The paper mainly focuses on the organization “Greensafe” which is one of the consulting, auditing, training and outsourcing organization that is mainly dedicated to provide proper workplace safety and health, environment and quality services to different industries and workplaces. Organization mainly assists the clients in the implementation, development and in the maintenance of environment, quality and health and safety management system. The main mission of the organization is to provide proper health and safety, quality and environment solutions by designing and delivering number of innovative programs with the service and cost advantage. The organization is approved by the Ministry of manpower as an accredited provider of training and workplace safety and health auditing organization. 

Planned project timing plan

WBS

Task Name

Duration

Start

Finish

0

Review of Health & Safety Policies

61 days

Thu 04-05-17

Thu 27-07-17

1

   Identifying the need

6 days

Thu 04-05-17

Thu 11-05-17

1.1

       Reasons for reviewing the health and safety policy

1 day

Thu 04-05-17

Thu 04-05-17

1.2

       Analyzing the team members who are needed for the project

2 days

Fri 05-05-17

Mon 08-05-17

1.3

      Estimating the budget for the project

2 days

Tue 09-05-17

Wed 10-05-17

1.4

      Appointing project team members

1 day

Thu 11-05-17

Thu 11-05-17

2

   Preliminary work  (Collection of data and statistics)

47 days

Fri 12-05-17

Mon 17-07-17

2.2

      Examining whether the health and policy reflects organizations plans and targets

2 days

Mon 15-05-17

Tue 16-05-17

2.3

      Examining health and system is effectively reporting to the board

3 days

Wed 17-05-17

Fri 19-05-17

2.4

       Reporting health and safety shortcomings

2 days

Mon 22-05-17

Tue 23-05-17

2.5

      Identification of the policies used by the company

4 days

Wed 24-05-17

Mon 29-05-17

2.6

      Identifying main regulations of health and safety

3 days

Tue 30-05-17

Thu 01-06-17

2.7

       All policies and procedures related with health and safety must be properly reviewed

3 days

Fri 02-06-17

Tue 06-06-17

2.8

      Management of health and safety work regulation review

4 days

Wed 07-06-17

Mon 12-06-17

2.9

      Review of policy against the relevant workplace regulations

5 days

Tue 13-06-17

Mon 19-06-17

2.10

     Review of policy against the industry practices

3 days

Tue 20-06-17

Thu 22-06-17

2.11

      Collation of inputs

2 days

Fri 23-06-17

Mon 26-06-17

2.12

      Circulate to the employees for their suggestions

3 days

Tue 27-06-17

Thu 29-06-17

2.13

Finalize the inputs

4 days

Fri 30-06-17

Wed 05-07-17

2.14

Table to management for approval

3 days

Thu 06-07-17

Mon 10-07-17

3

Document and circulate the Policy

7 days

Tue 18-07-17

Wed 26-07-17

3.1

       Brief to the employees

2 days

Tue 18-07-17

Wed 19-07-17

3.2

Display on the prominent locations

2 days

Thu 20-07-17

Fri 21-07-17

3.3

      Post project review

3 days

Mon 24-07-17

Wed 26-07-17

4

   Project closure

1 day

Thu 27-07-17

Thu 27-07-17

 

Analysis and description of process

The main aim of the module is to exercise my capability for meeting the learning outcomes while reviewing the health and safety policies for knowing how the organization “Greensafe” is able to provide health and safety services for the different industries and organizations. It is found that the planned time that is mainly allocated for delivering the project is around 61 days.

The main purpose of this entire study is to review the health and safety policies that is followed for maintaining proper health condition within the employees of the organization. This generally include providing strategies that the organization utilizes in context to health and safety for providing proper solutions by designing and delivering proper innovative programmes with proper cost and service advantage. The evidence that is gathered after the analysis generally suggests the organization utilizes number of health and safety regulations and policies so that the employees of the organizations does not have to face any type of issues and challenges related to health and safety. Some of the regulations that are generally utilized by the organizations include management of health and safety work regulations, and more. All this regulation and policies are utilized by the organization so that they can be capable of providing consultation, training and can audit the health and safety services of different other organizations.

