Epm5700 Installation Of New Information Assessment Answers
Prepare Project Scope.
List of assumptions used in the project (if any)
Planning methodology – outline the technique for the delivery of the project.
Use Template to prepare the full report on Project Charter
Stage 2 (Wk. 4-7) – WBS and Manual Scheduling (15%)
Project calendar showing start and finish dates, weekends, RDO’s, and public holidays, etc.
Develop a Work Breakdown Structure (WBS), an Organisation Break Down Structure (OBS) and a Responsibility Assignment Matrix (RAM).
List of tasks, durations and their logical relationship.
Execution program (a manual PDM diagram or a Gantt chart).
Estimate the cost of the project as per the WBS and listed activities.
Develop a risk register using RBS as per WBS to identify and prioritize all risk associated with this project.
Sub-contractors schedule for the project.
References if any.
Each group must obtain the costs for carrying out each activity. Use Cordell’s Estimating Guide OR Rawlinson’s Estimating Handbook for reference
Answer:
The project of Installation of New Information Technology Center had been developed for forming the foundation of the efficient and better communication center installation for the organization. The involvement of the processes was installed for easing the execution of the information processing using the New Information Technology Center. The charter documentation had been developed for aligning with the compilation of the efficient and smart information processing.
The use of the proper management plan documentation was helpful for easing the flow of information and listing the taking care of the efficient and smart processing network. The information technology installation was supported by the use of the smart and efficient plan installation. The document had served as an initial project plan documentation for easing the progress of the project.
Project Overview
The implication of the better New Information Technology Center was required for making sure that the information access and storage can be done more efficiently. The main purpose of the project was aligned for supporting the implementation of the factors defining the using of the better functional and efficient documentation. The project completion would result in listing the foundation of the better communication and foundation of the factors defining the support and installation using smart processing. The ease of information transfer would also allow the improvement of the factors defining the successful foundation of operations.
The project plan installation would align for easing the simplicity of the information technology center installation. The organization had needed the probability of forming the system foundation and installation. The organization had been facing the probable issues in listing the formation of the better analysis. The New Information Technology Center would allow the simplification of the activities for listing the formation of the efficient and better data processing. The new technology centre is required for easing the existing operations of the organization and provides scope for better information transfer and installation. The project completion would result in listing the foundation of the better communication and foundation of the factors defining the support and installation using smart processing.
Scope Statements
The new IT center was efficiently developed with the aim for easing the information installation and taking care of the activities. The installation had been done with the help of proper project management processes and information installation. The project scope can be divided into in scope and out of scope. The following table would highlight the in scope and out scope items of the project of new IT center installation,
In Scope: The in scope items are those items of the project that was one of the major deliverable for the project. The project activities would involve these elements and it is very important for ensuring the completion of the project. The Construction of infrastructure, Installation of the new equipments, Project Plan Documentation, Resource Management Plan, Procurement Plan, and Closure Report are the in scope items of the project.
Out of Scope: The out of scope are those items that are not a part for this project and do not form any direct impact on the project. The Transportation Cost and Recruitment plan are not a part of this project are the out of scope items of the project.
Scope Statement: The project scopes for using the project management principles and developing the efficient using of the operations for easing the information center installation with the help of innovative technology. The ease of information transfer would also allow the improvement of the factors defining the successful foundation of operations.
Stakeholders and Key Personnel Project Organization
The project requires the support and installation using the efficient and better IT center for the organization. The organization had needed the probability of forming the system foundation and installation. The new technology centre is required for easing the existing operations of the organization and provides scope for better information transfer and installation. The activities and operations of the organization was better with the foundation of the new center with all the new equipments and technology devices.
The ease of information transfer would also allow the improvement of the factors defining the successful foundation of operations. The project completion would require the use of the IT project management and principles of construction projects. The major requirement of developing the better operations for the organization was resulted by the installation of the new information technology center. The main purpose of the project was aligned for supporting the implementation of the factors defining the using of the better functional and efficient documentation.
