ITC505 Project Management-Research Centre Project
Your team must include appropriate experts to assess the application, network and database software and hardware needs to support this project.Your manager, Bruce has given you guidance that the project needs to be completed within 8 months and that costs should be minimised wherever possible with given budget of AUD 50000.00
- WBS first using indented format.
- Gantt chart-Take the WBS you have already developed. Define all of the activities that will be necessary to create each deliverable in your WBS. Create a schedule for your project. First create the schedule by hand using Post-itNotes, and then put the information into MS Project. Take screenshots of the schedule to be pasted in your word document that you are submitting. Be sure to include all of the summary rows (including the first row for the project title) and any key milestones. Make sure the critical path is easy to see.
- Create a time-phased budget for your example project using bottom-up estimating. To the extent your sponsor will supply rates for workers, use those. Approximate rates for ones you cannot get. Ask your sponsor how they treat indirect costs. Be sure to include direct labour costs for you and your team mates and add 20% for fringe. State all assumptions and constraints you have used when creating your budget. State how confident you are in your estimates and what would make you more confident. Give examples of known knowns and known unknowns on your project. Tell how you have budgeted for both of them plus how you have budgeted for unknown unknowns.
- Create a risk register ( 4 risks- 3 negative and 1 positive risk)for your example project.
- Quality Management Plan. It should include:
A short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client.
Develop and describe 3 quality issues related to this project that your project team could implement to ensure quality.
Closure checklist and project evaluation
Develop a closure checklist that the project team will use to ensure that the project has been closed properly.
Develop a project evaluation –outline and discuss how your project’s MOV will be evaluated.
Answer:
Project management team needs to manage all activities regarding project. On the basis of given case study it is to be described that a research centre needs to be developed by which the process of implementation can be done in efficient manner. As described in the case study that David Wright is a company’s boss who give Bruce an objective to develop a research centre in order to promote the quality (Turner, 2014).
The research centre project is going to be started in February 2018. Initially an unofficial group of research is to be developed till June 2017. As being a manager of this project, it is a responsibility that project management aspects must focus on the social media research centre project.
With the help of defined activity project charter will be executed in this project report which provides help in developing the work breakdown structure for the social media research centre and that will be chased by the Gantt chart by which proper knowledge can be gathered regarding this project (Martinsuo, et. al., 2014).
Boss of this company has provided the minimum budget for AUD 50000 for completing this project within the given timeframe of 8 months. This project report will be developed in order to provide assistance for developing Social Media Research Centre b
y which the quality of activities can be developed and project could be get completed within the given timeframe and budget (Petit, 2012).
Plan for Time Management
S.NO |
Activity to be executed |
Total days |
Initialize date |
Completion date |
Action which is to be planned |
1 |
Project on social media research centre development |
225 D |
1 April 17 |
30 Nov 17 |
This phase is about to establishment of the Social Media Research Centre and makes strategies accordingly (Norman, et. al., 2010). |
2 |
Starting of project |
61 D |
1 April 17 |
31 May 17 |
|
2.1 |
Project charter development |
30 D |
1 April 17 |
30 April 17 |
Project charter is to be developed in this step and on the basis of assignment 1 charter has created on last month to directing the project. |
2,2 |
Commencement of meeting to start the project |
31 D |
1 May 17 |
31 May 17 |
Meetings are to be organised in this step and discussion is done on the project processing as well as about the tasks associated with the project (Pearson, et. al., 2013). |
3. |
Project requirement identification |
61 D |
1 June 17 |
31 July 17 |
|
3.1 |
To collect data in respect to the necessity |
30 D |
1 June 17 |
30 June 17 |
This step is about to accumulate the necessary information in respect with project. Through the process of project analysis all the necessities of this project is to be assessed and develop regarding strategies. |
