Ma6088 Project Management: Avoid Delay Assessment Answers

Questions:

New Stadium 

20,000-seat stadium in the West of Singapore 

Construction: 

West Hub Construction is planning to prepare a bid for the construction of a 20,000-seat stadium in the West of Singapore. The construction must start on June 4th 2017 and be completed by the January 2nd 2020. A penalty clause of S$100,000 per day of delay beyond January 2nd 2020 is written into the contract.

Patrick Tan, the managing director of the company has expressed optimism in gaining the contract having previously completed the construction of a similar type of stadium in Jakarta, Indonesia. Success in completing the 20,000-seat stadium will enhance the company’s chances of securing similar projects not only in Singapore and Malaysia but also in China and Thailand.

The project begins with the clearing of the site. Once the site is cleared, work can start simultaneously on the structure itself and demolishing an adjacent building. From there, the tasks, durations and dependencies of each activity are indicated as follows:

All other holidays are classed as NON-working days.

The construction team works a 5 day week Monday-Friday

The working day is based upon 8 hours, excluding breaks.

Requirements  

Use the information detailed in the case and accompanying activity list to complete the following;

  1. Construct a network diagram and a Gantt chart to represent the project. Identify the critical path, project duration and milestones.
  2. If the project is undertaken and bad weather introduces a thirty day delay to the project, outline the options available to the Project Manager to overcome this.

Answers:

Gantt chart

Critical path

Following activities form the critical path:

Task Name

Clear site

Drive support piles

Pour lower concrete base

Pour main concourse

Construct upper steel bowl

Install seats

Construct steel canopy

Light installation

Inspection

Milestones

Following are key milestones:

  • Setup construction site
  • Laying files
  • Stadium infrastructure
  • Roof installation

Avoid delay in the project execution

Critical path is the longest duration path which should be completed in time for the project to be completed by deadline. Any delay in any of the activity can lead to delaying the entire project. The path contains critical activities which have 0 slack. All other activities have non-zero slack. Delaying these activities do not have any impact on the project completion date.

Following options can be taken to avoid delay (Baguley, 2008):

a. Make use of slack occurring in non-critical activities – Slack is termed as the cushion time period. In the given scenario, if the delays the project by 30 days then project manager an make use of this slack of next activity in project path (Heerkens, 2015). Lay/install playing field has largest slack time period of 250 days so it can absorb the delay if rain happens before it. Similarly, there are following activity at every interval which can avoiding this rain delay:

Task Name

Duration

Start

Finish

Predecessors

Total Slack

Build boxes 

90 days

Wed 05-12-18

Tue 09-04-19

7,9

120 days

Install scoreboard 

40 days

Wed 05-12-18

Tue 29-01-19

7,9

170 days

Stadium infrastructure 

120 days

Wed 05-12-18

Tue 21-05-19

7,9

90 days

Construct steel canopy 

60 days

Wed 22-05-19

Tue 13-08-19

10

0 days

Light installation 

30 days

Wed 14-08-19

Tue 24-09-19

14

0 days

Build roof supports 

90 days

Wed 20-06-18

Tue 23-10-18

6

60 days

Install roof 

180 days

Wed 24-10-18

Tue 02-07-19

16

60 days

b. Allocating more resources to the left-over activities to complete the project. However, this option may lead to increase in the project budget (Maylor, 2010). Hence it is not a feasible solution.


Buy Ma6088 Project Management: Avoid Delay Assessment Answers Online


Talk to our expert to get the help with Ma6088 Project Management: Avoid Delay Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Ma6088 Project Management: Avoid Delay Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.