Managerial Accounting Variance Analysis

  5 Download     📄   2 Pages / 335 Words

Question Description

Rog Corporation makes a product with the following standard costs: Standard input/ output ratio Standard Price per Unit of Input Direct materials 7 grams$6.00 per grab direct labor 2 hours$16.00 per hour Variable manufacturing overhead 2 hours$6.00 per hour The monthly budgeted fixed manufacturing overhead is $432,000. Budgeted monthly output is 10,800 units.The company reported the following results concerning this product in June. Actual output 11, 000 units Direct materials used in production 78,400 grams Purchases of direct materials 88,200 grams actual direct labor-hours 20,000 hours actual cost of direct materials purchases $520,380 Actual direct labor cost$324,000 Actual variable overhead cost$140,000 Actual fixed overhead cost$412,000 The company allocates manufacturing overhead based on direct lobar-hours.

Required

a.Use a table to calculate direct materials price variance and efficiency variance, labor rate variance and efficiency variance, variable overhead spending varianceand efficiency variance, and fixed overhead spending variance and production volume variance. Indicate whether each variance is favorable or unfavorable

b.What are the possible causes of a favorable direct materials price variance? Provide three causes and explain.

c.What are the possible causes of an unfavorable direct labor efficiency variance? Provide three causes and explain.

Answer

a)

Please view excel sheet.

b)

1-Purchase is at blew the standard value. this might be due to efficiency in purchasing by purchase department.

2-Company might have purchased bulk quantity resulting discount on purchase of bulk quantity.

3-Materials prices decreased unexpectedly in the market.

c)

1- Inexperienced workers. Inexperienced labor will take time to produce the product which will lead to decrease in production of number of units in a specified time.

2- Frequent breakdowns leads to wastage of time. waste of time has direct impact on in shape of less no. of units produced.

3-Shortage of raw materials leads to breakdown in production due to shortage of raw material and ultimately efficiency get effected due to breakdown.

Resources

  • 24 x 7 Availability.
  • Trained and Certified Experts.
  • Deadline Guaranteed.
  • Plagiarism Free.
  • Privacy Guaranteed.
  • Free download.
  • Online help for all project.
  • Homework Help Services
Copyright © 2009-2023 UrgentHomework.com, All right reserved.