It is quite necessary for me to understand how the analysis is generally performed by the team members and what type of information are generally provided to them. This generally include meeting with the human resource of the department to know about the aims and objectives of the project including the resources that is allocated for reviewing the health and safety policies of the organization. I also require information that is mainly associated with understanding the requirement of information and training to the organizational staff at the induction stage. It is found that this type of findings generally helps in allowing me to understand the competency that is associated with the managers and team installation that further can create effect on the attitudes of the employees towards the adoption of health and safety regulations while involving with the project.

It is identified that for delivering and facilitating the entire project effectively, it is quite necessary to understand the requirements of the project quite properly.  In addition to this, I utilized techniques like communication, co-operation and co-ordination for assisting various types of processes and activities. It is found that this type of techniques generally helps in enabling me to analyze the weaknesses and strengths in controlling the health and safety related issues so that appropriate principles of prevention and hierarchy of control is generally utilized for ensuring proper health and safety for the persons who are generally affected due to the activities of the site as per the health and safety act at work.

Discussion that generally surrounds product of value realized by the work

The findings from both written procedures, systems and on-site observation generally suggests both weaknesses and strengths for managing the health and safety within the entire organization.

It is found that the review that is associated with analyzing the utilization of health and safety policies by the organization generally helps in eliminating and reducing the site hazards that is related to working at height in context to identification of risks that generally arises from various unprotected edge to carry out proper roof work. It is found that this type of activities had previously carried out the utilization of a ladder. It is found that depending on the needs and requirements of the safety and health regulations we select appropriate steps to avoid the risks and challenges that is mainly associated with health and safety risks.

It is identified that the review also helps in identifying number of failures for complying with the act that can be helpful in resolving the issues and challenges that are associated with health and safety policies. It is found that the reviews are quite helpful in managing and planning health and work-related policies to give opportunity so that the approved code of practice can act as a guide to control the risks to create proper training programme so that the employees of the organization can be made aware about the measures that needs to be taken to avoid health and safety risks on the site.

According to my view, the most significant value of the product must be realized by the management for highlighting the lack of awareness in context to operatives so that the risks that are associated with the activities and processes due to lack of information, instruction and training. It is found that the findings from the site observation suggests that if the management fails to allocate proper amount of time and resources to implement training and information of the staff. In addition to this, the review is quite helpful in adding value to the staffs with appropriate instruction, training and information. This type of improvements that generally assists in protecting the health and safety of the workers generally helps in preventing challenges

Meeting the learning outcomes

 Learning outcome 1: Synthesise and demonstrate skills and competencies required for successful integrated management

It is identified that in this project, integrated management concept is mainly utilized. An integrated management generally helps in integrating the systems and procedures within one complete framework to enable Greensafe to work successfully on the unified objectives so that health and safety policies are successfully reviewed.  It is identified that a quality team is mainly concerned with QMs so that both environmental as well as health and safety issues related with the organization can easily be mitigated. The organization focusses on quality management system, environmental management system and safety management system. Proper communication as well as negotiation is generally considered to make the entire project successful.

Proper communication is used by the team members to discuss about the needs as well as demands of the project so that the goals and objectives can be successfully achieved. Appropriate negotiation is utilized by the project team members to settle the differences within the project. It is identified that to synthesise as well as demonstrate skills and competencies it is very much necessary to select proper project team members. Project team members must hire as per the skills and experience so that the policies related with health and safety can be successfully achieved. To make the project successful, the higher authorities of the organization are consulted so that they can be able to provide proper information about the policies and procedures that are associated with health and safety.

Learning outcome 2: - Displays resourcefulness and initiative in tackling a variety of practical tasks in an occupational setting

The second learning outcomes helps in displaying the resourcefulness and tackles number of practical tasks to make the project successful. It is identified that by tackling number of varieties of tasks within the project, the project manager can finish the entire project within the expected budget and time. It is found that appropriate resourcefulness assists in utilizing the needed resources properly for reviewing the policies that are associated with health and safety. It is identified that the project managers utilize both material as well as human resources to finish the entire project successfully.

The resources that are utilized in the project are appropriate or not is generally analyzed by tracking the utilization of resources within the project on a regular basis. The problems as well as risks that are mainly associated with the project can be resolving by introducing number of strategies as well as steps that are helpful. It is found that for managing the project effectively, the project manager needs to tackle the risks and challenges that are associated with the project. The risks and challenges can be resolved by creating proper risk register, by determining impact and likelihood and by estimating the risks and challenges.


