Manu2123 Project Management Plan-Cost And Assessment Answers
Assignment
The assignment 2 for this Subject is based on the proposal (assignment 1) completed by the student. A student needs to develop a project management plan (project communication plan) for the project described in the assignment 1. The assignment is to be done individually by students. Assignment details are as follows:
Assignment Purpose and Objective
The aim of the assignment is to develop the Student’s understanding of Project Management Life Cycle through the evaluation of a case study Proposal. This assignment is based on concepts and principles from the lectures, class notes, syndicate exercises and reading references.
To meet the requirements of this assignment you as a Project Manager will need to write a project management plan and to address the following questions in relation to your selected project:
- Provide a 1 page Executive Summary, aimed at senior management, on the background of your project (assignment 1).
- Describe the project communication plan which captures details of all project communications including the schedule, the type of project control, reporting, project milestone, project environment.
- Describe communications strategy and approach (this section of the plan would describe the general strategy and approach to communications management with the project). (For instance in a community-based project you would describe what the general approach to communicating with the community would be).
- Discuss project reporting arrangements. Detail the project-reporting requirements, including status type reports that are to be generated by the project. It is common practice to include blank template reports as appendices to the Communication Management Plan.
- Describe briefly Committee, project meetings arrangements, Review process (this is very important for the formation external communications)
- Project management information system (PMIS). (this could range from corporate ICT systems to more specific project-related information systems, the security of access to these systems)
- Risk review (review any communication activities to carried out and identify risks, ensure they captured within the project risk register).
- Lessons learned (insure that a review of any lessons learned from prior similar projects is carried out and that any relevant lessons learned).
Answer:
Project Management Plan
The project management plan is developed for the project of Wireless LAN replacement at GV Health and the alignment of the successive integration of the operations. The project plan would be developed for forming the utilization of the information technology and development of effective implication of the operations. The deployment of the activities had also favoured the intrusion of the successive alignment of the operations favouring the alignment of the improved operation development. The project management plan would be developed for easing the implication of the improved operation development. The development of project management plan is helpful for forming the list of the activities favouring the operation development.
Introduction
Project Scope of Works
The project of Wireless LAN replacement at GV Health is developed for replacing the existing network structure with improved and better wireless network connection. The project is a network project and it would align with the deployment of the facilities favouring the utilization of the effective development of the operations. The project scope is the elements of the project that are being considered for the completion of the project. The implication of the activities would be aligned for the development of the activities favouring the successful integration of operations. The project includes deployment of the wireless network connection, project plan development, use of effective documentation process, and alignment of the effective system integration development.
Project Timeline
The project of Wireless LAN replacement at GV Health is being deployed for implementing the new wireless LAN network for GV health. The timeline is being considered for forming the deployment of the effective plan activities. The timeline of the project would be developed for listing the activities in a specified time schedule,
Project Assumptions
The project of Wireless LAN replacement at GV Health is developed for developing the final deliverable of changing the network connection in the organization with wireless LAN connection. The assumptions of the project were based on the implementation of the improved operation development. The assumptions of the project include,
- Use of network engineering process for the development of the WLAN network connection at GV Health
- Required resources of the project would be assembled easily in the project so that project can be completed in the required time
- Project would be completed in the estimated time duration with the help of IT project management
- Cost budget estimation in project can be done cohesively for aligning the deployment of the effective program development
- Activity development in projects can be achieved for aligning the utilization of the operations and successive deployment of the operations
Project Limitations
The project of Wireless LAN replacement at GV Health is developed for developing the final deliverable of changing the network connection in the organization with wireless LAN connection. The project is limited to the network replacement at GV Health, considering the IT and network management operations, and skills of the workers involved in the project. The project deployment would be aligned with the consideration of the effective utilization of the technology. However, the lack of prior knowledge would act as the major setback for the project. The implication of the activities would be limited by the infrastructure development.
