Ict352 Project Management: Tier One Assessment Answers
Project Management Tier One Assessment is a critical evaluation in the realm of project management, designed to assess an individual's or team's knowledge and proficiency in applying project management principles and techniques. These assessments are often a fundamental component of project management courses, certifications, and professional development programs. Typically, Tier One Assessments cover the foundational concepts and core competencies of project management, such as project initiation, planning, execution, monitoring and control, and project closure. Participants may be tested on their ability to create project plans, define objectives and scope, allocate resources, manage risks, and ensure successful project delivery. The assessment may include a variety of question formats, including multiple-choice, scenario-based questions, or even practical exercises, where participants demonstrate their problem-solving and decision-making abilities in a simulated project environment. Successfully completing a Project Management Tier One Assessment is often a prerequisite for progressing to higher-level project management certification levels, such as PMP (Project Management Professional) or PRINCE2 (Projects IN Controlled Environments). It validates an individual's understanding of the fundamental principles and their capability to apply these concepts in real-world project scenarios. Overall, Project Management Tier One Assessments are an essential step in the journey to becoming a proficient and certified project manager, and they help ensure that individuals have a solid foundation in the field to effectively lead and deliver successful projects in various industries and sectors.
Case Study: Tier One Suppliers Insurance Group (TOSIG).
Background:
Tier One Suppliers Insurance Group (TOSIG) offers insurance to tier one suppliers primarily on improvements such as buildings, fencing, stock yards, storage silos and machinery. They also offer insurance for crops. TOSIG have been in business for approximately 65 years and pride themselves on traditional values and maintaining long-term relationships with clients. They underwrite insurance on 6.7 billion dollars worth of risk and have 150 agents in the field, maintaining offices in most major regional primary producing areas. The organisational strategy is to maintain existing customers and increase the number of insurance products offered to clients. They also want to grow their business by increasing sales of insurance to small and medium enterprises in regional areas. Currently it is up to each agent to maintain information on their book of clients although information on policies is kept in a central database.
Approximately every five years a site visit to the client is arranged so that the agent can confirm the details of the items they are currently insuring. At this site visit the agent remeasures and inspects the property insured and enters the information (including the details of the insured) in a form. The agent also has a discussion with the insured about changes in policies and any additional insurance products they may be able to assist with. At the end of the visit the agent must re-enter the information into the TOSIG system and receive a report on the property.
There is concern that TOSIG are missing opportunities to sell more insurance because their agents do not have the ability to receive a report in the field. Another factor is that currently agents spend a considerable about of time in the office entering information into the system from the site visit form, while TOSIG would prefer that they spent more time out in the field visiting potential and existing clients. There is also an awareness at the managerial level that the clients could be risk managed better so that higher risk clients received visits more frequently while visits to low risk clients might be made at a longer intervals or by phone. Currently this risk is managed by individual agents and there is awareness that some agents use these visits as an opportunity to sell more insurance or relationship build rather than managing the insurance risk, for instance they might insure a building for replacement when it is really at the end of its economic life and should be removed from the policy.
TOSIG is also aware of an increased threat from insurance companies who have not traditionally dealt with Tier One Suppliers or have entered the Australian insurance market. Currently the agents are issued with a vehicle, laptop with wireless dongle and Blackberry telephone.
They have planned an upgrade to their information systems, starting with a new customer relationship system. The idea is that the agents will be issued with tablets in which a customer number is entered and a form will be prepopulated with client and policy information. This is to reduce the amount of time the agents spend entering data. They will also be issued with laptops and smart phones which will integrate with the TOSIG systems which will be moved to the cloud. From the company perspective they would prefer that the agents are able to do more work from their vehicle and much less time in the office. The end goal is to close some physical offices to help minimise overhead costs. The agents have become aware of this plan and there is some bad feeling about the plan to close offices. The agents are also resistant to the cloud based system as they are aware this will enable TOSIG to track their movements.
You have been requested to prepare a report by the owners, although they have good technical knowledge, this report may be read by associated business people such as investors and bankers.
It is important to achieve well in this assignment that you discuss this ICT project for Performers Cooperative not ICT projects in general.
This report should address the following issues and you should include the following sections in the main body of the report. Please note standard report structure must be adhered to. There are standard templates available on blackboard for some sections.