Learning outcome 3: Examine the critical practical concerns that arise in carrying out a project within the workplace and synthesise the constraints that exist within such frameworks

The risks that are associated with the project including inappropriate time estimation, lack of resources, lack of budget as well as absence of experienced project team members for finishing the project can be successfully resolved by implementing proper strategies. It is identified that absence of proper employees and staffs within the project generally obstructs the project and generally creates lots of issues and concerns in completing the entire project successfully within the expected time.  It is found that the impact of the risks is higher on the project and thus the project manager wants to   manage the risks by analyzing the utilization of project budget and resources on a weekly basis for making sure that the project is on the right track. It is found that both employees and staff availability is analyzed for reviewing the safety  and health policies of the organization effectively.

It is found that in the absence of staffs the project managers influence as well as motivates the team members to work extra for finishing the project. In addition to this, the problem or issues due to staff availability can be avoided by estimating the resources that is needed for the project. It is found that absence of proper customer-supplier relationship and absence of project finance generally creates lot of issues and challenges in executing the project within the expected time that is mainly assumed during the initial stage of the project. The problem can be resolved by tracking the budget that is utilized by the project manager on a weekly basis.

Learning outcome 4: Critically apply knowledge about the practical application and synthesise the different abilities required to implement the chosen client-based tasks

The paper utilizes proper training and skills requirements development for the team members so that they can be able to review the health and safety policies effectively. Training and skill development is needed within the team members of the project so that they can able to get involved successfully with the project for finishing the project within the expected time and budget. The project team members are hired without appropriate skills and thus proper training and skill development within the project is necessary. In addition to this the client descriptor project focuses on proper legislative and statutory considerations during the review of health and safety rules so that none of the rules get violated. As the organization utilizes appropriate rules for maintaining the health and safety of the employees therefore the steps that are taken within the project must not violates that rules and regulations. In addition to this, it is identified that application of the company culture to identify the work and health regulations and laws that are generally helpful to avoid the problems and challenges that are mainly associated with health and safety of the organizational employees. The organization “Fuor Australia Pty Ltd.” Is one of the organization whom Greensafe helps in following the health and safety culture within the organization.

Self-assessment in relation to the overall success of the work

The key for the project success is basically dependent on the entire training package and on the delivery to the site personnel.

The study generally resulted in minimizing the chances of accidents and incidents that can be helpful in creating proper culture within the organizations with the help of appropriate communication, co-operation, consultation and involvement. My main objective is basically dependent on the utilization of aims and objectives that generally assists in driving the entire workforce for believing the end goal of the entire project. After reflecting on the organizational failures, it is quite important to understand the significance of the workforce that are involved within the project. It is very much necessary to analyze the services that is provided by Greensafe so that proper health and safety regulations will be utilized by the organizations for avoiding any type of risks and challenges.

Self-assessment in relation to performance to each learning outcome

It is identified that the self-assessment that is created in relation to performance is totally based on Gibb’s reflective model.  It is identified that Gibbs reflective cycle is one of the model that is mainly utilized in this project as one of the framework in coursework assignment that mainly needs appropriate reflective writing. The project generally needs integrated skills of management for successfully delivering the project within the time that is generally expected. It is found that as discussed within the project descriptor for achieving the aims and objectives, it is very much necessary to manage, plan and monitor the various activities of the site however when I refer on the review of health and safety policies, I found that leadership is the main concept towards the success of the project.

 It is found that utilization of proper principles generally acted as a guide for enabling me to consider the various types of failures that are related with the management. This information is very much helpful in changing the attitudes, behaviours that generally leads to engagement, empowerment and motivation among the workforce of the organization for achieving the goals and objectives. The health and safety of the organizations are mainly driven with the help of the project managers who generally failed to engage successfully within the project that generally leads to poor morale of the entire project. The information that needs to be utilized for improving the attitudes and behaviour generally leads to empower, engage and motivate the entire workforce to understand  and analyze the objectives of the project.


Buy Project- Safety & Health Policy review of Greensafe – Free Samples Answers Online

Talk to our expert to get the help with Project- Safety & Health Policy review of Greensafe – Free Samples Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Project- Safety & Health Policy review of Greensafe – Free Samples Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.