House Construction
PROJECT MANAGEMENT
Introduction
This project is about the "House construction" project management plan. The project management plan covers different aspects of a house development project. The first thing discloses in the paper is the project's background and objectives. It will serve as a guide for the readers to understand the scenario of the whole project. Moreover, it also covers the role of its key deliverables and stakeholders. The roles and responsibilities of project team members are discussed in respect of project key deliverables. Moreover, the paper also covers an important part of the project management plan which is project time management. The main motive behind the discussion of project time
management is to understand project work breakdown structure, Gantt chart, network diagram, and critical path as well. At last, the project covers the budget and quality plan for the project. All these aspects are studied under the study of previous research sources. Moreover, the project time management and project budget are prepared through the use of advanced software which is MS Project and MS Excel. Both of these tools are an important source of the plan the overall schedule of a particular project.
Project Background and Objectives
Project Background
The project is about the preparation of a complete house in Oman City. The premises shall be handed over to the owner no later than 1st August 2019. The contract price for the project will remain at OMR 130,000. Generally, the house will prepare as per the requirements of the owner. It will include a ground floor with four different rooms, one kitchen, and one washroom set. Apart from this, it will also include construction of the first floor with 3 different rooms and one set of the kitchen as well as washrooms. The house will properly cover with the latest tiles and appropriate design and structure. It will involve the groundworks, materials, structure, project management, interior, services, signoff, and exterior systems. Moreover, it also has a pool and garden for the entertainment of family members.
Project Objectives
The project objective is to prepare a well-organized house Design
Accomplish the project within the budget of OMR 130,000.
Project Team Members and their key roles
The project involves a large number of project team members. It is because the home needs to construct within one year from its initial starting date. The key project team member involved in the project is following:
Owner: The owner is the person responsible for the whole management and evaluation of his or her house. The owner will sponsor the Housing construction team members to build his or her house (Alwan, 2017). He or she will remain responsible for providing necessary funds.
Design-Builder: These are the team members who will remain responsible for the overall structural design of the project and will oversee the activities done by the labor and another person.
Architect: The architect will prepare the effective blueprint of the owner's house so that he or she can live effectively with all facilities.
Civil Engineer: These are the individual who directly responsible for the evaluation of construction work. They will guide the team members in performing their tasks and responsibilities (Banihashemi, 2017). This group involves electrical, structural, project manager, mechanics, and various other people.
Landscape: The landscaping team is responsible for the landscaping tasks. It involves the construction of a yard, garden, and pool which will perform by plan mechanics, and other labors (Clevenger, 2017).
Project Stages and Key Deliverables
The project stages and their key deliverables can understand with the help of the 4D model of project management. It is an exciting and appropriate concept for the management of housing and other complex projects
(Burtonshaw-Gunn, 2017).
(Kerzner, 2017)
Define
The "Housing Construction" project is conducted with the sole aim of prepares an attractive and best design house with the presence of a garden, pool, and two different floors. It will start on the 1st of May 2018 and finish on 30th July 2019. It will consume the construction process of one year and three months. In order to accomplish the project as per predetermined timeline, the project management team will keep strict towards their goals and deadline as well.
Design
The design of the house will be unique and different from other nearby
houses. The project will integrate with the following design:
Spacious kitchen with plenty of storage
Creation of keeping rooms
Master bath
Bedroom on both floors (Mubarak, 2015)
Covers entrance
Attractive design pool with best tiles
Garden with plenty of plants
Development
The project development will perform as per the below-mentioned procedure:
From the above-mentioned figure, it can clarify that the implementation process of the house will proceed accordingly. The contractor will remain responsible for the continuous evaluation of Groundworks, materials, structure, and project management procedure of the project so that any delay can avoid effectively (Marsh, 2015).
Deliver
The project delivery will perform by sharing the project quality and progress report (Merschbrock, 2015). It will give surety to the client about the project specifications. At this stage, the owner takes the responsibility of his or her home and makes necessary payments if anything left.
