Urgenthomework logo
UrgentHomeWork
Live chat

Loading..

Eng 7071 Project Management For Assessment Answers

Questions: 

Q1. Construct a suitable networ which shows the precedence logic of each activity. You should use the activity-on-arrow or precedence method. This may be done manually on paper but a higher grade may be obtained with the help of software to draw the diagram. Use the diagram to calculate each activity Early Start Day number and hence determine the earliest likely overall completion time. Taking this day number as a target for completion, calculate the Latest Times for each activity or node. Finally
calculate the floats and show the critical path. 

Q2. From your network information using an Excel spreadsheet to one day accuracy produce a Gantt chart based on Early Start times. Explain the limitations of the Gantt Chart on its own and how an activity network assisted by computer software could be used to monitor the actual progress in terms of timing throughout the project and what steps might be taken to improve the timing schedule if the project were required to be completed in two months.  
 
Q3. Using the given cost estimate information calculate total cost by Group and Overall, without and then with Contingency. Construct a budget (BCWS) spreadsheet with activities down the left-hand side and a month by month calendar as the X-Axis. Apply a suitable method of allocating the cost of each activity evenly over each month of its duration. Allocate costs to months. The sheet should show sub-total costs for each activity group and overall per month. Construct a graph against time for the periodic spend and the same information on a cumulative basis. 
 
Q4. Explain how the Earned Value System (EV) works and why it is more appropriate for projects than a simple Actual v Budget system as often applied in on-going business operations. Illustrate how the indices can reveal the true cost and time variances at intermediate stages in the project and help to predict the final position at project completion.   

Answers:

Project Objective

This project’s aim is to describe the planning as well as the implementation process for the installation of an Emergency Power Plant at Pengerang Island. Pengerang Island is located in Kota Tinggi District, Johor, in Malaysia. Being the hub for Petroleum mining, it was necessary to install an Emergency Power Plant that would serve this and other infrastructural and industrial operations that take place in the area. Doing this will ensure that there is ample and uninterrupted power supply in the region hence ensuring the smooth running of the projects in this region. As such, this report will give a step by step procedure of the process of installing this new emergency power plant with utmost consideration of the time frame provided, the budget available and ensure that a quality plant is established at the end of the project.

According to the available land on the Island, the power plant is set to be constructed on a piece of land that has the dimension, 90meter in length and 60 meters in width thus occupying a total area of 4800 square meters.

The project tasks that will be undertaken in a particular project, which are arranged in a logical and systematic manner. As such, it shows the schedule of the whole project with activities starting from the first activity to the last and also showing the duration that each task will take. In this paper, the Activity-on arrow type of network diagram will be used to illustrate the project activities in the installation of the emergency power plant at Penerang Island.

The following table shows the work breakdown structure (WBS) with timing and cost data. The working hours per day are 8 hours standard.

Group

Task Id

Activity details

Duration in Days

Elapsed Time

Cost Information

A General

1

Put up Plan for Approval

2

 

No Cost

 

2

Board Approval

 

5

No Cost

 

3

Notice to organize transport of generator on-site

 

 

 

 

4

Transport generator to site

3

 

10km at 50$ per km

 

5

Hire of crane, lead time

 

 

Hired at 500$ per day

 

6

Lift and Place new generator on site

2

 

5 men at 100$ per day

 

7

Connect to barrier and final test

3

 

3 men at 120$ per day

 

 

8

Commission and sign off with client

1

 

 

 

9

Procurement of contract

15

 

Consultation fee 1500$

B Generator Design and Manufacture

10

Generator in-house designing

30

 

2 staff at 250$ per day

 

11

Delivery of outer steel casing

 

14

Casing costs 7500$

 

12

Spray paint outer casing

1

 

2 staff at 150$ per day

 

13

Manufacture of core generator

14

 

Total cost to manufacture 30,000$

 

14

Assembly of core generator into casing

2

 

5 men at 100$ per day

 

C Electronic Systems

15

Produce new systems specifications

10

 

IT specialists at 20,000$

 

16

Program coding

20

 

IT specialists at 10,000$

 

17

Order hardware for electronics

 

35

Hardware cost 24,000$

 

18

Embed and test new programs

5

 

3 staff at 200$ per day

 

19

Complete purchase of land at barrier

 

40

Land costs 100,000$

 