Program Management
The project of installation of new information technology center was efficiently developed aligning with the formation of the waterfall based project plan installation. The project program has been developed using the waterfall model and it involves the sequential execution of the project activities aligning with the formation of the smart project execution. The complete program is divided into initiation phase, plan installation phase, design phase, installation phase, inspection and testing, and closure. The explanation of these phases is given below,
Initiation Phase: The initiation phase involves the initial activities that results in initialization of the project by collecting information and foundation of the functions supporting the execution of the project. It comprises of requirement analysis, tender documentation, charter documentation, resource accumulation, and reviews and signs off.
Plan Installation Phase: The plan installation phase was based on the foundation of the smart processing and using of the factors aligning with the simplification of the efficient factors. It includes the activities of activities are identified, scheduling of the activities, outline of the plan, complete plan installation, and plan approval.
Design Phase: The design phase comprise of evaluation of the design principles and developing design for both centre infrastructure and the IT equipment installation. The center design includes the activities of hiring an architect, building design requirements are given, design outline is made, complete design is developed, and design approval. The IT facility and equipment design includes design platform is selected, IT equipment set up is designed, complete set up is made, and IT set up approval.
Installation Phase: The installation phase involves the installation of the infrastructure and IT technology set up. The construction activities would include hiring a contractor, center infrastructure design is given, site clearing and leveling, ground works are made, infrastructure is developed, roof works, interior is developed, painting of the walls, complete infrastructure is developed, and construction work completion. The IT facility and equipment installation includes equipments and devices are bought, installation plan is followed, equipments and devices are installed, set up is reviewed, and set up work completed.
Inspection and Testing: In this phase, the developed functions was evaluated and tested for any errors. The activities include in this phase are alpha testing, beta testing, simulation, trial and error method, safety installation review, and inspection and testing completed.
Closure: The final phase of the project resulting in closing the execution of the project activities including final documents are made, review and sign off, and closed.
Work Breakdown Structure and Schedule
The work breakdown is the representation of the project in specific work packages comprising of the activities required for the project schedule. The work packages of the project include initiation phase, plan installation phase, design phase, installation phase, inspection and testing, and closure. The diagrammatical and the tabular representation of the project work breakdown structure is shown below.
Work Package Number |
Work Package Task Name |
1 |
Initiation Phase |
1.1 |
Requirement Analysis |
1.2 |
Tender Documentation |
1.3 |
Charter Documentation |
1.4 |
Resource Accumulation |
1.5 |
Review and Sign off |
2 |
Plan Installation Phase |
2.1 |
Activities are identified |
2.2 |
Scheduling of the activities |
2.3 |
Outline of the plan |
2.4 |
Complete Plan Installation |
2.5 |
Plan Approval |
3 |
Design Phase |
