would be helpful for the execution of the improved communication and implication of the project management concepts for the project. The completion of the merger would help the three organizations for supporting and developing their specific factors for including the saint factors that would support the merger of the two companies.
1. Project Management Approach
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd has been completed using the agile development methodology and hence specific sprints are included in project. Each of the sprints would comprise of developing the project activities while supporting the inclusion of a specific deliverable and a milestone for the project. The five sprints of the project are initialization, structuring the merged principles, inventory development, planning, and execution of activities. The use of the agile methodology would help in easing the project execution and the development of the effective implication development.
2. Project Scope
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd is a merger acquisition project and it involves the following points,
- Formation of the structure supporting the operations of the three organizations in an integrated organizational structure
- Forming the inventory that would support the information processing for the organizations
- Developing communication process, integration plan, and initiating the staff retention activities
3. Milestone List
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd has been completed using the agile development methodology and hence specific sprints are included in project. Each of the sprints would comprise of developing the project activities while supporting the inclusion of a specific deliverable and a milestone for the project. The milestones represent the various initial and end points of a sprint for the project. The following are the milestones of the project,
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
Initialization |
11 days |
Tue 6/12/18 |
Tue 6/26/18 |
1.5 |
Project kick off |
0 days |
Tue 6/26/18 |
Tue 6/26/18 |
2 |
Structuring the merged principles |
13 days |
Wed 6/27/18 |
Fri 7/13/18 |
2.5 |
Structuring completed |
0 days |
Fri 7/13/18 |
Fri 7/13/18 |
3 |
Inventory Development |
13 days |
Mon 7/16/18 |
Wed 8/1/18 |
3.5 |
Inventory Integration |
0 days |
Wed 8/1/18 |
Wed 8/1/18 |
4 |
Planning |
20 days |
Thu 8/2/18 |
Wed 8/29/18 |
4.6 |
Approval of plans |
0 days |
Wed 8/29/18 |
Wed 8/29/18 |
5 |
Execution of Activities |
49 days |
Thu 8/30/18 |
Tue 11/6/18 |
5.5 |
Closure |
0 days |
Tue 11/6/18 |
Tue 11/6/18 |
4. Project Schedule and Work Breakdown Structure
The schedule for the project of Merger Acquisition Project for ABC, PLC, and DEF Ltd is given below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Merger Acquisition Project for ABC, PLC, and DEF Ltd. |
106 days |
Tue 6/12/18 |
Tue 11/6/18 |
1 |
Initialization |
11 days |
Tue 6/12/18 |
Tue 6/26/18 |
1.1 |
Requirement Analysis |
3 days |
Tue 6/12/18 |
Thu 6/14/18 |
1.2 |
Development of documents |
5 days |
Fri 6/15/18 |
Thu 6/21/18 |
1.3 |
Defining the objectives |
2 days |
Fri 6/22/18 |
Mon 6/25/18 |
1.4 |
Signing off the documents |
1 day |
Tue 6/26/18 |
Tue 6/26/18 |
1.5 |
Project kick off |
0 days |
Tue 6/26/18 |
Tue 6/26/18 |
2 |
Structuring the merged principles |
13 days |
Wed 6/27/18 |
Fri 7/13/18 |
2.1 |
Guidelines are developed |
3 days |
Wed 6/27/18 |
Fri 6/29/18 |
2.2 |
Merger Structure is developed |
4 days |
Mon 7/2/18 |
Thu 7/5/18 |
2.3 |
Expanding the culture |
3 days |
Fri 7/6/18 |
Tue 7/10/18 |
2.4 |
Business, Operations, and System analysis |
3 days |
Wed 7/11/18 |
Fri 7/13/18 |
2.5 |
Structuring completed |
0 days |
Fri 7/13/18 |
Fri 7/13/18 |
3 |
Inventory Development |
13 days |
Mon 7/16/18 |
Wed 8/1/18 |
3.1 |
Pre Closure data backup |
3 days |
Mon 7/16/18 |
Wed 7/18/18 |
3.2 |
Strategic meetings |
