ITC505 Measurable Organisational Value
Explain the desired value you have chosen)
- Better - is improving quality important to your client
- Faster - does your client want to increase efficiency
- Cheaper - is cutting costs important?
- Do more - does your client want to continue its growth
Step 3: Identify the Metrics
Explain the metrics you have chosen)
- Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.
Step 4: Identify the Timeframe
Explain the timeframe you have chosen)
Determine the timeframe for achieving the MOV - ask yourselves, when do we want to achieve this target metric
Step 5: Agree with the sponsor
Explain the recommendations given by your sponsor)
Step 6: Summairse in a clear concise statement
Provide the statement here)
(Note: the MOV should inform everyone what the project will achieve, not how it will be achieved. It should also focus on the organisation, not on the technology that will be used to build or support the information system)
Answer:
Part One:1.1 MOV - Measurable Organisational Value
;">
Area of Impact |
Rank (1 to 5) |
Customer |
1 |
Operational |
2 |
Financial |
3 |
Social |
4 |
Strategy |
5 |
1.2 Value of the project
The desired project value are explained below:
Better: The organization assist in providing proper facility with the help of number of new features which further improves the operational efficiency and thus the facility which are provided are considered to be efficient.
Faster: It is analyzed that the online transactions service is quite faster in crediting or debiting money in comparison to the present system which is used by the organization.
1.3 Appropriate metric
Rank |
Impact |
Metrics |
Timeframe |
1 |
Customer |
20% more customers are added for utilizing the services provided by the organization due to the I-crop system. |
3 months |
2 |
Operational |
There is around 12% increment in the efficiency of the organizational efficiency as the organization can easily manage the operations. |
3 months |
3 |
Financial |
12% hike is reflected within the yearly revenue of the organization due to increment within the customers number |
2 months |
4 |
Social |
The organization utilizes social platform like LinkedIn as well as Facebook for promotion. |
1 month |
5 |
Strategy |
It is quite necessary to use proper strategies for managing the development of the system. |
2 months |
2.1 Scope
The scope includes:
- The website as well as application are developed
- Selection of the prototype
- Designing the entire project outline
- Reviewing the project design
- Adding the option of the preferred buyers
- Adding the option of transaction facility
- The option for the seasonal sales is added
- Giving proper training manuals
- Providing the facility of training
- Documentation
2.2 Out of Scope
The project out-scope include:
- Excluding the details related with the suppliers as well as vendors
- Facility of training is omitted from project charter
2.3 Assumptions
The assumptions of the project include:
- The project manager makes assumption such that entire project completes within time and budget that is given
- Proper support and help from the stakeholders will be get during the project progress
- The project will progress as per the scope and thus the objectives of the project can be achieved successfully.
2.4 Constraints
The project constraints are listed below:
- It is essential to finish the work related with the project within 119 days
- The entire activities of the I-crop system should be executed within the budget of $79,240.
2.5 Scope Management Plan
The project manager generally takes the initiative of managing the project scope so that no scope related issues as well as challenges can occur within the project. The steps include:
- Properly determining the project related issues
- Identifying the various types of reasons due to which the problem of scope creep occurs
- The scope of the project should be managed effectively
- Proper facility of training must be given to the team members so that they can avoid scope creep
- 2.6 Resource Plan
- People: The people who are engaged within the project work are listed within the given table.