Prepare a project plan for the above project. Please include the following sections and follow the instructions contained in chapter 4 of the text.
- Project Background which includes the following sub-sections
- Project Background
- Project goal
- Project objective
- Project Deliverable
- Strategic alignment of project.
- Project Schedule which includes the following sub-sections
- Milestones
- Project requirements
- Limits and exclusions
- Work/ process breakdown schedule
- Time and cost management which includes the following sub-sections
- Time management
- Cost management
- Resource management
- Risk management
- Communication management plan
Answer:
Project Background
Project Background
The technological advancement in the ICT technologies influenced organizations to transform their working practices to the new environment and digitization platform. Tier one supplier insurance group (TOSIG) is the insurance organization which wants to use ICT environment for managing database of their customers to know their current improvement in the profit and turnover earned by the enterprise. The organization believes in providing high quality insurance policies on building, fencing equipment, inventory, and machinery to the participating organizations. The use of online software tools helps in minimising the time spend by the employees in the field area. The purpose of this paper is to design an online web application which helps in managing inter-cooperation between working employees and customers.
Project Goal
The transformation of the current working structure to the new cloud model and its services helps in managing the complexities which is faced by the employees and customers. The inconvenience of the customers in placing their request proposal can be effectively resolved with the cloud based service model. The working hours of the employees can be used for the productive work which was wasted in managing field work previously.
Project Objective
The project objectives are classified as below:
- Inclusion of cloud based service model in the working platform of the enterprise
- Helps in overcoming the complexities faced by the customers in placing their request
- Increasing the working efficiency of the employees
- Minimizing the wastage of working hours and maximising the productivity of the organization
Project Deliverables
The project will delivered a working plan for the implementation of the cloud based technologies in the organization to improve the coordination between participating units for increasing the sale of the insurance policies. The work breakdown structure focuses on the scheduling of project activities which helps in implementing the cloud service model effectively. The development of the resource management plan helps in managing the cost according to the role and responsibilities provided to them. The proactive identification of risks and delivery of risk register helps in developing effective risks mitigation policies. The communication management plan focuses on managing the coordination between the working units of the enterprise for managing the flow of data and information to get accurate result of the final outcome of the project.
Strategic alignment of project
The systematic arrangement of project activities are related to the implementation of the cloud based service model helps in accomplishing the project development within the approved cost and time (Otieno, 2014). The following table shows the alignment of activities for the accomplishment of project activities:
Particular |
Description |
Mission |
The TOSIG organization focuses on implementing cloud architecture for improving the work efficiency of the employees. The centralisation control can be effectively managed between the employees and customers for increasing the sale of the enterprise (Patanakul, 2010). |
Values |
The employees can manage the sale of the insurance policies through the centralization system of cloud architecture. The time spent of the employees in the field work can be minimised with the development of the web portal application. |
Vision |
The automation in the preparation of the database of the customers and sale of the insurance policies for calculating the financial statement of the enterprise. |
Strategy |
The strategic plan should be developed for the transformation of traditional business activities with the cloud based service model to improve the profitability and turnover of the business units (Brown, 2016). |
Balanced score card |
The preparation of the balanced score card helps in analysing the difference between the expected outcome and the actual outcome of the proposed model which is based on cloud services |
Strategic initialization |
The project is decomposed into several activities like planning, requirement gathering, designing, evaluation, testing and execution, and implementation for achieving the strategic objective of the enterprise. |
Project Objectives |
The project objectives are classified as Inclusion of cloud based service model in the working platform of the enterprise, Helps in overcoming the complexities faced by the customers in placing their request, Increasing the working efficiency of the employees, and Minimizing the wastage of working hours and maximising the productivity of the organization (Otieno, 2014) |
Project schedule
Milestones
Milestone |
Duration (Days) |
Start date |
Finish Date |
Responsible authorities |
Development of the scope management plan for the completion |
15 days |
July 12, 2018 |
August 1, 2018 |
Project Manager |
Development of Hardware, software, and network connecting devices |
15 Days |
August 13, 2018 |
August 31, 2018 |
Business Analyst |
Evaluation of required Resources |
7 Days |
October 3, 2018 |
October 11, 2018 |
Business Analyst |
Evaluation of the designed project |
5 Days |
November 6, 2018 |
November 12, 2018 |
Database Developer |
Testing phase |
3 Days |
December 5, 2018 |
December 7, 2018 |
Tester |
Closure of the project |
2 Days |
December 24, 2018 |
December 25, 2018 |
Project Manager |
Project Requirement
Some of the required resources for the project are listed below:
Hardware: The required hardware for the project are
- Black berry mobile phones
- Tablet, Desktop, and Laptops
- Motorcycle
- Wireless networking devices for connection
- Dongles and networking equipment
Software: The required software resources are
- Cloud software
- Big data database management system
- Zigbee, Hadoop file system
- Windows operating system
- Database for storing the information of the customers and organization staff members
Network:
- High broadband connectivity helps in establishing required connection between the participating units.