5 days |
Thu 7/19/18 |
Wed 7/25/18 |
3.3 |
Support Plan development for tactical problems |
2 days |
Thu 7/26/18 |
Fri 7/27/18 |
3.4 |
Governance and Strategy is integrated |
3 days |
Mon 7/30/18 |
Wed 8/1/18 |
3.5 |
Inventory Integration |
0 days |
Wed 8/1/18 |
Wed 8/1/18 |
4 |
Planning |
20 days |
Thu 8/2/18 |
Wed 8/29/18 |
4.1 |
Activities are listed |
2 days |
Thu 8/2/18 |
Fri 8/3/18 |
4.2 |
Schedule is developed |
3 days |
Mon 8/6/18 |
Wed 8/8/18 |
4.3 |
Complete Plan is developed |
7 days |
Thu 8/9/18 |
Fri 8/17/18 |
4.4 |
Staff Retention plan |
4 days |
Mon 8/20/18 |
Thu 8/23/18 |
4.5 |
Integration Plan |
4 days |
Fri 8/24/18 |
Wed 8/29/18 |
4.6 |
Approval of plans |
0 days |
Wed 8/29/18 |
Wed 8/29/18 |
5 |
Execution of Activities |
49 days |
Thu 8/30/18 |
Tue 11/6/18 |
5.1 |
Planning the implementation |
2 days |
Thu 8/30/18 |
Fri 8/31/18 |
5.2 |
Executing the implementation process |
14 days |
Mon 9/3/18 |
Thu 9/20/18 |
5.3 |
Business, Operations, and System analysis |
30 days |
Fri 9/21/18 |
Thu 11/1/18 |
5.4 |
Documenting the lessons learnt |
3 days |
Fri 11/2/18 |
Tue 11/6/18 |
5.5 |
Closure |
0 days |
Tue 11/6/18 |
Tue 11/6/18 |
The following is the Gantt chart for the Merger Acquisition Project for ABC, PLC, and DEF Ltd project,
The following is the work breakdown structure for the project of Merger Acquisition Project for ABC, PLC, and DEF Ltd,
5. Project Lifecycle
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd has been completed using the agile development methodology and hence specific sprints are included in project. Each of the sprints would comprise of developing the project activities while supporting the inclusion of a specific deliverable and a milestone for the project. The five sprints of the project are initialization, structuring the merged principles, inventory development, planning, and execution of activities. These sprints have been explained below,
- The initialization comprises of requirement analysis, development of documents, defining the objectives, and signing off the documents. The deliverable for the sprint is initial documents and the milestone for the sprint is project kick off.
- The structuring the merged principles comprise of guidelines are developed, merger structure is developed, expanding the culture, and business, operations, and system analysis. The sprint has the deliverable for specific merger structure and the milestone of structuring completed.
- The inventory development comprise of pre closure data backup, strategic meetings, support plan development for tactical problems, governance and strategy is integrated, and inventory integration.
- The planning comprise of activities are listed, schedule is developed, complete plan is developed, staff retention plan, and integration plan. The various plans would act as the deliverable for the sprint and the approval of plans is the milestone.
- The execution of activities would comprise of planning the implementation, executing the implementation process, business, operations, and system analysis, documenting the lessons learnt, and closure.
6. Project Deliverables
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd has been completed using the agile development methodology and hence specific sprints are included in project. Each of the sprints would comprise of developing the project activities while supporting the inclusion of a specific deliverable and a milestone for the project. The deliverables for the project are initial documents, specific merger structure, pre closure data backup, various plans (project plan, staff retention plan, and integration plan), and final reports.
7. Resource Management Plan
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd would require a number of human resources like analyst, documenter, negotiator, acquisitor, database admin, executives, planner, hr manager, and staff.
