Inf2040 Project Management For Service Assessment Answers
Answer:
Introduction
The following is the project management plan developed for project of Service-Tourism Convention Project and it has help in developing the successful management of the tasks. The plan developed has be effectively managed with the help of project scheduling software like Ms-Project, WBS Pro, and Calender. The finalizing of the project management plan has help in providing information to the stakeholders in relation to the project.
Scope Management
The project scope management has been formed confining the evaluation of the factors and the development of the successful execution of the project. The project scop management includes the evaluation of the in-scope and out-of-scope items of the project and the project scope statement.
In Scope
The in scope items for the project has include the booking of the convention space, arrangement for the preferred hotel rooms for participants, event staff, and keynote speakers. Apart from this, the registration of exhibitor and participants is also included in the project tasks. The hiring of contractor, onsite food vendor, and construction processes are also a part of the project.
Out of Scope
There are some tasks that are important for the event execution however they are not a part of the project tasks. The obtaining of the key notes for the speaker, advertisement, guest list, event advertisement, and hotel rooms development are not a part of the project.
Scope Statement
The event execution has include the use of the event management processes and the usages of the successful management of the tasks. The finalizing of the project has involve the management of the successful management of processes for integrating the activity alignment.
Schedule Management
Project Schedule
The schedule for the project of Service-Tourism Convention Project is given below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Service-Tourism Convention Project |
150 days |
Mon 11/5/18 |
Fri 5/31/19 |
1 |
Initial Phase |
9 days |
Mon 11/5/18 |
Thu 11/15/18 |
1.1 |
Analysis of the Requirements |
2 days |
Mon 11/5/18 |
Tue 11/6/18 |
1.2 |
Charter Documentation |
3 days |
Wed 11/7/18 |
Fri 11/9/18 |
1.3 |
Project Initiation Documents |
3 days |
Mon 11/12/18 |
Wed 11/14/18 |
1.4 |
Submission of Documents |
1 day |
Thu 11/15/18 |
Thu 11/15/18 |
1.5 |
Sign off |
0 days |
Thu 11/15/18 |
Thu 11/15/18 |
2 |
Planning Phase |
12 days |
Fri 11/16/18 |
Mon 12/3/18 |
2.1 |
Activities are listed |
3 days |
Fri 11/16/18 |
Tue 11/20/18 |
2.2 |
Resources Accumulated |
2 days |
Wed 11/21/18 |
Thu 11/22/18 |
2.3 |
Scheduling project activities |
4 days |
Fri 11/23/18 |
Wed 11/28/18 |
2.4 |
Risk management planning |
3 days |
Thu 11/29/18 |
Mon 12/3/18 |
3 |
Execution Phase |
34 days |
Tue 12/4/18 |
Fri 1/18/19 |
3.1 |
Booking Convention Space |
3 days |
Tue 12/4/18 |
Thu 12/6/18 |
3.2 |
Making guest list |
2 days |
Fri 12/7/18 |
Mon 12/10/18 |
3.3 |
Arrangement for picking guests |
4 days |
Tue 12/11/18 |
Fri 12/14/18 |
3.4 |
Booking hotel rooms in Brampton, Mississauga or Toronto |
3 days |
Mon 12/17/18 |
Wed 12/19/18 |
3.5 |
Transporting people and luggage to the respective hotel locations |
4 days |
Thu 12/20/18 |
Tue 12/25/18 |
3.6 |
Registering Exhibitors and Participants |
2 days |
Wed 12/26/18 |
Thu 12/27/18 |
3.7 |
Hiring Engineer |
2 days |
Fri 12/28/18 |
Mon 12/31/18 |
3.8 |
Renting Audio-Visual Equipments |
1 day |
Tue 1/1/19 |
Tue 1/1/19 |
3.9 |
Infrastructure Development |
4 days |
Wed 1/2/19 |
Mon 1/7/19 |
3.10 |
Exhibition Residue Development |
4 days |
Tue 1/8/19 |
Fri 1/11/19 |
3.11 |
Onsite Catering Service Development |
3 days |