3.2 |
To develop appropriate documents |
31 D |
1 July 17 |
31 July 17 |
This phase is about to fulfil the necessities of the documentation and assessment will be done regarding the several aspects that must be fulfilled in the upcoming period of time (Pinto, 2013). |
4 |
Review |
90 D |
1 Aug 17 |
31 Oct 17 |
|
4.1 |
To develop documentation for review technically |
7 D |
1 Aug 17 |
7 Aug 17 |
This phase is about to develop the document for the technical assessment which involves the entire associated topic to the Social Media centre. |
4.2 |
Project planning |
7 D |
8 Aug 17 |
14 Aug 17 |
This step is about to make plan for the ongoing activities associated with the projects by which project could be completed within the given budget and given time frame of 8 months (Roberts, 2012). |
4.3 |
Work breakdown structure (WBS) development |
7 D |
15 Aug 17 |
21 Aug 17 |
In this step WBS will be executed with the help of team members in which work will be disseminate in equal part to all the members by which team can do the activities in effective manner and acquire the desired quality. |
4.4 |
Project scheduling |
7 D |
22 Aug 17 |
28 Aug 17 |
In this phase scheduling of project will be executed in order to make the project complete with appropriate manner (Silvius, 2017). |
4.5 |
Collecting resources for project |
7 D |
29 Aug 17 |
4 Sep 17 |
Resources are to be collected in this phase in accordance with the specification so all types of tasks can be managed. |
4.6 |
To identify stakeholders |
7 D |
5 Sep 17 |
11 Sep 17 |
This step is about to identify the stakeholders as well evaluation is also executed in order to fulfil the project requirement by which proper support is to be provided. |
4.7 |
Predicted project cost |
7 D |
12 Sep 17 |
18 Sep 17 |
The overall estimated project cost is to be analysed in this phase on which basis all the activities needs to be completed (Turner, 2014). |
4.8 |
Budget according time phase |
7 D |
19 Sep 17 |
25 Sep 17 |
Budget will be developed in this step in the basis of time phase. Through the time phrase entire estimated expenses that is going to be incurred into the project as well recording will be done in order to provide assistance to the project. |
4.9 |
To evaluate risk |
7 D |
26 Sep 17 |
2 Oct 17 |
This step is about to identify the risk involved in this project. Later on, Identified risk will be recorded in the risk register. |
4.10 |
To develop risk register |
7 D |
3 Oct 17 |
9 Oct 17 |
In this phrase risk register is to be developed and presented to the boss Bruce in first week (Martinsuo, et. al., 2014). |
4.11 |
Quality management plan development |
14 D |
10 Oct 17 |
23 Oct 17 |
Quality management plan is to be developed in this step that will provide assistance to the project as well as provide guidelines also to complete this within time frame. |
4.12 |
To develop Plan to control the change |
15 D |
24 Oct 17 |
31 Oct 17 |
Planning regarding change control will be executed in this step and named as plan B and that assures about the changes which will be doing must be according to the market. |
5 |
To design website |
30 D |
1 Nov 17 |
30 Nov 17 |
|
5.1 |
Modules development |
10 D |
1 Nov 17 |
10 Nov 17 |
This is about to develop the modules along with coding in order to execute the program and can perform required alteration accordingly. |
5.2 |
To conduct testing |
10 D |
11 Nov 17 |
20 Nov 17 |
Testing will be performed after the modules development in order to check that all functions are being done accordingly. |
5.3 |
To make the live website |
10 D |
20 Nov 17 |
30 Nov 17 |
At last website is to be developed and introduce it live by which people can use it and could acquire some benefits (Petit, 2012). |
6 |
To evaluate the closing checklist |
1 D |
29 Nov 17 |
29 Nov 17 |
In the end, project closing checklist will be developed in order to evaluate whether all the activities are performed or not. |
6.1 |
Project closing |
- |
- |
- |
- |
(Norman, et. al., 2010)
Constraints:
Companies indulged in the project management do not provide any kind of information related with the project cost that is being quoted by them.
Quotation of the cost depends upon the time that will be taken by the project (Silvius, 2017).
Assumption:
Assumption as made that the contract was signed between the project Management Company and David Wright regarding labour that will work on project and their cost.
Known Knowns:
Assistants are not required in the project therefore there cost will also be not included
The per day basis cost that is being provided to the team members will not change
Known Unknown:
The treatment of the indirect cost used by the sponsors is not known (Turner, 2014).