3.1 |
Center Design |
3.1.1 |
Hiring an Architect |
3.1.2 |
Building Design Requirements are given |
3.1.3 |
Design Outline is made |
3.1.4 |
Complete Design is developed |
3.1.5 |
Design Approval |
3.2 |
IT Facility and Equipment Design |
3.2.1 |
Design Platform is selected |
3.2.2 |
IT equipment Set up is designed |
3.2.3 |
Complete Set up is made |
3.2.4 |
IT Set Up Approval |
4 |
Installation Phase |
4.1 |
Construction Activities |
4.1.1 |
Hiring a Contractor |
4.1.2 |
Center Infrastructure Design is given |
4.1.3 |
Site Clearing and Leveling |
4.1.4 |
Ground Works are made |
4.1.5 |
Infrastructure is developed |
4.1.6 |
Roof Works |
4.1.7 |
Interior is developed |
4.1.8 |
Painting of the walls |
4.1.9 |
Complete Infrastructure is developed |
4.1.10 |
Construction work Completion |
4.2 |
IT Facility and Equipment Installation |
4.2.1 |
Equipments and Devices are Bought |
4.2.2 |
Installation Plan is followed |
4.2.3 |
Equipments and Devices are Installed |
4.2.4 |
Set Up is reviewed |
4.2.5 |
Set Up work Completed |
5 |
Inspection and Testing |
5.1 |
Alpha Testing |
5.2 |
Beta Testing |
5.3 |
Simulation |
5.4 |
Trial and Error Method |
5.5 |
Safety Installation Review |
5.6 |
Inspection and Testing Completed |
6 |
Closure |
6.1 |
Final Documents are made |
6.2 |
Review and Sign off |
6.3 |
Closed |
The project has been developed using the waterfall model and it involves the sequential execution of the project activities aligning with the formation of the smart project execution. The following is the project schedule,
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
0 |
Installation of New Information Technology Center |
75 days |
Mon 9/3/18 |
Fri 12/14/18 | |
1 |
Initiation Phase |
14 days |
Mon 9/3/18 |
Thu 9/20/18 | |
1.1 |
Requirement Analysis |
3 days |
Mon 9/3/18 |
Wed 9/5/18 | |
1.2 |
Tender Documentation |
2 days |
Thu 9/6/18 |
Fri 9/7/18 |
2 |
1.3 |
Charter Documentation |
6 days |
Mon 9/10/18 |
Mon 9/17/18 |
3 |
1.4 |
Resource Accumulation |
3 days |
Tue 9/18/18 |
Thu 9/20/18 |
4 |
1.5 |
Review and Sign off |
0 days |
Thu 9/20/18 |
Thu 9/20/18 |
5 |
2 |
Plan Installation Phase |
12 days |
Fri 9/21/18 |
Mon 10/8/18 | |
2.1 |
Activities are identified |
2 days |
Fri 9/21/18 |
Mon 9/24/18 |
6 |
2.2 |
Scheduling of the activities |
3 days |
Tue 9/25/18 |
Thu 9/27/18 |
8 |
2.3 |
Outline of the plan |
2 days |
Fri 9/28/18 |
Mon 10/1/18 |
9 |
2.4 |
Complete Plan Installation |
5 days |
Tue 10/2/18 |
Mon 10/8/18 |
10 |
2.5 |
Plan Approval |
0 days |
Mon 10/8/18 |
Mon 10/8/18 |
11 |
3 |
Design Phase |
11 days |
Tue 10/9/18 |
Tue 10/23/18 | |
3.1 |
Center Design |
11 days |
Tue 10/9/18 |
Tue 10/23/18 | |
3.1.1 |
Hiring an Architect |
1 day |
Tue 10/9/18 |
Tue 10/9/18 |
12 |
3.1.2 |
Building Design Requirements are given |
2 days |
Wed 10/10/18 |
Thu 10/11/18 |
15 |
3.1.3 |
Design Outline is made |
3 days |
Fri 10/12/18 |
Tue 10/16/18 |
16 |
3.1.4 |
Complete Design is developed |
5 days |
Wed 10/17/18 |
Tue 10/23/18 |
17 |
3.1.5 |
Design Approval |
0 days |
Tue 10/23/18 |
Tue 10/23/18 |
18 |
3.2 |
IT Facility and Equipment Design |
9 days |
Tue 10/9/18 |
Fri 10/19/18 | |
3.2.1 |
Design Platform is selected |
1 day |
Tue 10/9/18 |
Tue 10/9/18 |
12 |
3.2.2 |
IT equipment Set up is designed |
3 days |
Wed 10/10/18 |
Fri 10/12/18 |
21 |
3.2.3 |
Complete Set up is made |
5 days |
Mon 10/15/18 |
Fri 10/19/18 |
22 |
3.2.4 |
IT Set Up Approval |
0 days |
Fri 10/19/18 |
Fri 10/19/18 |
23 |
4 |
Installation Phase |
30 days |
Mon 10/22/18 |
Fri 11/30/18 | |
4.1 |
Construction Activities |
28 days |
Wed 10/24/18 |
Fri 11/30/18 | |
4.1.1 |
Hiring a Contractor |
1 day |
Wed 10/24/18 |
Wed 10/24/18 |
19 |
4.1.2 |
Center Infrastructure Design is given |