Mon 1/14/19 |
Wed 1/16/19 |
3.12 |
Event Execution |
2 days |
Thu 1/17/19 |
Fri 1/18/19 |
4 |
Closing |
95 days |
Mon 1/21/19 |
Fri 5/31/19 |
4.1 |
Post Evaluation |
10 days |
Mon 1/21/19 |
Fri 2/1/19 |
4.2 |
Feedback Collection |
80 days |
Mon 2/4/19 |
Fri 5/24/19 |
4.3 |
Final Documents |
5 days |
Mon 5/27/19 |
Fri 5/31/19 |
4.4 |
Project Closed |
0 days |
Fri 5/31/19 |
Fri 5/31/19 |
Cost Management
The project cost management has been done considering the resource usage plan and the bottom up estimation method in which each of the resource usage is multiplied by the standard rate of the resource. The summation of the cost of individual resource has help in calculating the final project budget cost. The following is the cost estimation for the project,
Resource Name |
Work |
Standard Rate |
Cost |
Analyst |
16 hrs |
$45.00/hr |
$720.00 |
Documenter |
96 hrs |
$50.00/hr |
$4,800.00 |
Planner |
56 hrs |
$55.00/hr |
$3,080.00 |
Project Manager |
152 hrs |
$100.00/hr |
$15,200.00 |
Risk Analyst |
24 hrs |
$60.00/hr |
$1,440.00 |
Event Manager |
40 hrs |
$75.00/hr |
$3,000.00 |
Volunteers |
80 hrs |
$70.00/hr |
$5,600.00 |
Contractor |
64 hrs |
$80.00/hr |
$5,120.00 |
Engineer |
40 hrs |
$90.00/hr |
$3,600.00 |
Vendor |
24 hrs |
$70.00/hr |
$1,680.00 |
Documents |
3 |
$150.00 |
$450.00 |
Food and Beverage |
1 |
$10,000.00 |
$10,000.00 |
Construction Material |
1 |
$15,000.00 |
$15,000.00 |
Audio-Video Equipments |
1 |
$5,310.00 |
$5,310.00 |
Total Budget |
$75,000.00 |
Quality Management
The quality management for the project of Service-Tourism Convention Project can be done for following the effective implication of the SDLC process. The SDLC comprise of the following elements,
Information Collection: The collection of the required information is done in this phase for the project tasks.
Plan Development: The project tasks are scheduled using the appropriate calendar software for execution of the project.
Execution: The project tasks has be executed successfully for the finalizing of the project.
Monitor and Control: The monitor and control of the project has be done using 7QC, checklist, and evaluation methods.
Communication Management
Communication Medium |
Information Transferred |
Frequency |
Sender |
Receiver |
Reports |
Project Progress |
Weekly |
Project team, Project Manager |
Project Client, Sponsor |
Emails, Messages |
Issues identified |
Monthly |
Project team |
Project Manager |
Face to Face Talk |
Project Requirement |
Once |
Project Client |
Project Manager |
Phone calls |
Change requirements |
Twice |
Project Manager, Project Manager |
Project Manager, Project Team |
Risk Management
Risk Factor |
Type |
Probability |
Impact |
Mitigation |
Delay in Completion |
Operational |
High |
Low |
Time Management Plan should be used |
Cost Issues |
Financial |
Medium |
Medium |
Provisional Budget should be included |
Technical Issues |
Technology |
Low |
High |
Hiring of external engineer |
Conclusion
The event is developed for executing the event of management of the better activity alignment. The finalizing of the documents had been helpful for analysing the prospect of developing successful project tasks. The finalizing of the project had been eased with the usages and development of the successive information management.
Bibliography
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leach, L. P. (2014). Critical chain project management. Artech House.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Buy Inf2040 Project Management For Service Assessment Answers Online
Talk to our expert to get the help with Inf2040 Project Management For Service Assessment Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.