Schedule (Time Management)
The project of Wireless LAN replacement at GV Health is developed for developing the final deliverable of changing the network connection in the organization with wireless LAN connection. The project schedule had been developed using the waterfall methodology and it includes the division of project in 5 phases of Initiation, Planning, Designing, Executing, and Closing. The schedule and time management list for the project is listed below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Wireless LAN replacement at GV Health |
74 days |
Mon 6/4/18 |
Thu 9/13/18 |
1 |
Initial Phase |
11 days |
Mon 6/4/18 |
Mon 6/18/18 |
1.1 |
Requirement Analysis |
2 days |
Mon 6/4/18 |
Tue 6/5/18 |
1.2 |
Development of Project Initiation Document |
4 days |
Wed 6/6/18 |
Mon 6/11/18 |
1.3 |
Development of Project Charter Document |
4 days |
Tue 6/12/18 |
Fri 6/15/18 |
1.4 |
Submission of documents |
1 day |
Mon 6/18/18 |
Mon 6/18/18 |
1.5 |
Project Kick off |
0 days |
Mon 6/18/18 |
Mon 6/18/18 |
2 |
Plan Phase |
9 days |
Tue 6/19/18 |
Fri 6/29/18 |
2.1 |
Activity Listing is done |
2 days |
Tue 6/19/18 |
Wed 6/20/18 |
2.2 |
Proper Scheduling of activities |
1 day |
Thu 6/21/18 |
Thu 6/21/18 |
2.3 |
Estimating the costs of the project |
3 days |
Fri 6/22/18 |
Tue 6/26/18 |
2.4 |
Making communication plan |
3 days |
Wed 6/27/18 |
Fri 6/29/18 |
2.5 |
Approval of the plan |
0 days |
Fri 6/29/18 |
Fri 6/29/18 |
3 |
Design Phase |
13 days |
Mon 7/2/18 |
Wed 7/18/18 |
3.1 |
Analysis of the WLAN replacement design |
2 days |
Mon 7/2/18 |
Tue 7/3/18 |
3.2 |
Development of Network topology |
2 days |
Wed 7/4/18 |
Thu 7/5/18 |
3.3 |
Identification of client, access points, routers, and gateways |
2 days |
Fri 7/6/18 |
Mon 7/9/18 |
3.4 |
Analysis of the network connections |
2 days |
Tue 7/10/18 |
Wed 7/11/18 |
3.5 |
Simulation of design |
5 days |
Thu 7/12/18 |
Wed 7/18/18 |
3.6 |
Approval of the design |
0 days |
Wed 7/18/18 |
Wed 7/18/18 |
4 |
Execution Phase |
36 days |
Thu 7/19/18 |
Thu 9/6/18 |
4.1 |
Calculation of network capacity |
2 days |
Thu 7/19/18 |
Fri 7/20/18 |
4.2 |
Setting network standards |
3 days |
Mon 7/23/18 |
Wed 7/25/18 |
4.3 |
Alignment of security functions |
4 days |
Thu 7/26/18 |
Tue 7/31/18 |
4.4 |
Network Design Implementation |
2 days |
Wed 8/1/18 |
Thu 8/2/18 |
4.5 |
Test Case Simulation |
2 days |
Fri 8/3/18 |
Mon 8/6/18 |
4.6 |
Network Migration is scheduled |
1 day |
Tue 8/7/18 |
Tue 8/7/18 |
4.7 |
Existing Network is taken down |
3 days |
Wed 8/8/18 |
Fri 8/10/18 |
4.8 |
Migration of network |
2 days |
Mon 8/13/18 |
Tue 8/14/18 |
4.9 |
Switches are replaced |
3 days |
Wed 8/15/18 |
Fri 8/17/18 |
4.10 |
Configuring VPN for network migration |
4 days |
Mon 8/20/18 |
Thu 8/23/18 |
4.11 |
Setting the new WLAN setup |
7 days |
Fri 8/24/18 |
Mon 9/3/18 |
4.12 |
Development of new network connection |
2 days |
Tue 9/4/18 |
Wed 9/5/18 |
4.13 |
Development of new network access for authentic users |
0 days |
Wed 9/5/18 |
Thu 9/6/18 |
5 |
Closure Phase |
5 days |
Fri 9/7/18 |
Thu 9/13/18 |
5.1 |
Final Reports are being made |
3 days |
Fri 9/7/18 |
Tue 9/11/18 |
5.2 |
Final Reports are submitted |
1 day |
Wed 9/12/18 |
Wed 9/12/18 |
5.3 |
Signing off the reports |
1 day |
Thu 9/13/18 |
Thu 9/13/18 |
5.4 |
Project Closure |
0 days |
Thu 9/13/18 |
Thu 9/13/18 |
Milestones
Project Review Process
The project review is based on the development of the wireless LAN connection at GV Health and it would align with the use of the specific testing methods. The analysis of the network connections would be done for the deployment of the operations aligning the utilization of the effective management of the operations. The project review process would be based on the development of the successive operation development and alignment of the operations favoring the completion of the project. The Simulation of design is done for ensuring that the improved communication is established. The utilization of the operations would also be helpful for the successful implication of the activities and alignment of the operations favoring the implication of the review process. The Setting network standards and Test Case Simulation are also helpful for the implication of the review process in projects.