1 day |
Thu 10/25/18 |
Thu 10/25/18 |
27 |
4.1.3 |
Site Clearing and Leveling |
3 days |
Fri 10/26/18 |
Tue 10/30/18 |
28 |
4.1.4 |
Ground Works are made |
2 days |
Wed 10/31/18 |
Thu 11/1/18 |
29 |
4.1.5 |
Infrastructure is developed |
5 days |
Fri 11/2/18 |
Thu 11/8/18 |
30 |
4.1.6 |
Roof Works |
3 days |
Fri 11/9/18 |
Tue 11/13/18 |
31 |
4.1.7 |
Interior is developed |
4 days |
Wed 11/14/18 |
Mon 11/19/18 |
32 |
4.1.8 |
Painting of the walls |
2 days |
Tue 11/20/18 |
Wed 11/21/18 |
33 |
4.1.9 |
Complete Infrastructure is developed |
7 days |
Thu 11/22/18 |
Fri 11/30/18 |
34 |
4.1.10 |
Construction work Completion |
0 days |
Fri 11/30/18 |
Fri 11/30/18 |
35 |
4.2 |
IT Facility and Equipment Installation |
11 days |
Mon 10/22/18 |
Mon 11/5/18 | |
4.2.1 |
Equipments and Devices are Bought |
1 day |
Mon 10/22/18 |
Mon 10/22/18 |
24 |
4.2.2 |
Installation Plan is followed |
1 day |
Tue 10/23/18 |
Tue 10/23/18 |
38 |
4.2.3 |
Equipments and Devices are Installed |
6 days |
Wed 10/24/18 |
Wed 10/31/18 |
39 |
4.2.4 |
Set Up is reviewed |
3 days |
Thu 11/1/18 |
Mon 11/5/18 |
40 |
4.2.5 |
Set Up work Completed |
0 days |
Mon 11/5/18 |
Mon 11/5/18 |
41 |
5 |
Inspection and Testing |
36 days |
Wed 10/17/18 |
Wed 12/5/18 | |
5.1 |
Alpha Testing |
2 days |
Mon 10/22/18 |
Tue 10/23/18 |
23 |
5.2 |
Beta Testing |
2 days |
Wed 10/24/18 |
Thu 10/25/18 |
44 |
5.3 |
Simulation |
2 days |
Fri 10/26/18 |
Mon 10/29/18 |
45 |
5.4 |
Trial and Error Method |
3 days |
Wed 10/17/18 |
Fri 10/19/18 |
17 |
5.5 |
Safety Installation Review |
3 days |
Mon 12/3/18 |
Wed 12/5/18 |
35 |
5.6 |
Inspection and Testing Completed |
0 days |
Wed 12/5/18 |
Wed 12/5/18 |
46, 47, 48 |
6 |
Closure |
7 days |
Thu 12/6/18 |
Fri 12/14/18 | |
6.1 |
Final Documents are made |
5 days |
Thu 12/6/18 |
Wed 12/12/18 |
36, 42, 49 |
6.2 |
Review and Sign off |
2 days |
Thu 12/13/18 |
Fri 12/14/18 |
51 |
6.3 |
Closed |
0 days |
Fri 12/14/18 |
Fri 12/14/18 |
52 |
A Gantt chart is helpful for evaluating the concept of efficient and smart project execution management and foundation of the better project timeline identification. The following is the diagram for representing the project activities and schedule,
PDM Network Diagram Cost Management Plan
The cost management plan is the process of analysing the resources and providing efficient completion of the project activities. The analysis of the efficient cost management plan was done by following the steps of resource analysis and work analysis. The resources was identified for the work that needs to be done in the project. Each of the activities of the project was assigned with some resources (either human or material) for execution. The following table is the identification of the resources required for the execution of the project activities,
Resource Name |
Type |
Work |
Standard Rate |
Cost |
Analyst |
Work |
24 hrs |
$50.00/hr |
$1,200.00 |
Documenter |
Work |
104 hrs |
$60.00/hr |
$6,240.00 |
Project Manager |
Work |
64 hrs |
$150.00/hr |
$9,600.00 |
Planner |
Work |
96 hrs |
$70.00/hr |
$6,720.00 |
Client |
Work |
16 hrs |
$0.00/hr |
$0.00 |
Architect |
Work |
64 hrs |
$95.00/hr |
$6,080.00 |
Designer |
Work |
72 hrs |
$85.00/hr |
$6,120.00 |
Workers |
Work |
208 hrs |
$100.00/hr |
$20,800.00 |
Contractor |
Work |
208 hrs |
$120.00/hr |
$24,960.00 |
Engineer |
Work |
88 hrs |
$125.00/hr |
$11,000.00 |
Tester |
Work |
96 hrs |
$90.00/hr |
$8,640.00 |
Documents |
Material |
3 |
$120.00 |
$360.00 |
Construction Materials |
Material |
1 |
$15,000.00 |
$15,000.00 |
Paints |
Material |
1 |
$2,500.00 |
$2,500.00 |
Furniture and Fixture |
Material |
1 |
$4,500.00 |
$4,500.00 |
Fire Safety Devices |
Material |
1 |
$2,000.00 |
$2,000.00 |