Risk Register
To prepare risk register is an essential element in order to execute the project. There can be several risk factors associated with the projects are described as under:
Risk Description |
Response to Risk |
Objectives |
Framework |
Operational risk has been identified in this case that in Social Median Research Centre project all the operations are ceased that will put negative impact on the productivity. |
Regarding this risk it is evaluated that problem should be identified and eliminate them accordingly (Martinsuo, et. al., 2014). |
To conduct all the activities in efficient manner. |
Likely |
Boss of the company pressurize the David (senior executive) to achieve good quality that can also make negative impact on the productivity as work pressure is not good for employees. |
Appropriate set of training and development will be given by the senior executive to reduce the work pressure and work with ease. |
To make employee comfortable with work leads to develop the good environment which will help to improve the quality of the services provided (Petit, 2012). |
Likely |
On the basis of case study it is identified that the David’s work unit not possess clear direction and identity this will direct effect on the service quality along with this company’s stakeholder will get affected. |
It is essential to provide uniqueness to the work unit by which they can produce good output along with good quality. |
This assists in to increase the company’s goodwill (Norman, et. al., 2010). |
Less prone |
To make huge investment in the project of David is also a big risk but this can be positive if the project will become successful (Pearson, et. al., 2013). |
Proper quality management is required to acquire desired quality. |
This assists company to make good amount of profit through big investment. |
Likely |
Quality Management Plan
Project Name: Social Media Research Centre |
Project Manager: |
Date: | |||
Features |
Category |
motive |
Technique |
proprietor |
Status |
The main focus of this project to attain high quality. |
To create project (Pinto, 2013) |
To expand the business |
To imitate described procedure in an appropriate manner. |
David Wright |
Processing |
Another aspect is to complete this project within given timeframe and budget. |
Initiate project |
That will reduce the expenses |
Time phrase |
Bruce |
Processing |
To minimize the project cost |
Financing |
This will help to attain higher quality in lower cost (Roberts, 2012) |
Time phrase |
Bruce |
Processing |
Teamwork |
Operating |
This will help in developing coordination among team members. |
To organize meetings |
David Wright |
To be proceed |
To do work in pressure |
Operation |
This will teach the employees to perform in extreme work load and acquire good quality |
Motivating
|
David Wright |
To be proceed |
(Silvius, 2017)
S.NO |
Activity to be executed |
Completion date |
Status of the activities |
1 |
Project on social media research centre development |
30 Nov 17 |
Completed |
2 |
Starting of project |
31 May 17 |
Completed |
2.1 |
Project charter development |
30 April 17 |
Completed |
2,2 |
Commencement of meeting to start the project |
31 May 17 |
Completed |
3. |
Project requirement identification |
31 July 17 |
To be Completed |
3.1 |
To collect data in respect to the necessity |
30 June 17 |
Due |
3.2 |
To develop appropriate documents |
31 July 17 |
Due |
4 |
Review |
31 Oct 17 |
Due |
4.1 |
To develop documentation for review technically |
7 Aug 17 |
Due |
4.2 |
Project planning |
14 Aug 17 |
Due |
4.3 |
Work breakdown structure (WBS) developing |
21 Aug 17 |
Due |
4.4 |
Project scheduling |
28 Aug 17 |
Not completed |
4.5 |
Collecting resources for project |
4 Sep 17 |
Not completed |
4.6 |
To identify stakeholders |
11 Sep 17 |
Not completed |
4.7 |
Predicted project cost |
18 Sep 17 |
Not completed |
4.8 |
Budget according time phase |
25 Sep 17 |
Not completed |
4.9 |
To evaluate risk |
2 Oct 17 |
Not completed |
4.10 |
To develop risk register |
9 Oct 17 |
Not completed |
4.11 |
Quality management plan development |
23 Oct 17 |
Not completed |
4.12 |
To develop Plan to control the change |
31 Oct 17 |
Not completed |
5 |
To design website |
30 Nov 17 |
Not completed |
5.1 |
Modules development |
10 Nov 17 |
Not completed |
5.2 |
To conduct testing |
20 Nov 17 |
Not completed |
5.3 |
To make the live website |
30 Nov 17 |
Not completed |
6 |
To evaluate the closing checklist |
29 Nov 17 |
Not completed |
6.1 |
Project closing |
- |
- |
(Turner, 2014)
References
Martinsuo, M. and Killen, C. (2014). Value Management in Project Portfolios: Identifying and Assessing Strategic Value. Project Management Journal, 45(5), 56-70.
Petit, Y. (2012). Advancing project and portfolio management research: applying strategic management theories. Strategic Direction, 28(9), 187-192.
Norman, E. S., Brotherton, S. A., & Fried, R. T. (2010). Work breakdown structures: The foundation for project management excellence. John Wiley & Sons.
Pearson, N., Larson, E. W., & Gray, C. F. (2013). Project management in practice: A complete course for BSB41513 and BSB51413. North Ryde, NSW: McGraw-Hill Education (Australia).
Pinto, J. K. (2013). Project management: Achieving competitive advantage (3rd, Global ed.). Harlow, Essex;Boston;: Pearson Education.
Roberts, P., 1964, & Books24x7, I. (2012). Strategic project management (1st ed.). London, U.K;Philadelphia, PA, USA;: Kogan Page.
Silvius, G., ebrary, I., & Books24x7, I. (2012;2017;). Sustainability in project management. Burlington, VT: Gower Pub.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Buy ITC505 Project Management-Research Centre Project Answers Online
Talk to our expert to get the help with ITC505 Project Management-Research Centre Project Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.