Deliverables
The project is developed for the final deliverable of the wireless network connection at GV Health and it would result in forming the development of the successful project deliverable. The deliverables for the project are documents like project initiation document, project charter, and final reports. The communication plan and project plan are the deliverable project. The network topology, design simulation, security functions, test case execution, and a number of network development activities are the deliverable for the project. The configuring VPN for network migration, setting the new WLAN setup, development of new network connection, and development of new network access for authentic users are the technological deliverable for the project. The following table would show the deliverable item of the project along with expected time duration,
Deliverable |
Task Name |
Duration |
Start |
Finish |
D1 |
Development of Project Initiation Document |
4 days |
Wed 6/6/18 |
Mon 6/11/18 |
D2 |
Development of Project Charter Document |
4 days |
Tue 6/12/18 |
Fri 6/15/18 |
D3 |
Making communication plan |
3 days |
Wed 6/27/18 |
Fri 6/29/18 |
D4 |
Development of Network topology |
2 days |
Wed 7/4/18 |
Thu 7/5/18 |
D5 |
Simulation of design |
5 days |
Thu 7/12/18 |
Wed 7/18/18 |
D6 |
Alignment of security functions |
4 days |
Thu 7/26/18 |
Tue 7/31/18 |
D7 |
Test Case Simulation |
2 days |
Fri 8/3/18 |
Mon 8/6/18 |
D8 |
Switches are replaced |
3 days |
Wed 8/15/18 |
Fri 8/17/18 |
D9 |
Configuring VPN for network migration |
4 days |
Mon 8/20/18 |
Thu 8/23/18 |
D10 |
Setting the new WLAN setup |
7 days |
Fri 8/24/18 |
Mon 9/3/18 |
D11 |
Development of new network connection |
2 days |
Tue 9/4/18 |
Wed 9/5/18 |
D12 |
Development of new network access for authentic users |
1 day |
Thu 9/6/18 |
Thu 9/6/18 |
D13 |
Final Reports are submitted |
1 day |
Wed 9/12/18 |
Wed 9/12/18 |
Client Presentations
The presentation to the client would be based on the project charter developed as information sharing document helpful for the alignment of the activities supporting the utilization of the operations. The presentation to the client would be supported by the use of the effective alignment of the activities favouring the implication of the operations.