20

Prepare site and fence off

5

 

3 security specialists at 500$ per day

 

21

Dig foundations

2

 

4 men at 15$ per hour

 

22

Form and reinforcement

5

 

5 men at 15$ per hour

 

 

23

Pour concrete for foundation

1

 

5 men at 15$ per hour

 

24

Concrete cure

15

 

1 man at 15 $ per day

 

25

Order steel security fencing

 

50

 

 

26

Erect steel fence and secure

 

 

Fence contractors charge 100$ per meter of fence

E final assembly

27

Cabling and loom wiring

3

 

2 staff at 150$ per day

 

28

Generator mechanical test

2

 

3 staff at 150$ per day

 

29

Generator electrical test

3

 

2 staff at 150$ per day

To get the earliest time this is obtained by adding the time in the critical path running from A, B, C,D, and E events.

  • The critical path is A1+A3+A7+A8+A9= 2+3+1+15=21days
  • The critical path is B10+B12+B13+B14=30+1+14+2=47days
  • The critical path is C15+C16+C18=10+20+5=35 days
  • The critical path is D20+D21+D22+D23+D24=5+2+5+1+15=28days
  • The critical path is E27+E28+E29+E30+E31=3+2+3+3+2=13days

Thus the earliest time for the whole project will be the sum of the events above which is

21+47+35+28+13=144 days.

The Representation on the Gantt chart

A Gantt chart is a type of graph that is used to describe and show the planning process for a project. As such, this chat illustrates the schedule of the whole project from its start to the end.  The time parameter is a crucial parameter in the setting up of the Gantt chart and it is mostly represented in the form of days, weeks, or months. 

The Gantt chart baseline is the type that is used that gives a comparative depiction of the project of what was planned and what is actually implemented currently. It captures the components of time, cost and the project scope. The baseline chart thus enables the project manager to keep track of the ongoing project and identify any deviations from the project, hence taking the necessary measures to correct this. If everything is going on well according to the baseline, then the project mostly turns out successful.

Advantages and disadvantages of using the Gantt Chart

One of the major advantages of using the Gantt chart is that it is easy read and interpret the information represented on this chart. Secondly, the chart provides more accurate estimates for the project duration hence is reliable for the planning stage of the project. However, the Gantt chart also has some shortcomings which include the fact that the bars only show the duration of the project but they do not truly reflect the amount of work that has to be done so as to achieve this. As such, it may be prone to overestimation or underestimation of the work. The other disadvantage of this chart is that, in the case of big projects, it tends to be very complex and may be difficult to both develop and utilize it.

Planning and Implementing Project Tasks

In order to undertake any kind of project, like in this case the installation of the emergence power supply system, it is necessary that a well-planned procedure is put down that will guide on the same. As such, the manager is tasked with four main responsibilities to achieve this effectively. To begin with, the manager should set up all the activities whereby they will identify and describe all the actions that will be undertaken including their durations. Secondly, the project manager is supposed to establish the relationship between these activities so as to come up with a logical sequence of the activities from the first to the last. Thirdly, the manager should estimate the total amount and type of resources that will be required to achieve each planned activity. Here, they should also establish the costs and the location of these resources and how they will be acquired. Finally, the manager should estimate the duration of each project task and cumulatively establish the time that will be needed to carry out all of these activities. After doing this, they should review the whole project again to ensure that everything is planned in an effective manner and fit for implementation. 

Use of Project Planning Software

There are several planning software that are available in the field of project management which can be very beneficial to the manager undertaking this project. The software will be simplify the work of the manager as it can be used to come up with the various components

Budget BCWP of Pengerang Emergency Power Plant

The budget for the whole project is obtained from the workbreakdown structure provided and it  includes the total cost of the labour, equipment and resources that will be used in carrying out the whole project.  The buget cost of work performed (BCWP) takes into consideration the work that has already been undertaken and includes the overhead costs incurred. It is a crucial parameter in the Earned Value Mangement of the project.

Earned Value (EV) System

The Earned Value System is a project management technique that is used to assess the performance and advancement of a project in an unbiased manner. As such, it measures the three main aspects in a project which are time, cost and scope and enables the comparison of the project in terms of what is planned and what is implemented basis. This system relies on various components which others have been discussed above such as the BCWP, and the Earned Value Analysis.

