Urgenthomework logo
UrgentHomeWork
Live chat

Loading..

ICT352 ICT Project Management-Scope Management Plan

Identify the desired area of impact - Rank the following areas in terms of importance: Strategy / Customer / Financial / Operational / Social.
Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.
Determine the timeframe for achieving the MOV - ask yourselves, when do we want to achieve this target metric.

Answer:

A show is arranged by BT&Sons every year in November which they call RALS. In this show, they display their agricultural and lifestyle equipment. They sell tickets for the show arranged. They contribute the money they earn by selling tickets for the well-being of the native people to a trust called ICV. The show lasts for three days. There the ticketing system is hand operated so many problems occur, thus RALS decided to transform the hand-operated ticketing system to online ticketing system. For this transformation, BT&Sons gave the project to Virtucon.

Area of Impact:

Rank 1 - Customer:

The customers who will visit show will be very happy and satisfied. This new system will help them in the reservation of tickets before the show begins in November without standing in the queue outside t


he ticket counter.

Rank 2 - Operational:

Majority of customers will reserve their tickets online due to this system so the workload can be reduced.

Rank 3 – Finance:

RALS will get more money as more customers will attend the show.

Rank 4 – Strategy:

Globex will contribute more to ICV as more tickets will be sold and they will earn more.

Rank 5 – Social:

Since Globex will contribute more money to ICV it will become easier for them to show their concerns for the society.

Project value:

Value 1 (Faster):

The workers who manage the ticket counter and the security gate will get relief as there will be no crowd in the main gate and they will be able to do their work faster.

Value 2 (Do more):

Globex will be inspired to develop the show more by these good results.

Metrics & Time target:

Metrics

Target

Fewer workers can fulfill the desires in the main gate and ticket counter

During the show in November

Beginning of  earning money before the beginning of the show

Before the start of RALS

For the increase in income, contribution to ICV by 38% more

After RALS show

Starting with revenue income before the beginning of the show in November

Before the start of RALS

Scope Management Plan

Define Scope (Khan, 2006):

The main target of this project is to develop a web-based computerized ticket reserving system to permit those who visit the show to reserve their tickets online before the show begins in November. This will decrease the workload on the workers in the main gate and ticket counter. The system will be easily open to all devices.

Collect Requirements:

The personal identity proof for first time sign in, open to all devices, free from cyber-attack and a scanner ID for identification of customers should be contained.

In-Scope:

A scanner ID tag for the customer’s identification proof should be there. It should be open to all devices.

Out-of-Scope items/activities:

From upkeep of hardware to provide the support and usage need to be contained in this level.

Deliverables:

The stakeholder’s desires must be fulfilled with the delivery of an accurate, valid and project.

List of Resources:

Resource Name

Notes (Value Based Management, 2016)

Type

Initials

Max. Units

Std. Rate

Accrue At

Executive Sponsor

Responsible for the overall arrangement of funds whenever required

Work

ES

100%

$225.00/hr

Prorated

Project Manager

Overall responsible for the completion of project & coordinate with the internal and external stakeholders

Work

PM

100%

$120.00/hr

Prorated

Web Developer

Develop the web page for booking tickets

Work

WD

100%

$95.00/hr

Prorated

Expert Leader

Overall responsible for the technical matters and implementation of the program

Work

EL

100%

$105.00/hr

Prorated

IT Supporter

Design and Develop the system and database

Work

ITS

100%

$85.00/hr

Prorated

IT Security Team

Design, develop and implement the security features for the system development

Work

ITST

100%

$70.00/hr

Prorated

Executive Stakeholders

Responsible for the overall coordination of the stakeholders

Work

ES

100%

$80.00/hr

Prorated

Vendor

Design, Develop and Implement the System & it’s hardware

Work

VEN

100%

$1,000.00/hr

Prorated

Local Area Network System for connecting all the hardware Printing facility with Internet connectivity Provide training facility & travel

Assumptions

  1. No difficulty needs to be there with the price range of the task.
  2. Resources have to be there for the duration of the project execution.
  3. For schooling the employees after the implementation of the online ticketing machine, they have to be well known.