Equipments and Devices |
Material |
1 |
$12,000.00 |
$12,000.00 |
Testing Tools |
Material |
3 |
$760.00 |
$2,280.00 |
However, the cost management has one more factor and it is work management which includes the analysis of the cost for each of the activities of the project. The foundation of the better cost management was supported by the using of the resources for each of the project activity. The following table would show the resource analysis for the project installation,
WBS |
Task Name |
Resource Names |
Cost |
1.1 |
Requirement Analysis |
Analyst |
$1,200.00 |
1.2 |
Tender Documentation |
Documenter, Documents[1] |
$1,080.00 |
1.3 |
Charter Documentation |
Documenter, Documents[1] |
$3,000.00 |
1.4 |
Resource Accumulation |
Project Manager |
$3,600.00 |
1.5 |
Review and Sign off |
$0.00 | |
2.1 |
Activities are identified |
Planner |
$1,120.00 |
2.2 |
Scheduling of the activities |
Planner |
$1,680.00 |
2.3 |
Outline of the plan |
Planner |
$1,120.00 |
2.4 |
Complete Plan Installation |
Planner |
$2,800.00 |
2.5 |
Plan Approval |
$0.00 | |
3.1.1 |
Hiring an Architect |
Project Manager |
$1,200.00 |
3.1.2 |
Building Design Requirements are given |
Client |
$0.00 |
3.1.3 |
Design Outline is made |
Architect |
$2,280.00 |
3.1.4 |
Complete Design is developed |
Architect |
$3,800.00 |
3.1.5 |
Design Approval |
$0.00 | |
3.2.1 |
Design Platform is selected |
Designer |
$680.00 |
3.2.2 |
IT equipment Set up is designed |
Designer |
$2,040.00 |
3.2.3 |
Complete Set up is made |
Designer |
$3,400.00 |
3.2.4 |
IT Set Up Approval |
$0.00 | |
4.1.1 |
Hiring a Contractor |
Project Manager |
$1,200.00 |
4.1.2 |
Center Infrastructure Design is given |
Project Manager |
$1,200.00 |
4.1.3 |
Site Clearing and Leveling |
Workers, Contractor |
$5,280.00 |
4.1.4 |
Ground Works are made |
Workers, Contractor |
$3,520.00 |
4.1.5 |
Infrastructure is developed |
Workers, Contractor, Construction Materials[1] |
$23,800.00 |
4.1.6 |
Roof Works |
Workers, Contractor |
$5,280.00 |
4.1.7 |
Interior is developed |
Workers, Contractor, Furniture and Fixture[1] |
$11,540.00 |
4.1.8 |
Painting of the walls |
Workers, Contractor, Paints[1] |
$6,020.00 |
4.1.9 |
Complete Infrastructure is developed |
Workers, Contractor, Fire Safety Devices[1] |
$14,320.00 |
4.1.10 |
Construction work Completion |
$0.00 | |
4.2.1 |
Equipments and Devices are Bought |
Engineer, Equipments and Devices[1] |
$13,000.00 |
4.2.2 |
Installation Plan is followed |
Engineer |
$1,000.00 |
4.2.3 |
Equipments and Devices are Installed |
Engineer |
$6,000.00 |
4.2.4 |
Set Up is reviewed |
Engineer |
$3,000.00 |
4.2.5 |
Set Up work Completed |
$0.00 | |
5.1 |
Alpha Testing |
Tester, Testing Tools[1] |
$2,200.00 |
5.2 |
Beta Testing |
Tester, Testing Tools[1] |
$2,200.00 |
5.3 |
Simulation |
Tester, Testing Tools[1] |
$2,200.00 |
5.4 |
Trial and Error Method |
Tester |
$2,160.00 |
5.5 |
Safety Installation Review |
Tester |
$2,160.00 |
5.6 |
Inspection and Testing Completed |
$0.00 | |
6.1 |
Final Documents are made |
Documenter, Documents[1] |
$2,520.00 |
6.2 |
Review and Sign off |
Project Manager |
$2,400.00 |
6.3 |
Closed |
$0.00 |
Risk Management Plan
The risk analysis is a crucial factor for the progress of the project and foundation of the efficient formation of the project. The using of the risk analysis was helpful for forming the major foundation of the factors developing the smart deliverable for the project. The probable risk factors for the execution of the project of developing new IT center are over budget, delay in schedule, construction problems, shortage of raw materials, and probable human mistakes. The assumptions of the risk being mitigated with the use of the efficient risk mitigation factors.