Earned Value Analysis

 The earned value analysis is a method which the manager uses to measure the actual amount of work that has been completed. From this information, the manager is then able to predict the total cost of the project as well as the date for completion of the same. This relies on some other components such as the planned value, actual costs, earned value and the variance analysis which are discussed below.

Planned value

The planned value is used to determine how far along the project should be undertaken at any given time during the implementation process. It therefore heavily depends on the cost and schedule baseline. The planed value can be categorized into two, the cumulative and current PV. The cumulative planned value entails the amount of the approved budget for all activities that are to be performed to a certain date, while the current planned value considers the budget that has been approved for activities to be performed for a certain period.

The Actual Costs

 The actual costs in a project captures the total amount of money incurred during the implementation of the work and can also be defined as either cumulative or current.

Earned Value

The earned value refers to the figural representation of the accomplishments for the project. It thus relies on the quantification of the whole project and can also be cumulative or current.

Variance Analysis

Variance analysis refers to the technique that the project managers use to examine the actual project implementation and comparing it to what was planned. There are two major aspects that are considered in variance analysis which are the schedule and the cost variances.

Performance Indexes

Performance indexes are methods used to establish the project’s burn rate. This is an alternative method of analysis that managers can use. There are two main types of performance indexes which are schedule index and cost index.  

References

Government Electronics and Information Association. (2002) Earned value management systems Approved: May 19, 1998. Reaffirmed: August 28, 2002. ANSI/EIA-748-A-1998

"KM Systems Group Announces First Annual wInsight Industry Group Conference -- "WIGCON": Earned Value Management (EVM) is an important tool for improving Department of Defense, Federal Agency, and Government Contractor Project Performance". Wall Street Journal - MarketWatch. 21 September 2011. Retrieved 15 November 2011

Marshall, Robert A. (2006-11-09). "The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners" (PDF). PMI (www.pmi.org). Archived from the original (PDF) on July 22, 2011. Retrieved 2006-11-09.

Marshall, Robert. The Contribution of Earned Value Management to Project Success of Contracted Efforts. Journal of Contract Management, 2007, pp. 21-331.

Project Management Institute. (2004) A Guide to the Project Management Body of Knowledge (PMBOK® Guide). (Third ed.) Newtown Square, PA: Project Management Institute

Project Management Institute. (2005) Practice standard for earned value management (PMI Global Standard) (2005 ed.) Newtown Square, PA: Project Management Institute

United States Department of Energy (2005) Earned value managemen

"New federal contracting rules can help or hurt, says former contracting officer". Huntsville Times. 23 September 2011. Retrieved 15 November 2011.

Triant G. Flouris; Dennis Lock (2009). Managing Aviation Projects from Concept to Completion. Ashgate Publishing, Ltd. pp. 207–. ISBN 978-0-7546-7615-7.

"U.S. Penalizes Huntington Ingalls". Reuters. 11 November 2011. Retrieved 15 November 2011.

Wilson, James M. (1 September 2003). "Gantt charts: A centenary appreciation" (PDF). European Journal of Operational Research. 149 (2). doi:10.1016/S0377-2217(02)00769-5. Arc A Guide to the Project Management Body of Knowledge. Newtown Square, PA: Project Management Institute. 2013. pp. 217–219.

Sumara, Jim; John Goodpasture (1997-09-29). "Earned Value -- The Next Generation -- A Practical Application for Commercial Projects" (PDF). Retrieved 2006-10-26.

Goodpasture, John C. (2004). Quantitative Methods in Project Management. J. Ross Publishing. pp. 173–178. ISBN 1-932159-15-0.

Devaux, Stephen A. (2014). Managing Projects as Investments: Earned Value to Business Value. CRC Press. pp. 160–171. ISBN 978-1-4822-1270-9.

Fortuin, Chris. "Agile Compass". OrangeFortune.

Alleman, Glen (2012-06-02). "Herding Cats : Issues with Deploying Earned Value Management". Retrieved 2013-04-04.

Schulze, E. (2010-06-21). "How Earned Value Management is Limited". Retrieved 2013-04-04.hived from the original (PDF) on 2013-11-26. Retrieved 2013-07-28.


Buy Eng 7071 Project Management For Assessment Answers Online


Talk to our expert to get the help with Eng 7071 Project Management For Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Eng 7071 Project Management For Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.