The following is the project management plan developed for project of Service-Tourism Convention Project and it has help in developing the successful management of the tasks. The plan developed has be effectively managed with the help of project scheduling software like Ms-Project, WBS Pro, and Calender. The finalizing of the project management plan has help in providing information to the stakeholders in relation to the  project.

Scope Management

The project scope management has been formed confining the evaluation of the factors and the development of the successful execution of the project. The project scop management includes the evaluation of the in-scope and out-of-scope items of the project and the project scope statement.

In Scope

The in scope items for the project has include the booking of the convention space, arrangement for the preferred hotel rooms for participants, event staff, and keynote speakers. Apart from this, the registration of exhibitor and participants is also included in the project tasks. The hiring of contractor, onsite food vendor, and construction processes are also a part of the project.

Out of Scope

There are some tasks that are important for the event execution however they are not a part of the project tasks. The obtaining of the key notes for the speaker, advertisement, guest list, event advertisement, and hotel rooms development are not a part of the project.

Scope Statement

The event execution has include the use of the event management processes and the usages of the successful management of the tasks. The finalizing of the project has involve the management of the successful management of processes for integrating the activity alignment.  

Schedule Management

Project Schedule

The schedule for the project of Service-Tourism Convention Project is given below,

WBS

Task Name

Duration

Start

Finish

0

Service-Tourism Convention Project

150 days

Mon 11/5/18

Fri 5/31/19

1

Initial Phase

9 days

Mon 11/5/18

Thu 11/15/18

1.1

Analysis of the Requirements

2 days

Mon 11/5/18

Tue 11/6/18

1.2

Charter Documentation

3 days

Wed 11/7/18

Fri 11/9/18

1.3

Project Initiation Documents

3 days

Mon 11/12/18

Wed 11/14/18

1.4

Submission of Documents

1 day

Thu 11/15/18

Thu 11/15/18

1.5

Sign off

0 days

Thu 11/15/18

Thu 11/15/18

2

Planning Phase

12 days

Fri 11/16/18

Mon 12/3/18

2.1

Activities are listed

3 days

Fri 11/16/18

Tue 11/20/18

2.2

Resources Accumulated

2 days

Wed 11/21/18

Thu 11/22/18

2.3

Scheduling project activities

4 days

Fri 11/23/18

Wed 11/28/18

2.4

Risk management planning

3 days

Thu 11/29/18

Mon 12/3/18

3

Execution Phase

34 days

Tue 12/4/18

Fri 1/18/19

3.1

Booking Convention Space

3 days

Tue 12/4/18

Thu 12/6/18

3.2

Making guest list

2 days

Fri 12/7/18

Mon 12/10/18

3.3

Arrangement for picking guests

4 days

Tue 12/11/18

Fri 12/14/18

3.4

Booking hotel rooms in Brampton, Mississauga or Toronto

3 days

Mon 12/17/18

Wed 12/19/18

3.5

Transporting people and luggage to the respective hotel locations

4 days

Thu 12/20/18

Tue 12/25/18

3.6

Registering Exhibitors and Participants

2 days

Wed 12/26/18

Thu 12/27/18

3.7

Hiring Engineer

2 days

Fri 12/28/18

Mon 12/31/18

3.8

Renting Audio-Visual Equipments

1 day

Tue 1/1/19

Tue 1/1/19

3.9

Infrastructure Development

4 days

Wed 1/2/19

Mon 1/7/19

3.10

Exhibition Residue Development

4 days

Tue 1/8/19

Fri 1/11/19

3.11

Onsite Catering Service Development

3 days

Mon 1/14/19

Wed 1/16/19

3.12

Event Execution

2 days

Thu 1/17/19

Fri 1/18/19

4

Closing

95 days

Mon 1/21/19

Fri 5/31/19

4.1

Post Evaluation

10 days

Mon 1/21/19

Fri 2/1/19

4.2

Feedback Collection

80 days

Mon 2/4/19

Fri 5/24/19

4.3

Final Documents

5 days

Mon 5/27/19

Fri 5/31/19

4.4

Project Closed

0 days

Fri 5/31/19

Fri 5/31/19

Cost Management

The project cost management has been done considering the resource usage plan and the bottom up estimation method in which each of the resource usage is multiplied by the standard rate of the resource. The summation of the cost of individual resource has help in calculating the final project budget cost. The following is the cost estimation for the project,

Resource Name

Work

Standard Rate

Cost

Analyst

16 hrs

$45.00/hr

$720.00

Documenter

96 hrs

$50.00/hr

$4,800.00

Planner

56 hrs

$55.00/hr

$3,080.00

Project Manager

152 hrs

$100.00/hr

$15,200.00

Risk Analyst

24 hrs

$60.00/hr

$1,440.00

Event Manager

40 hrs

$75.00/hr

$3,000.00

Volunteers

80 hrs

$70.00/hr

$5,600.00

Contractor

64 hrs

$80.00/hr

$5,120.00

Engineer

40 hrs

$90.00/hr

$3,600.00

Vendor

24 hrs

$70.00/hr

$1,680.00

Documents

3

$150.00

$450.00

Food and Beverage

1

$10,000.00

$10,000.00

Construction Material

1

$15,000.00

$15,000.00

Audio-Video Equipments

1

$5,310.00

$5,310.00

Total Budget

$75,000.00

Quality Management

The quality management for the project of Service-Tourism Convention Project can be done for following the effective implication of the SDLC process. The SDLC comprise of the following elements,

Information Collection: The collection of the required information is done in this phase for the project tasks.

Plan Development: The project tasks are scheduled using the appropriate calendar software for execution of the project.

Execution: The project tasks has be executed successfully for the finalizing of the project.

Monitor and Control: The monitor and control of the project has be done using 7QC, checklist, and evaluation methods.

Communication Management

Communication Medium

Information Transferred

Frequency

Sender

Receiver

Reports

Project Progress

Weekly

Project team, Project Manager

Project Client, Sponsor

Emails, Messages

Issues identified

Monthly

Project team

Project Manager

Face to Face Talk

Project Requirement

Once

Project Client

Project Manager

Phone calls

Change requirements

Twice

Project Manager,

Project Manager

Project Manager,

Project Team

Risk Management

Risk Factor

Type

Probability

Impact

Mitigation

Delay in Completion

Operational

High

Low

Time Management Plan should be used

Cost Issues

Financial

Medium

Medium

Provisional Budget should be included

Technical Issues

Technology

Low

High

Hiring of external engineer

Conclusion

The event is developed for executing the event of management of the better activity alignment. The finalizing of the documents had been helpful for analysing the prospect of developing successful project tasks. The finalizing of the project had been eased with the usages and development of the successive information management.

Bibliography

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. Amacom.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.

Leach, L. P. (2014). Critical chain project management. Artech House.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.


Buy Inf2040 Project Management For Service Assessment Answers Online


Talk to our expert to get the help with Inf2040 Project Management For Service Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Inf2040 Project Management For Service Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.