Limits and Exclusion
The activities which are out of scope management plan of deploying cloud services in the current working structure of the enterprise:
- Monitoring of the working of cloud model program is not developed
- Deployment of training program
- The project should be completed within the budget of $ 130,160
- The project plan should be completed within the period of 150 days.
Work Process Breakdown
Time and Cost Management
Time Management
The time required for completing the project of developing centralised control and automation of services through the cloud service model is 150 days. The project will start on May 30, 2018 and end on 25 December, 2018.
Cost Management
The project cost approved for the implementation of the cloud based model is $ 130,160. The distribution of the cost for different phases of the project is shown below in the table:
Project Phases |
Cost |
Project Initiation |
$ 43,680 |
Project Requirement phase |
$ 29,680 |
Designing and development phase |
$ 14,240 |
Evaluation phase |
$ 15,360 |
Testing Phase |
$ 13,200 |
Implementation and closure phase |
$ 14,000 |
Resource Management plan
Resources | |||
Type of Resources |
Cost |
Total Cost |
Deliverables |
Project manager |
$ 85/ hour |
$ 85,120 |
The project manager is responsible for delivering the project schedule and work breakdown structure for implementing and transforming to cloud based architecture. The division of responsibilities helps in managing the activity schedule for the employees. |
Business analyst |
$ 50/ hour |
$ 11,200 |
The specification of the problem domain helps in analyzing the business requirement to provide centralization and automation in the working processes of the enterprise. |
Programmer (two available) |
$ 50/ hour |
$ 8,640 |
The designing of the database and development of the program code to make it functional for the enterprise is the responsibility of the programmer (Monnappa, 2017). |
Database developer |
$ 50/ hour |
$ 6,400 |
The big data of the enterprise can be effectively managed by deploying Hadoop file system to increase the efficiency of the cloud based services |
Graphical user interface developer |
$ 50/ hour |
$ 9,920 |
The development of the graphical user interface provides a new and easy environment to the customers for placing their request to get required information about the insurance policies (Marks, 2017) |
Tester |
$ 40/ hour |
$ 6,000 |
The testing plan and procedures should be developed for checking the efficiency of the expected outcome of the project |
Administration officer |
$ 30/ hour |
$ 2,880 |
The administration officer is responsible for managing the difference between the expected outcome and the actual services provided by the cloud model. |
|
Total Cost |
$ 130,160 |
|
Risk Management plan
Risk Register |
Risk Consequences |
Risk Probability |
Frequency |
Mitigation policies |
Organizational issues |
The cloud service model requires some infrastructural changes in the business enterprise |
Low |
Once |
The infrastructural changes in the organization can improve the functionality of the cloud services provided to the customers and employees (Lindh, 2012) |
Restriction from the staff members |
The staff members opposes the proposal of transforming current functioning of the enterprise to the new cloud model |
High |
Periodic |
The implementation of the training module helps in improving the capabilities of the employees according to the requirement of the cloud model (Mansfield Community, 2013) |
Difference between expected requirement and actual working of the project |
The problems in managing the functions and services provided by the cloud model according to the requirement plan of TOSIG enterprise |
Medium |
Once |
The periodic meetings should be arranged with the project owner to analyse the correct requirement of the owner and development of the project plan |
Strategic Plan |
Incompetence of the project manager in developing required strategic plan (Kharaiweish, 2013) |
Medium |
Periodic |
Training and development program for the project manager to improve his skills and expertise |
Communication Management plan
Who? |
What? |
When? |
How? |
Whom? |
Project manager |
Development of work breakdown structure
Development of project schedule for the deployment of cloud service model for the TOSIG enterprise
Managing coordination between business units, employees, and customers