The risk mitigation would involve the usage of the proper mitigation methods for ensuring that the risk can be sorted out by using the efficient and smart risk analysis. The mitigation of the risk factors is also one of the major factors depicting the use of the efficient risk management. The mitigation of the risk was aligned for easing the using of the proper formation of the functions and operations. The identified risks of the project are over budget, delay in schedule, construction problems, shortage of raw materials, and probable human mistakes that can be sorted out with the help of risk mitigation planning. These risk factors are explained below,
Over Budget: The problem of over budget is one of the most crucial factors for the project. The resources are one of the most crucial factors that is required for ensuring the completion of the project. The resources of the project was aligned with the activities for ensuring the execution. However, the budget limits the usage of the resources and hence resulting in limiting the scope of the project.
Delay in Schedule: The time or schedule for the project is a major factor that restrains the project and forms foundation issues with the completion of the project. The construction and IT installation projects was limited due to the time allocated for the execution of the project. The foundation of the major factors supporting the project activities are bounded by the time factor.
Construction Problems: The project quality is another major constraint for the project as the construction and IT technology was limited with safety and function limitation. The safety requirements and quality of the materials used is another major constraint for the project. The functionality of the system equipments installed in the new function installation. Hence, the problems in construction would result in forming major problems for the project.
Shortage of Materials: The resources of the project was aligned with the activities for ensuring the execution. However, the budget limits the usage of the resources and hence resulting in limiting the scope of the project. Hence, it results in shortage of the resources for the project that develops the problems in quality and project execution.
Probable Human Mistakes: A number of human resources are aligned with this project such as Analyst, Documenter, Project Manager, Planner, Client, Architect, Designer, Workers, Contractor, Engineer, and Tester. The mistakes of any one of them would result in forming the issues in completion of the project.
The following is the risk priority matrix for the project,
Risk Factor |
Likelihood |
Severity |
Impact |
Mitigation |
Over Budget |
High |
Medium |
High |
Mitigate |
Delay in Schedule |
High |
Low |
Medium |
Accept |
Construction Problems |
Medium |
High |
Critical |
Avoid |
Shortage of Materials |
Low |
Medium |
Low |
Transfer |
Probable Human Mistakes |
Low |
Low |
Negligible |
Enhance |
S-Curve of Risk Analysis
Risk Factor |
Likelihood |
Severity |
Impact |
Over Budget |
3.00 |
2.00 |
6.00 |
Delay in Schedule |
3.00 |
1.00 |
3.00 |
Construction Problems |
2.00 |
3.00 |
6.00 |
Shortage of Materials |
1.00 |
2.00 |
2.00 |
Probable Human Mistakes |
1.00 |
1.00 |
1.00 |
Likelihood |
High=3 |
Medium=2 |
Low=1 |
Severity |
High=3 |
Medium=2 |
Low=1 |
Impact |
Likelihood*Severity |
Likelihood*Severity |
Likelihood*Severity |
Quality Assurance Requirements
The new IT centre was efficiently developed with the aim for easing the information installation and taking care of the activities. It is required for easing the existing operations of the organization and provides scope for better information transfer and installation. The activities and operations of the organization was better with the foundation of the new center with all the new equipments and technology devices. The project must be completed in the estimated time and budget requirements. It is assumed that the project plan is feasible and the activities was completed in the calculated time duration resulting in the successful completion of the project.