Resource Name |
Std. Rate |
Project Manager |
$50.00/hr |
Financial Officer |
$45.00/hr |
Developer |
$40.00/hr |
Operational Manager |
$40.00/hr |
Project Planner |
$30.00/hr |
Project Sponsor |
$0.00/hr |
System Analyst |
$35.00/hr |
Trainer |
$35.00/hr |
IT Manager |
$30.00/hr |
Tester |
$30.00/hr |
Designer |
$32.00/hr |
HR Manager |
$25.00/hr |
Risk Manager |
$25.00/hr |
Business Analyst |
$26.00/hr |
IT Consultant |
$35.00/hr |
Hardware |
RAM, Hard disk, Desktop |
Software |
Designing tools, development tools |
Network |
Server |
- Other
Travel Requirements |
Allowance for travelling should be given to the workers. |
Training Requirements |
Monthly training should be provided. |
Part three:
3.1 Project Milestones
The milestones of the project are:
Milestone |
Completion date |
Milestone 1: The initiation phase of the project completed |
Thu 18-10-18 |
Milestone 2: The final plan for the project is completely prepared |
Mon 26-11-18 |
Milestone 3: The entire design of the project that is designed is completed reviewed |
Thu 03-01-19 |
Milestone 4: Development of the project is completed |
Thu 07-02-19 |
Milestone 5: Completion of the project closure phase |
Tue 12-03-19 |
The assumptions of the project include:
- Proper support and help from the stakeholders will be get
- The project will progress as per the scope.
- Finishing the project within time that is assumed
- 4.2 Project risks and management strategy
Risk ID |
Description |
Probability |
Impact |
Rate |
Assigned To |
Response Strategy |
Threat or Opportunity |
1 |
Budget shortage |
90% |
5 |
450 |
Financial manager |
It is necessary to track the budget on regular basis for finishing the project within budget |
Threat |
2 |
Lack of resources |
80% |
4 |
320 |
Hr. manager |
It is necessary to estimate the project resources properly before undertaking the project. |
Threat |
3 |
Improper management |
80% |
4 |
320 |
Hr. manager |
It is necessary to hire experienced team members |
Threat |
4 |
Extension in the project schedule |
70% |
4 |
210 |
Project manager |
It is necessary to analyze the need of the project properly before the project initiation. |
Opportunity |
5 |
Improper facility of training |
80% |
5 |
400 |
Trainer |
Proper facility of training should be given to the team members. |
Threat |
Part Five:
- Statement on project quality
The quality of the project can be improved by adopting strategies that are listed below:
- Checking the hardware quality that are used within the project
- Undertaking testing within the project
- Providing training facility to the workers
- Proper quality analysis should be conducted on monthly basis.
- A set of verification activities
Verification Activity |
When? |
External audit |
After the entire project work is completed |
Undertaking prototype testing |
After the protype is completed |
Undertaking hardware testing |
Before utilization of hardware within the project. |
- A set of validation activities
Validation Activity |
When? |
Equipment testing |
Before using within the project |
Document review |
After the project closure phase |
Using method of prototype |
During the development phase of the project |
b. Develop a closure checklist
Activities |
Status |
Has project testing is properly accomplished? |
Yes |
Have project documents been properly approved? |
Yes |
All project issues and risks closed? |
No |
Does the fcaility of training given? |
Yes |
Does the issues as well as risks are successfully closed? |
No |
Develop a project evaluation
Evaluation Criteria |
Option |
Does the needs of the project are accomplished? |
Yes No |
Does the training facility is provided? |
Yes No |
Does the project finish are within the approved budget? |
Yes No |
Does proper project review is done? |
Yes No |
Bibliography
Amrollahi, A., Ghapanchi, A. H., &Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.
Batselier, J., & Vanhoucke, M. (2015). Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management. International Journal of Project Management, 33(7), 1588-1596.
Braglia, M., &Frosolini, M. (2014).An integrated approach to implement project management information systems within the extended enterprise.International Journal of Project Management, 32(1), 18-29.
Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.
Galliers, R. D., &Leidner, D. E. (2014). Strategic information management: challenges and strategies in managing information systems. Routledge.
Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence.pearson.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.
Muriana, C., & Vizzini, G. (2017). Project risk management: A deterministic quantitative technique for assessment and mitigation. International Journal of Project Management, 35(3), 320-340
Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-29).Springer International Publishing.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success factors for project managers in virtual work settings.International Journal of Project Management, 31(1), 68-79.
Buy ITC505 Measurable Organisational Value Answers Online
Talk to our expert to get the help with ITC505 Measurable Organisational Value Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.