Project Time Management
Work Breakdown Structure
Mubarak (2015) said that the work breakdown structure represents the overall activity involved in the accomplishment of a project. The work breakdown structure for "Housing Construction" project is prepared through the use of advanced software known as MS Project. It is an important method of preparing work breakdown structure with required specifications (Merschbrock, 2015). The work breakdown structure for housing construction project can understand with a below-mentioned table:
Task Mode |
Task Name |
Duratio n |
Start |
Finish |
Predecess ors |
Resource Names |
Auto Schedu led |
House Construction at Oman |
310 days |
Tue 5/1/18 |
Mon 7/8/19 | ||
Auto Schedu led |
Conduct Ground Work |
100 days |
Tue 5/1/18 |
Mon 9/17/18 | ||
Auto Schedul ed |
Concrete works |
55 days |
Tue 5/1/18 |
Mon 7/16/18 |
Laborer | |
Auto Schedu led |
Excavation |
45 days |
Tue 7/17/18 |
Mon 9/17/18 | ||
Auto Schedul ed |
Pool |
15 days |
Tue 7/17/18 |
Mon 8/6/18 |
3 |
Plant Mechanic, Site Joiner |
Auto Schedul ed |
Foundation |
30 days |
Tue 8/7/18 |
Mon 9/17/18 |
5 |
Client |
Auto Schedu led |
Perform Landscaping |
90 days |
Tue 9/18/18 |
Mon 1/21/19 | ||
Auto |
Pool |
40 days |
Tue |
Mon |
5,6 |
Laborer |
Schedul ed |
9/18/18 |
11/12/1 8 | ||||
Auto Schedul ed |
Yard |
20 days |
Tue 11/13/1 8 |
Mon 12/10/1 8 |
8 |
Plant Mechanic |
Auto Schedul ed |
Gardens |
30 days |
Tue 12/11/1 8 |
Mon 1/21/19 |
8,9 |
Plant Mechanic |
Auto Schedu led |
Arrange Materials |
80 days |
Tue 12/11/1 8 |
Mon 4/1/19 | ||
Auto Schedul ed |
Project Management |
25 days |
Tue 12/11/1 8 |
Mon 1/14/19 |
9 |
Laborer |
Auto Schedul ed |
Storage |
40 days |
Tue 1/22/19 |
Mon 3/18/19 |
10 |
Plant Mechanic |
Auto Schedul ed |
Delivery |
10 days |
Tue 3/19/19 |
Mon 4/1/19 |
12,13 |
Site Joiner |
Auto Schedu |
Give Structure |
86 days |
Tue 9/18/18 |
Tue 1/15/19 |
led |
| |||||
Auto Schedul ed |
Timber |
44 days |
Tue 9/18/18 |
Fri 11/16/1 8 |
6 |
Steel structural |
Auto Schedul ed |
Masonry |
22 days |
Mon 11/19/1 8 |
Tue 12/18/1 8 |
16 |
Site Joiner |
Auto Schedul ed |
Steel |
20 days |
Wed 12/19/1 8 |
Tue 1/15/19 |
17 |
Steel structural |
Auto Schedu led |
Design House Interior |
61 days |
Wed 1/16/19 |
Wed 4/10/19 | ||
Auto Schedul ed |
Lining |
26 days |
Wed 1/16/19 |
Wed 2/20/19 |
18 |
Painter and Decorator |
Auto Schedul ed |
Kitchen/Bathroom |
10 days |
Thu 2/21/19 |
Wed 3/6/19 |
20 |
Laborer |
Auto Schedul ed |
Storage |
10 days |
Thu 3/7/19 |
Wed 3/20/19 |
21 |
Roofer |
Auto Schedul ed |
Decorating |
15 days |
Thu 3/21/19 |
Wed 4/10/19 |
22 |
Painter and Decorator |
Auto Schedu led |
Arrange Services |
48 days |
Thu 2/21/19 |
Mon 4/29/19 | ||
Auto Schedul ed |
Plumbing |
5 days |
Thu 4/11/19 |
Wed 4/17/19 |
23 |
Laborer |
Auto Schedul ed |