Resource Management plan
Scope Development plan |
During the complete project life cycle |
Face to face communication
Telephonic conversation |
Project Owner
Database developer |
Business analyst |
Development of the problem domain
Development of the cleat stating requirement specification plan
Approval from the project owner on the requirement specification plan
Approval of required resources, hardware, and software (Fuzitsu, 2013) |
In the requirement gathering phase |
Face to face communication with the project owner
Survey of the site visit |
Project Manager
Database Designer and Developer |
Programmer |
Programming code |
Designing and development phase |
|
Database Developer
Business analyst |
Database developer |
Development of the database for storing large data and information of the TOSIG enterprise |
Designing and development phase |
|
Programmer
Business analyst |
Graphical User Interface Developer |
Provides graphic Icon for the cloud application development for the business enterprise. The development of the user friendly environment helps in increasing the efficiency of the working employees (Branco, Soares, and Rivero, 2017) |
Designing and development phase |
|
Database Developer
Business analyst |
Tester |
Development of testing procedure
Deployment of the pilot testing program |
Testing and evaluation phase |
Face to face communication |
Database Developer
Programmer |
Administration officer |
Interconnection and cooperation between the various section of the business unit |
Evaluation phase |
Face to face communication |
Project Owner
Project Manager |
References
Branco, T., Soares, F., and Rivero, A. (2017). Key issues for the successful adoption of cloud computing. 1st ed. [ebook]. Available at: https://ac.els-cdn.com/S187705091732207X/1-s2.0-S187705091732207X-main.pdf?_tid=13069957-6347-497d-954f-8e85636a3067&acdnat=1527075444_98c4bb1df299239ac6bf637573f42284 [Accessed 02 June. 2018].
Brown, E. (2016). Strategic project Management. 1st ed. [ebook]. Available at: https://www.researchgate.net/publication/268031840_Strategic_Project_Management_1_Strategic_Project_Management [Accessed 02 June. 2018].
Fujitsu. (2013). Cloud Adoption. 1st ed. [ebook]. Available at: https://notatanycost.com.au/wp-content/uploads/2014/02/senatereport.pdf [Accessed 02 June. 2018].
Kharaiweish, M. (2013). Project Monitoring and control measures. International Journal of computer science and information technology, 5(5). Available at: https://airccse.org/journal/jcsit/5513ijcsit03.pdf [Accessed 02 June. 2018].
Lindh, C. (2012). How does information technology impact on business relationships? The need for personal meetings. 1st ed. [ebook]. Available at: https://www.impgroup.org/uploads/papers/6732.pdf [Accessed 02 June. 2018].
Mansfield Community. (2013). Introduction to project management. 1st ed. [ebook]. Available at: https://www.mansfield.vic.gov.au/Libraries/Community_Development/Intro_to_Project_Management_Manual.sflb.ashx [Accessed 02 June. 2018].
Marks, E. (2017). Designing and implementing cloud governance. 1st ed. [ebook]. Available at: https://www.eiseverywhere.com/file_uploads/8d78b669e86b0120d704469d84fbf680_CLF_2011_Governance_Frameworks_Eric_Marks.pdf [Accessed 02 June. 2018].
Monnappa. (2017). Project scope management: What it is and why it is important. 1st ed. [ebook]. Available at: https://www.simplilearn.com/project-scope-management-importance-rar89-article [Accessed 02 June. 2018].
Otieno, F. (2014). The role of monitoring and evaluation in projects. 1st ed. [ebook]. Available at: https://www.irbnet.de/daten/iconda/CIB8942.pdf [Accessed 02 June. 2018].
Passenheim, O. (2015). Project Management. 1st ed. [ebook]. Available at: https://home.hit.no/~hansha/documents/theses/projectmanagement.pdf [Accessed 02 June. 2018].
Patanakul, P. (2010). An Empirical study on the use of project management tools and techniques across project life cycle and their impact on project success. 1st ed. [ebook]. Available at: https://www.researchgate.net/publication/260059419_An_Empirical_Study_on_the_use_of_Project_Management_Tools_and_Techniques_across_Project_Life-Cycle_and_their_Impact_on_Project_Success [Accessed 02 June. 2018].
Buy Ict352 Project Management: Tier One Assessment Answers Online
Talk to our expert to get the help with Ict352 Project Management: Tier One Assessment Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.