Resource Name |
Activities Involved in |
Work |
Analyst |
Requirement Analysis |
24 hrs |
Defining the objectives |
16 hrs | |
Documenter |
Development of documents |
40 hrs |
Signing off the documents |
8 hrs | |
Documenting the lessons learnt |
24 hrs | |
Negotiator |
Guidelines are developed |
24 hrs |
Business, Operations, and System analysis |
24 hrs | |
Acquisitor |
Merger Structure is developed |
32 hrs |
Expanding the culture |
24 hrs | |
Support Plan development for tactical problems |
16 hrs | |
Database Admin |
Pre Closure data backup |
24 hrs |
Executives |
Strategic meetings |
40 hrs |
Governance and Strategy is integrated |
24 hrs | |
Planner |
Activities are listed |
16 hrs |
Schedule is developed |
24 hrs | |
Complete Plan is developed |
56 hrs | |
Integration Plan |
32 hrs | |
Planning the implementation |
16 hrs | |
HR Manager |
Staff Retention plan |
32 hrs |
Staff |
Executing the implementation process |
112 hrs |
Business, Operations, and System analysis |
240 hrs |
8. Cost Budget
The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd has the following project budget plan,
Resource Name |
Work |
Standard Rate |
Cost |
Analyst |
40 hrs |
£50.00/hr |
£2,000.00 |
Documenter |
72 hrs |
£70.00/hr |
£5,040.00 |
Negotiator |
48 hrs |
£90.00/hr |
£4,320.00 |
Acquisitor |
72 hrs |
£100.00/hr |
£7,200.00 |
Database Admin |
24 hrs |
£120.00/hr |
£2,880.00 |
Executives |
64 hrs |
£150.00/hr |
£9,600.00 |
Planner |
144 hrs |
£80.00/hr |
£11,520.00 |
HR Manager |
32 hrs |
£125.00/hr |
£4,000.00 |
Staff |
352 hrs |
£65.00/hr |
£22,880.00 |
9. Risk Management Plan
The risk management plan comprises of developing effective strategies for dealing with the probable risk factors. The risk management plan comprises of identifying the risk factors, analysing the impact of the risks, and developing the mitigation strategies. The Merger Acquisition Project for ABC, PLC, and DEF Ltd would have the following risk management plan,
Risk Identification |
Risk Analysis |
Risk Mitigation |
The identification of the risk is based on the consideration of the probable risk factors that would help in easing the processing of the project and identifying the possible issues that the organization might face in the due course for the completion of the project. |
The analysis of the risk factors would result in forming the major factor analysis for the project so that the implication of the probable risk would help them in supporting the utilization of the risk mitigation. The analysis would help in listing the probable reasons that would result in forming the problems for the execution of the project activities. |
The mitigation of the risk is initiated by forming some strategies convenient for the development of the support strategies for the execution of the project. The risk mitigation would help them in forming the effective listing of the operations. The risk mitigation is also helpful for easing the process of reducing the impact on the project activities. |
Conclusion
The report had been developed for the analysis of the activities and aligning the utilization of the operations for supporting the implication of the improved functional development. The effective use of the project management principles had been helpful for easing the merger of ABC, PLC, and DEF Ltd. The report had involve the utilization of the techniques of project lifecycle analysis, project management, planning, cost management, quality management, resource management, scope management, and controlling for the merger of the three organizations. The completion of the project had support the utilization of the improved activities. The alignment had been helpful for the execution of the improved communication and implication of the project management concepts for the project. The completion of the merger had help the three organizations for supporting and developing their specific factors for including the saint factors that had support the merger of the two companies. The five sprints of the project were initialization, structuring the merged principles, inventory development, planning, and execution of activities. The use of the agile methodology had help in easing the project execution and the development of the effective implication development. The deliverables for the project were initial documents, specific merger structure, pre closure data backup, various plans (project plan, staff retention plan, and integration plan), and final reports. The project of Merger Acquisition Project for ABC, PLC, and DEF Ltd had require a number of human resources like analyst, documenter, negotiator, acquisitor, database admin, executives, planner, HR manager, and staff.
References
Binder, J. 2016. Global project management: communication, collaboration and management across borders. Routledge.
Brioso, X. 2015. Integrating ISO 21500 guidance on project management, lean construction and PMBOK. Procedia Engineering, 123, 76-84.
Brooks, J., and King, N. 2014. Doing template analysis: evaluating an end of life care service. Sage Research Methods Cases.