Electrical |
8 days |
Thu 4/18/19 |
Mon 4/29/19 |
25 |
Electrician |
Auto Schedul ed |
Data |
4 days |
Thu 2/21/19 |
Tue 2/26/19 |
20 |
Site Joiner |
Auto Schedul ed |
Entertainment |
9 days |
Wed 2/27/19 |
Mon 3/11/19 |
27 |
Site Joiner |
Auto Schedul ed |
Security |
12 days |
Tue 3/12/19 |
Wed 3/27/19 |
28 |
Client |
Auto |
Pool |
17 days |
Thu |
Fri |
29 |
Roofer |
Schedul ed |
3/28/19 |
4/19/19 | ||||
Auto Schedu led |
Perform Cladding |
56 days |
Mon 4/22/19 |
Mon 7/8/19 | ||
Auto Schedu led |
Roofing |
39 days |
Mon 4/22/19 |
Thu 6/13/19 | ||
Auto Schedul ed |
Tiling |
19 days |
Mon 4/22/19 |
Thu 5/16/19 |
30 |
Roofer |
Auto Schedul ed |
Insulation |
20 days |
Fri 5/17/19 |
Thu 6/13/19 |
33 |
Roofer |
Auto Schedu led |
Walls |
56 days |
Mon 4/22/19 |
Mon 7/8/19 | ||
Auto Schedul ed |
Exterior |
24 days |
Mon 4/22/19 |
Thu 5/23/19 |
30 |
Plant Mechanic |
Auto Schedul |
Insulation |
32 days |
Fri 5/24/19 |
Mon 7/8/19 |
36 |
Electrician |
ed | ||||||
Auto Schedul ed |
Joinery |
14 days |
Mon 4/22/19 |
Thu 5/9/19 |
30 |
Client |
Auto Schedul ed |
Paint |
15 days |
Fri 5/10/19 |
Thu 5/30/19 |
38 |
Painter and Decorator |
Auto Schedul ed |
Project closure |
0 days |
Thu 5/30/19 |
Thu 5/30/19 |
39 |
Client |
Activity list
Task Name |
WBSID |
Activity |
Predecesso rs |
Duration in |
Resource Type |
Weeks | |||||
House Construction at Oman | |||||
Conduct Ground Work |
1 | ||||
Concrete works |
1.1 |
Complete foundation s |
Excavation |
1.2 |
Complete Excavatio ns | |||
Pool |
1.2.1 | ||||
Foundation |
1.2.2 | ||||
Perform Landscaping |
2 |
Complete landscapi ng package | |||
Pool |
2.1 | ||||
Yard |
2.2 | ||||
Gardens |
2.3 | ||||
Arrange Materials |
3 |
Perform effective material managem ents | |||
Project Management |
3.1 |
Perform project manageme nt | |||
Storage |
3.2 |
Delivery |
3.3 | ||||
Give Structure |
4 |
Complete structure | |||
Timber |
4.1 | ||||
Masonry |
4.2 | ||||
Steel |
4.3 | ||||
Design House Interior |
5 |
Effective completion of house interior | |||
Lining |
5.1 | ||||
Kitchen/Bathroom |
5.2 | ||||
Storage |
5.3 | ||||
Decorating |
5.4 | ||||
Arrange Services |
6 |
Get best house services | |||
Plumbing |
6.1 | ||||
Electrical |
6.2 | ||||
Data |
6.3 |
Entertainment |
6.4 | ||||
Security |
6.5 | ||||
Pool |
6.6 | ||||
Perform Cladding |
7 |
Exterior cladding systems and decoratio n | |||
Roofing |
7.1 | ||||
Tiling |
7.2 | ||||
Insulation |
7.3 | ||||
Walls |
8 |
Ensure effective design of walls | |||
Exterior |
8.1 | ||||
Insulation |
8.2 | ||||
Joinery |
8.3 | ||||
Paint |
8.4 | ||||
Project closure |
9 |
Perform project | |||
closing facilities |
Gantt chart
The below-mentioned figures represent the Gantt chart for the “Housing construction” Project. It is also prepared through the effective use of MS project management software.