Cost and Budget Management
WBS |
Task Name |
Resource Names |
Cost |
1.1 |
Requirement Analysis |
Analyst |
$640.00 |
1.2 |
Development of Project Initiation Document |
Documenter |
$1,600.00 |
Documents[1] |
$50.00 | ||
1.3 |
Development of Project Charter Document |
Documenter |
$1,600.00 |
Documents[1] |
$50.00 | ||
1.4 |
Submission of documents |
Documenter |
$400.00 |
2.1 |
Activity Listing is done |
Planner |
$960.00 |
2.2 |
Proper Scheduling of activities |
Planner |
$480.00 |
2.3 |
Estimating the costs of the project |
Project Manager |
$2,400.00 |
2.4 |
Making communication plan |
Project Manager |
$2,400.00 |
3.1 |
Analysis of the WLAN replacement design |
Network Engineer |
$1,440.00 |
3.2 |
Development of Network topology |
Network Designer |
$1,280.00 |
Networking Tools[1] |
$1,000.00 | ||
3.3 |
Identification of client, access points, routers, and gateways |
Network Designer |
$1,280.00 |
3.4 |
Analysis of the network connections |
Network Designer |
$1,280.00 |
3.5 |
Simulation of design |
Network Engineer |
$3,600.00 |
Simulation Tools[1] |
$500.00 | ||
4.1 |
Calculation of network capacity |
Network Engineer |
$1,440.00 |
4.2 |
Setting network standards |
Network Engineer |
$2,160.00 |
4.3 |
Alignment of security functions |
IT Engineer |
$2,880.00 |
4.4 |
Network Design Implementation |
Network Designer |
$1,280.00 |
4.5 |
Test Case Simulation |
IT Engineer |
$1,440.00 |
4.6 |
Network Migration is scheduled |
Network Engineer |
$720.00 |
4.7 |
Existing Network is taken down |
Network Engineer |
$2,160.00 |
4.8 |
Migration of network |
IT Engineer |
$1,440.00 |
4.9 |
Switches are replaced |
IT Engineer |
$2,160.00 |
Switches[1] |
$1,130.00 | ||
4.1 |
Configuring VPN for network migration |
Network Engineer |
$2,880.00 |
4.11 |
Setting the new WLAN setup |
IT Engineer |
$5,040.00 |
Infrastructure Cost[1] |
$3,500.00 | ||
4.12 |
Development of new network connection |
Network Engineer |
$1,440.00 |
4.13 |
Development of new network access for authentic users |
IT Engineer |
$720.00 |
Access Interface[1] |
$1,200.00 | ||
5.1 |
Final Reports are being made |
Documenter |
$1,200.00 |
Documents[1] |
$50.00 | ||
5.2 |
Final Reports are submitted |
Documenter |
$400.00 |
5.3 |
Signing off the reports |
Project Manager |
$800.00 |
Total |
$55,000.00 |
Human Resource Management
The Human Resource Management (HRM) plays a significant role in the development and management of the communication for the project. The alignment of the operations was the major factor that had resulted in forming the utilization of the activities favouring the implication of the project of development of the wireless LAN connection at GV Health. The HRM plan involves the deployment of the effective management activities for the human resources of the project like analyst, documenter, planner, network designer, network engineer, IT engineer, and project manager. The HRM would involve staffing, development of work policies, pay administration, and retention of the employees. All these factors would result in listing the humans that are required for the completion of the project. The implication of the HRM has formed the development of the successful alignment of the operations.
Staffing |
The staffing is one of the major procedural requirements of the organization. The alignment of the staff development would also be one of the major responsibilities that are being carried out by the HRM department. The recruitment and the selection of the candidates that would be required in the organization can carry on the alignment of the activities favouring the deployment of the operations for aligning the utilization of the activities. |
Development of Work Policies |
The work policies are also managed and developed by the HRM system. The effective alignment of the work policies had been helpful for listing the utilization of the activities favouring the implication of the operations for forming the casting of the operations. The alignment of the activities had also helped in forming the supportive deployment of the operations. |
Pay Administration |
The employees have been facing issues from the lack of proper payments and extra benefits and compensation from the organization. It had resulted in forming the major problems for the alignment of the human management. The HRM works for the management of the pay scale and ensure that the employees get their salaries on time. Moreover, the deployment of the HRM had also helped in introducing the applying the compensation and benefits for the employees It had resulted in keeping the employees and staffs happy from the organization. |
Retention of Employees |
The resignation of employees are the major factor that had resulted in forming the issue of the forming the effective implication of the operations. However, most of the organizations have been facing issues in retention of the employees. The lack of the retention in activities has resulted in forming most of the employee leaving the organization. The employee retention had been successful for the formation of the operations and alignment of the activities favouring the utilization of the HRM. |
Project Quality Management
Budget
Resource Name |
Type |
Work/Units |
Standard Rate |
Total |
Analyst |
Human |
16 |
$40.00 |
$640.00 |
Documenter |
Human |
104 |
$50.00 |
$5,200.00 |
Planner |
Human |
24 |
$60.00 |
$1,440.00 |
Network Designer |
Human |
64 |
$80.00 |
$5,120.00 |
Network Engineer |
Human |
176 |
$90.00 |
$15,840.00 |
IT Engineer |
Human |
152 |
$90.00 |
$13,680.00 |
Project Manager |
Human |
56 |
$100.00 |
$5,600.00 |
Documents |
Material |
3 |
$50.00 |
$150.00 |
Networking Tools |
Material |
1 |
$1,000.00 |
$1,000.00 |
Simulation Tools |
Material |
1 |
$500.00 |
$500.00 |
Switches |
Material |
1 |
$1,130.00 |
$1,130.00 |
Infrastructure Cost |
Material |
1 |
$3,500.00 |
$3,500.00 |
Access Interface |
Material |
1 |
$1,200.00 |
$1,200.00 |
Total Budget |
$55,000.00 |
Reporting
Various reports like project initiation, project charter, test results, project progress reports, and final project reports are used for the reporting of the project progress to the stakeholders. The reporting of the information would also be helpful for alignment of the activities and improving the strategies aligning for the development of operations.
