MNG00785 Project Management-Developing the Budget
Answer:
WBS |
Task Name |
0 |
Website development project for Social Media Research Centre |
1 |
Project Startup |
2 |
Initiation Phase |
2.1 |
Development of project charter |
2.2 |
Held meetings for project initiation |
2.3 |
Request approval of project charter |
M1 |
Approval of project charter |
4 |
Requirements Analysis Phase |
4.1 |
Gathering of requirements and analysis |
4.2 |
Development of document for requirements specification |
M2 |
Completion of requirements document development |
6 |
Review Phase |
6.1 |
Review project charter |
6.2 |
Review of identified requirements |
6.3 |
Prepare documentation of technical review |
M3 |
Completion of technical review |
8 |
Planning Phase |
8.1 |
Creation of WBS |
8.2 |
Development of schedule for project |
8.3 |
Allocation of resources |
8.4 |
Estimation of costs |
8.5 |
Analysis of stakeholders |
8.6 |
Development of test plan |
8.7 |
Prepare plan for risk management |
8.8 |
Prepare plan for change control |
M4 |
Completion of WBS, Schedule development and Cost estimation |
10 |
Design Phase |
10.1 |
Identification of requirements |
10.2 |
Draft layout of design overview |
10.3 |
Determining features of the website |
10.4 |
Identify coloring schema for design |
10.5 |
Determine the contents for website |
10.6 |
Prepare documentation for overall layout of the website |
M5 |
Completion of design layout |
12 |
Development Phase |
12.1 |
Analysis of functional requirements |
12.2 |
Designing of wireframes |
12.3 |
Development of modules |
12.4 |
Coding for modules |
12.5 |
Development of database |
M6 |
Completion of development |
14 |
Testing Phase |
14.1 |
Unit testing |
14.2 |
Integration testing |
14.3 |
System testing |
14.4 |
Usability testing |
M7 |
Completion of testing |
16 |
Go-live phase |
16.1 |
Hosting the website |
16.2 |
Launch of website |
17 |
Project Closeout |
3.2 Assumptions and constraints for developing the budget
The assumptions that have been considered in context to this project for website development of Social Media Research Centre are listed as below:
- The resources being allocated works for 5 days per week that is 40 hours per week on the day shift.
- The materials required for execution of project is readily available without incurring procurement cost overhead.
- Estimating the margin of error.
- Resources are distributed evenly in between the various activities.
- The overall cost associated daily activities will not increase.
- The economic conditions as an overall will remain the same.
The constraints being identified for budgeting of the project are presented as below:
- The allocated budget for this project is 50,000.00 AUD.
- The budget being allocated is for completion of the project within 07 months.
- 20% fringe has been added to the budget.
- The allocated resources will be available for entire duration of project.
3.5 Examples of known knowns and known unknowns on the project
The examples of known knowns on the project that have been identified are as below:
- Requirement of additional members in project team thus increasing direct labor costs.
- Extension of the project due to changes in scope resulting into increase in project cost.
- Sudden inflation in the price of hardware and software materials required for development of website.
The examples of known unknowns on the project that have been identified are as below:
- Allocation of additional resources during progress of the project will incur additional budget.
- Request for changes in project scope may increase the budget.
- The resource costs may increase with time during the project.
3.6 Budgeting for both and unknown unknowns
The budgeting for known knowns and known unknowns on the project to develop the website for Social Media Research Centre have been done with the help of bottom up estimation technique. This budget estimation technique is time consuming however it is also most accurate. It is also appropriate for high level estimates as per requirement described in project charter or project initiation phase. In this type of budget estimation technique, there is involvement of the entire project team as well as it offers with opportunity to participate in preparing the estimates for measuring the work and associated cost.
The budgeting for the unknown unknowns have been done by adding 20% for fringe that is 10,000.00 AUD have been kept reserved in terms of resolving the issues or risks that may occur in the project.
Risk Register
Risk ID |
Description and Cause |
Proximity |
Likelihood |
Consequence |
Level |
Treatment Response |
Treatment |
R01 |
Delay in approval of project charter |
Medium |
4.Likely |
4.Major |
High |
Reduce |
The project charter have to be distributed among the officials evenly and discussed with priority. |
R02 |
Over budgeting of the project |
High |
3.Possible |
4.Major |
High |
Avoid |
Budget should be estimated with appropriate techniques. |
R03 |
Changes in requirements and project scope |
Low |
2.Unlikely |
2.Minor |
Low |
Transfer |
Change requests have to be incorporated only after approval |
R04 |
Changes in blueprint design of website |
Medium |
2.Unlikely |
4.Major |
Medium |
Avoid |
Final design have to reviewed by the development team |
Quality Management Plan
5.1 Statement of team’s philosophy or objective
The project team focuses on developing the website according to the requirements of the users so that it fulfills the determined objectives. The quality of the website to be developed must have the functionalities as per request of the client. The objective of the project team is to deliver a standard quality website with achievement of the requirements of client. The project team will ensure a stable website is developed and enhancement in user experience.
5.2 Development and description of three quality issues
The three quality issues that have been identified in context to this project for development of the Social Media Research Centre project are as below:
- Not setting up the project with realistic budget – This is one of the major quality issues associated with this project as the inappropriate estimation of budget may lead to low quality of work.
- Improper design of the website – The website being developed is not user friendly as the design is complex also the look and feel is not aesthetic as it is not pleasing in context to view of users.
- Integration with database – The database connection fails in between the transaction by clients. The database developers will design the database with functionalities to reinstate it to previous state in case of failure or connection is lost.
Closure checklist and project evaluation
6.1 Development of Closure checklist
The closure checklist being developed for this project to develop the Social Media Research Centre website are as below:
ü The outstanding tasks outlined in the WBS have been completed |
ü The outstanding issues are documented and resolved |
ü The goals of project charter have been met |
ü Feedback has been achieved from stakeholders and documented |
ü Measures for success of project have been evaluated |
ü Evaluation have been done for project team and relieved from project |
ü Costs for project have been paid by client with settlement of outstanding dues |
ü Evaluation of post project have been completed |
6.2 Development of project evaluation
The evaluation of project’s MOV will be conducted with the help of following:
Areas |
Project’s MOV |
Client |
The website is user friendly and easy to use. |
Economical |
The traffic visiting the website increases to generate more revenue. |
Social |
The website offers users with social awareness. |
Connectivity |
The website allows various users to connect and share their views and opinions as well as reviewing others. |
Bibliography
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Konstantinou, E., & Müller, R. (2016). The role of philosophy in project management. Project Management Journal, 47(3), 3-11.
Leach, L. P. (2014). Critical chain project management. Artech House.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Turner, R. (2016). Gower handbook of project management. Routledge.
Buy MNG00785 Project Management-Developing the Budget Answers Online
Talk to our expert to get the help with MNG00785 Project Management-Developing the Budget Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.