Risk Analysis (ProjectEngineer, 2017)

RISK No.

Description

Probability

Impact

Product

Rank

Owner

Response / Mitigation

1

During initiation stage: unsuitably recognition of stakeholders

4

4

16

2

Project Manager (PM)

All the identified essentials with the co-workers should be discussed and continued

2

During planning Stage: unsuitable project management could increase the time and work in it, which can further result in delay in project submission

4

5

20

1

PM

After completing the employee's conspicuous evidence they must be changed as necessities

3

During execution stage: many problems may take place during the project execution if not managed properly

3

3

9

4

PM

All the stakeholders should be identified and the project work should be checked after every alteration

4

During monitoring & controlling stage: increase in scope of work if stakeholders are not identified properly

4

3

12

3

PM

Scope checking method like expert study should be done in each level

5

During close-out & evaluation stage: due to incomplete submission the project may get delayed

2

2

4

5

PM

the last conclusions of every stage should be submitted after the movement to diminished totaling up in the last level

Quality Management Plan

Team’s Philosophy for Quality (International Organization for Standardization, 2015):

The meeting tries to save the specified benchmarks of the problem and normally meet the apparent and documented assoc iate's dreams. Every one of the dangers must be checked possibly to avoid any overwhelm of increase in time. All employees must focus on their work to save it from any kind of development.

Verification Activity:

Activity

Target

Client’s dreams are fulfilled

3/April/2018

Project brought on time

3/April/2018

The single spending on any work must now not overshoot the overall finances of the project

3/April/2018

Recognition of risks and response configurations should be grabbed in every level

3/April/2018

Validation Activity:

Activity

Target

Quality standards or rules meet

3/April/2018

Basic things need to be affirmed against set standards or MOV

3/April/2018

Before finishing each level need to be recommended in opposition to every benchmark criteria

3/April/2018

Project Closure & Project Evaluation

  1. Annotated Bibliography is noted in Appendix below.
  2. Project Closure checklist:

Valued criteria earned mist should be maintained inside the project

Quality requirements need to satisfy

All the goals which can be of excessive interest ought to meet

Lessons found out have to be stated with the assignment group and Globex

  1. Project Evaluation:

Can more money be contributed to ICV?

Can the weight of labor at the employees in the price tag counter and safety gate be reduced?

Has the price ticket reserved begun earlier than the beginning of the show?

Will the complete income increase by 38% extra than the remaining year’s collection?

References

Hans, R. T. (2013). WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION. International Journal of Software Engineering & Applications (IJSEA), 4(4), 19-25.

International Organization for Standardization. (2015). Quality Management Principles. ISO Central Secretariat. Geneva, Switzerland: ISO.

Khan, A. (2006). Project Scope Management. Cost Engineering, 48(6), 12-16.

ProjectEngineer. (2017). Retrieved October 14, 2017, from Plan Risk Responses: https://www.projectengineer.net/knowledge-areas/project-risk/plan-risk-responses/

Smartsheet. (2017). All About Online Gantt Chart Software. Retrieved October 14, 2017, from https://www.smartsheet.com/all-about-online-gantt-chart-software-b

Thakur, S. (2011, April 4). How to Prepare a Milestones Report for a Project? Retrieved October 14, 2017, from https://www.brighthubpm.com: https://www.brighthubpm.com/templates-forms/116196-how-to-prepare-a-milestones-report-for-a-project/

Value Based Management. (2016). Agreeing on Roles and Responsibilities: Summary of RACI. Retrieved October 14, 2017, from https://www.valuebasedmanagement.net: https://www.valuebasedmanagement.net/methods_raci.html.


Buy ICT352 ICT Project Management-Scope Management Plan Answers Online

Talk to our expert to get the help with ICT352 ICT Project Management-Scope Management Plan Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for ICT352 ICT Project Management-Scope Management Plan Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.