Project Risks Management
The risk management in the project wireless LAN connection at GV Health is shown below,
Risk |
Risk Type |
Probability |
Impact |
Mitigation Strategy |
Design Errors |
Technical |
Likely |
Extreme |
Accept |
Cost Overrun |
Financial |
Moderate |
Major |
Reduce |
Equipments Failure |
Technical |
Unlikely |
Extreme |
Mitigate |
Delay in completion |
Operational |
Very Likely |
Minor |
Avoid |
Lack of Skilled workers |
Human |
Rare |
Moderate |
Transfer |
Communication Management
The management of communication in the project of wireless LAN connection at GV Health is developed for the implication of the activities for utilizing the implication of the operations aligning the development of the operations. The management of communication process is based on the four step process that includes identification of the stakeholders, planning communication, distributing information, and reporting performance.
The communication plan for the project is shown below,
Figure: Communication Management in project
Bibliography
Cooper, R., 2017. Supply chain development for the lean enterprise: interorganizational cost management. Routledge.
Daly, M.B., Pilarski, R., Axilbund, J.E., Berry, M., Buys, S.S., Crawford, B., Farmer, M., Friedman, S., Garber, J.E., Khan, S. and Klein, C., 2016. Genetic/familial high-risk assessment: breast and ovarian, version 2.2015. Journal of the National Comprehensive Cancer Network, 14(2), pp.153-162.
Fayard, D., Lee, L.S., Leitch, R.A. and Kettinger, W.J., 2014. Interorganizational cost management in supply chains: Practices and payoffs. Management accounting quarterly, 15(3), pp.1-9.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Forouzanfar, M.H., Alexander, L., Anderson, H.R., Bachman, V.F., Biryukov, S., Brauer, M., Burnett, R., Casey, D., Coates, M.M., Cohen, A. and Delwiche, K., 2015. Global, regional, and national comparative risk assessment of 79 behavioural, environmental and occupational, and metabolic risks or clusters of risks in 188 countries, 1990–2013: a systematic analysis for the Global Burden of Disease Study 2013. The Lancet, 386(10010), pp.2287-2323.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Henri, J.F., Boiral, O. and Roy, M.J., 2016. Strategic cost management and performance: The case of environmental costs. The British Accounting Review, 48(2), pp.269-282.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Li, Z., Ma, Z., van der Kuijp, T.J., Yuan, Z. and Huang, L., 2014. A review of soil heavy metal pollution from mines in China: pollution and health risk assessment. Science of the total environment, 468, pp.843-853.
Men, L.R., 2014. Strategic internal communication: Transformational leadership, communication channels, and employee satisfaction. Management Communication Quarterly, 28(2), pp.264-284.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Shao, H., Rao, L., Wang, Z., Liu, X., Wang, Z. and Ren, K., 2014. Optimal load balancing and energy cost management for internet data centers in deregulated electricity markets. IEEE Transactions on Parallel and Distributed Systems, 25(10), pp.2659-2669.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Turner, R., 2016. Gower handbook of project management. Routledge.
Buy Manu2123 Project Management Plan-Cost And Assessment Answers Online
Talk to our expert to get the help with Manu2123 Project Management Plan-Cost And Assessment Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.