Figure 1
Figure 2
Figure 3
Network Diagram
The Network Diagram for the “Housing Construction project” can understand through the below-mentioned figures:
Figure 1
Critical Path
The Critical Path for the “Housing Construction project” can understand through the below-mentioned figures:
Figure 1
Figure 2
Figure 3
Project Budget
The project budget can understand through the below-mentioned table prepared by using the MS Excel:
Task Name |
Budget (OMR) |
Total (OMR) |
House Construction at |
128600 |
Oman |
Conduct Ground Work |
Concrete works |
Excavation |
Pool |
Foundation |
Perform Landscaping |
Pool |
Yard |
Gardens |
Arrange Materials |
Project Management |
Storage |
Delivery |
Give Structure |
Timber |
Masonry |
Steel |
Design House Interior |
Lining |
49600 23200 |
49600 |
23200 54400 17400 |
46400 |
18000 3000 5000 |
89800 |
2000 124000 60000 |
10000 |
41000 |
225000 |
29600
Kitchen/Bathroom |
Storage |
Decorating |
Arrange Services |
Plumbing |
Electrical |
Data |
Entertainment |
Security |
Pool |
Perform Cladding |
Roofing |
Tiling |
Insulation |
Walls |
Exterior |
Insulation |
Joinery |
Paint |
Project closure |
54000 5000 6000 7000 9000 7500 |
135700 |
14000 38600 |
48500 |
14900 47200 14800 33600 |
53500 |
27000 |
122600 |
6000 |
6000 |
42200
9900
On the basis of the above-mentioned project schedule, it can clearly understand that the project can finish within the predetermined budget. It will consume the total cost of OMR128, 600.
Project Quality Plan
Project Quality Responsibilities
The project owner delegated the project quality responsibility to management levels of the project. In order to construct a good house, the project contractor, supervisory team, and engineering manager will remain responsible. The project contractor will ensure that the project outcomes effectively represent the owner specifications (Kerzner, 2018). On the other hand, the project manager will oversee the speed, efficiency, and economical completion of the overall project to avoid any unnecessary delay. Moreover, the engineering manager will ensure the project quality by continuous evaluation of project execution plan, construction process, and engineering codes and standards (Nicholas, 2017).
Quality Criteria
The quality of new house will judge on the basis of below-mentioned aspects:
Quality assurance Criteria |
Key aspects |
In General |
Age of the building Building layout Building size and type |
The condition of Structure Interior (Oakland, 2017) | |
Structure |
Structural span Construction Technology |
Common Areas |
Building Entrance Corridor, and Stairs |
Building Lot |
Pool Garden Parking space Presence and quality of common areas like washroom, kitchen, and bedroom (Sears, 2015) |
Other |
Utilities (Public Water supply, Garbage disposal, heating, electricity, sewage, and streets) Fire Escape and Protection |
Quality Methods
In order to evaluate the quality of the project, the two important methods will follow here. These methods are following:
QUALITY REGISTER |
FORM Ref: Ve | |
Programme Name: Project Management |
Project Name: House Constru | |
Quality Identifier: 1 |
Product Identifier: 1.1 | |
Product Title: Ground works |
Quality Method: Quality review | |
Roles/Responsibilities: Quality reviews and Project audit team members |
Result: Pass | |
Quality Records: Continuous Evaluation |
DATES | |
Planned | ||
Quality |
Process Checklists: At this stage, a list of critical tasks will prepare to evaluate it against the predetermined work breakdown structure. This will give information about any tendency in project accomplishment and breakdown schedule (Tedla, 2018).
Comparison of project outcomes against standard Criteria: Here, the project outcomes will compare the above-mentioned standard criteria to find any problem.
Project Quality Register
Project Risk Register
RISK REGISTER |
FORM Ref: Vers | ||||||
Programme Name: Project Management |
Project Name: House Construct | ||||||
Risk Identifier: 001 |
Risk Description: Failure to identify the project dependency on other team members | ||||||
Probability: 3 |
Impact: High |
Expected Value: High | |||||
Risk Response Category: Reduce | |||||||
Risk Response: Outline dependency to avoid any confusion | |||||||
Date Registered: 16th August |
Risk Author: Project Management Team |
Risk Owner: Project Management Team |
Risk Action: Project Management Tea |
The project is covered with a large number of risk factors. It can understand through the below-mentioned risk register:
Conclusion
On the basis of the above-mentioned analysis, it can be concluded that the success chances of the project are high than its failure. It is because the owner needs not to hire a big team for its management. Moreover, the project schedule and budget structure should effectively follow by the team to avoid any unnecessary delay and cost overrun problem. This will enhance the quality of generated project outcomes.
Resources
- 24 x 7 Availability.