The quality requirements of the project was based on the limitation of the scope and the installation of efficient functions. The project was completed in 75 working days (approx 3 and half months). The quality requirements of the project for the using of the resources are one of the major factors aligning with the installation of the efficient project execution. The plan of the use of the resources was based on the preliminary project management operations. The project quality is another major constraint for the project as the construction and IT technology was limited with safety and function limitation. The safety requirements and quality of the materials used is another major constraint for the project. The functionality of the system equipments installed in the new function installation.
Project Handover Requirements
The construction of the new IT center is the primary handover requirements for the project. The charter documentation, project plan, design, blueprint of the center, and test results are the other handover requirements of the project. The new IT center was efficiently developed with the aim for easing the information installation and taking care of the activities. The ease of information transfer would also allow the improvement of the factors defining the successful foundation of operations. The installation had been done with the help of proper project management processes and information installation. Some of the handover requirements for the project aloes include construction of infrastructure, installation of the new equipments, project plan documentation, resource management plan, procurement plan, and closure report.
Project Plan Approval
The project of developing the new information technology center was evaluated on the completion of the following factors,
- Installing all safety and quality equipments in the trade center
- Completion of the project in the estimated time duration
- Using of the resources in an efficient way
- Authorization
Approved by the Project Sponsor:
Date:
Bibliography
Borse, G.U. and Attarde, P.M., 2016. Application of six sigma technique for commercial construction project-A review. International Research Journal of Engineering and Technology, vol. 3, no. 6, pp.2323-2328.
Bryson, J.M., 2018. Strategic planning for public and nonprofit organizations: A guide to strengthening and sustaining organizational achievement. John Wiley & Sons.
de Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, vol. 33, no.7, pp.1509-1522.
Fainstein, S.S. and DeFilippis, J. eds., 2015. Readings in planning theory. John Wiley & Sons.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Kuchta, D. and Ptaszy?ska, E., 2017, July. Fuzzy based risk register for construction project risk assessment. In AIP Conference Proceedings, vol. 1863, no. 1, pp. 230006. AIP Publishing.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leigh, N.G. and Blakely, E.J., 2016. Planning local economic installation: Theory and practice. SAGE publications.
Lock, D., 2017. The essentials of project management. Routledge.
Mark, S. and Lurie, Y., 2018. Customized project charter for computational scientific software products. Journal of Computational Methods in Sciences and Engineering, (Preprint), pp.1-12.
Martin, J. and Haggerty, N., 2017. The Project Charter as a Sensemaking Device.
McCann, L., Hassard, J.S., Granter, E. and Hyde, P.J., 2015. Casting the lean spell: The promotion, dilution and erosion of lean management in the NHS. Human Relations, vol. 68, no. 10, pp.1557-1577.
Meredith, J.R., Mantel, S.J., Shafer, S.M. and Sutton, M.M., 2014. Project management in practice. Wiley.
Mok, K.Y., Shen, G.Q. and Yang, J., 2015. Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, vol. 33, no. 2, pp.446-457.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.
Prashar, A., 2014. Adoption of Six Sigma DMAIC to reduce cost of poor quality. International Journal of Productivity and Performance Management, 63(1), pp.103-126.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), pp.53-66.
Shirley, D., 2016. Project management for healthcare. CRC Press.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Tenera, A.M.B.R. and Luís Carneiro, P., 2014. A Lean Six Sigma (LSS) project management improvement model. Selected Papers From The 27th IPMA (International Project Management Association), pp.912-920.
Wuthishuwong, C., Traechtler, A. and Bruns, T., 2015. Safe trajectory planning for autonomous intersection management by using vehicle to infrastructure communication. EURASIP Journal on Wireless Communications and Networking, 2015(1), p.33.
Buy Epm5700 Installation Of New Information Assessment Answers Online
Talk to our expert to get the help with Epm5700 Installation Of New Information Assessment Answers to complete your assessment on time and boost your grades now
The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.