Cascante, I. L., Martin, F. M., Zubizarreta, J. P. O., and Aranburu, M. S. 2016, June. Three Historic Stages in the Graphic Confection of Project Documentation. BIM: Meetings in the Third Phase of the XXI Century. In Congreso Internacional de Expresión Gráfica Arquitectónica (pp. 1089-1097). Springer, Cham.
Chaves, M. S., Araújo, C. D., Teixeira, L., Rosa, D., Júnior, I., and Nogueira, C. 2016. A new approach to managing Lessons Learned in PMBoK process groups: the Ballistic 2.0 Model. International Journal of Information Systems and Project Management, 4(1), 27-45.
Coppola, D., D'Ambrogio, A., and Gianni, D. 2016. Bringing Model-based Systems Engineering Capabilities to Project Management: an Application to PRINCE2. In CIISE (pp. 6-15).
Drouart, G., De Breuck, C., Vernet, J., Seymour, N., Lehnert, M., Barthel, P., ... and Hatch, N. 2014. Rapidly growing black holes and host galaxies in the distant Universe from the Herschel Radio Galaxy Evolution Project. Astronomy & Astrophysics, 566, A53.
Hines, E. E., and Landis, W. G. 2014. Regional risk assessment of the Puyallup River Watershed and the evaluation of low impact deployment in meeting management goals. Integrated environmental assessment and management, 10(2), 269-278.
Hussein, B. A., and Ravnå, R. 2015, September. A template for building adaptable project risk management games. In Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS), 2015 IEEE 8th International Conference on (Vol. 2, pp. 535-542). IEEE.
Jamali, G., and Oveisi, M. 2016. A Study on Project Management Based on PMBOK and PRINCE2. Modern Applied Science, 10(6), 142.
Karaman, E., and Kurt, M. 2015. Comparison of project management methodologies: prince 2 versus PMBOK for it projects. Int. Journal of Applied Sciences and Engineering Research, 4(5), 657-664.
Kerzner, H., and Kerzner, H. R. 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E.W., Gray, C.F. and Irwin, M.H., 2016. University of Missouri–St. Louis…………………. Syllabus LOGOM 6347... Project Management InfoSys 6847… Financial and Project Management Fall 2016 A Blended Offering.
Lientz, B., and Rea, K. 2016. Breakthrough technology project management. Routledge.
Luo, Y., Melillo, J., Niu, S., Beier, C., Clark, J.S., Classen, A.T., Davidson, E., Dukes, J.S., Evans, R.D., Field, C.B. and Czimczik, C.I., 2011. Coordinated approaches to quantify long?term ecosystem dynamics in response to global change. Global Change Biology, 17(2), pp.843-854.
Maylor, H., 2001. Beyond the Gantt chart:: Project management moving on. European Management Journal, 19(1), pp.92-100.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Nicholas, J.M., 2004. Project management for business and engineering: Principles and practice. Elsevier.
Oya, T., Mehdad, Y., Carenini, G., and Ng, R. 2014. A template-based abstractive meeting summarization: Leveraging summary and source text relationships. In Proceedings of the 8th International Natural Language Generation Conference (INLG) (pp. 45-53).
Pinto, J., 2010. Achieving Competitive Advantage. Prentice-Hall, Upper Saddle River, NJ.
Rekker, S. 2016. Converting planetary boundaries into action, a new approach to meeting global greenhouse gas targets: A pitch. Accounting and Management Information Systems, 15(1), 160-167.
Rybka, I., Bondar-Nowakowska, E., and Po?o?ski, M. 2015. Management of Alterations to Project Documentation–a Case Study of Water Supply and Sewerage Works. International Journal of Contemporary Management, 2015Numer 14 ((3)), 41-57.
Schwalbe, K. 2015. Information technology project management. Cengage Learning.
Snyder, C. S. 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Snyder, C., and Dionisio, C. S. 2017. A project manager's book of forms: A companion to the PMBOK guide. John Wiley & Sons.
Spikol, D., Ehrenberg, N., Cuartielles, D., and Zbick, J. 2015. Design Strategies for developing a Visual Platform for Physical Computing with Mobile Tools for Project Documentation and Reflection.
Buy SIM335 Managing Projects Answers Online
Talk to our expert to get the help with SIM335 Managing Projects Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.