Bco6656 Implementation Of Sap In Assessment Answers

This assessment task (worth 35 percent of the total mark for the unit) requires you to take on the role of an IT
Project Manager to produce a Project Plan for your employer, Victoria University Information Systems Consulting
(VUISC). In this instance the Plan provides a detailed overview of a proposed project. It is developed to provide
the client with a detailed insight into how the project will be managed so they can determine if they will approve
the project to proceed as elaborated. This is an individual assessment task and must not be completed in a group or work shared.
 
You work as IT project manager for a consulting firm based in Melbourne, VUISC Pty Ltd. You have worked at there for four years, while the company has been in operation for several years. The company has a range of employees including consultants, administrative staff, project managers, programmers, testers, business analysts, help-desk and technical support staff who specialise in system implementation, technical writers and end user trainers for professional development. The company provides information systems consultancy and project management services as well.
For the purposes of this assessment task consider your lecturer/tutor to be your operational managers.
 
They can clarify any queries you may have. Your client A detailed client scenario is available on VU Collaborate. It describes a client Yes Chemist Pty Ltd. have asked VUISC to manage the implementation of their SAP System.
Requirements
Review the scenario above carefully before you begin to begin to prepare your Plan. Ask your lecturer or tutor (your VUISC manager) if you have any questions or require any clarification about the scenario. Review the VUIS Consulting Project Plan Template.docx file provided on VU Collaborate. Complete every section of the template removing all prompts (and square brackets) and replacing them with your responses to the scenario.You must develop a schedule for the project comprising at least 50 tasks using Microsoft Project tool.

Submission
This assessment task is due for submission via Turnitin prior to the start of classes in week 10, before midday/ Fri 11:59pm. You must submit three files:
• A copy of a completed assessment declaration sheet (including ticks acknowledging the declaration has been read and understood) as a separate Word document,
• A copy of the MS Project file .mpp schedule and
• Your completed Project Plan in the VUISC template in Word format.

Note that this submission requires the use of a template and a scenario. In some cases significant similarity
results for your Plan may be acceptable. However, you must not have direct matches to the scenario document,
internet sources or other student submissions in your work (the Plan). Please do not leave your submission to
Turnitin to the last moment and contact your tutor for advice if you are concerned about your Turnitin report.

Answer:

Yes Chemist is a business organization that has identified certain operational issues and hence, it has decided to start a project and implement a system that will solve their operational issues and help in business growth. Accordingly, SAP is selected as the most appropriate solution and the project will mainly involve implementation of SAP in their current operational system.

In this report, a project plan has been developed for the implementation of SAP for Yes Chemist and includes some major attributes of the project like schedule, budget, risk and communication plan.

Project scope

The main aim of this project is to develop and implement SAP in the existing operation system of Yes Chemist. Accordingly, the objectives of the project are as follows.

  • Technical upgrade of the existing hardware used by the company
  • Upgrade of the existing software platform utilized by the company
  • Introduction of Enterprise Resource Planning and Data Management System in Yes Chemist
  • Enhancement of operational performance of the organization
  • For client acceptance of each deliverable of the project, the following quality standards are required.

Deliverable

Quality Standard

Assessment of Quality Standard

Technical upgrade of hardware

All hardware resources updated with the latest available technologies

Review procured hardware against the highest quality available in market

Upgrade of software platform

All latest versions with valid license

Review product license and ensure the latest versions are used

ERP and DMS

Detailed resource planning system and data management process

Review the planning of resource use in business as well as how the data management process has been enhanced

Enhancement of operational performance

The operations are completed much faster and with greater efficiency

Monitor system performance and provide training to employees if necessary

Assumptions:

  • It has been assumed that the entire project will be feasible within the budget and schedule limits
  • It has been assumed that the project will solve all the problems faced by the organization

Exclusions:

  • Any business related parts have been excluded from the project
  • Development of future strategies using the developed system has been excluded from the project

Business case

This project will address a lot of business needs of the organization. This project is needed to speed up the lagging operations as a result of manual handling and management of most of the processes as well as use of hardware and software system that are not technically upgraded.

The benefits and dis-benefits of the project are listed below in the table.

Benefits

Current Status

Process for Assessment

More efficient data management process

Slow and error-prone due to manual handling

Monitor working of the system

Better resource management strategy

No specific strategy used

Monitor resource usage

Faster operational system

Slow due to lack of efficiency

Monitor operational progress

Dis-Benefits

Current Status

Process for Assessment

Hard for the employees to adapt

Employees are mostly adapted to the current system

Conduct training sessions

Reduced productivity

Reasonable productivity from the employees

Assess individual productivity of the employees

Project Schedule and Approach (Rollout strategy)

The project schedule (rollout strategy) is developed as follows.

WBS

Task Name

Duration

Start

Finish

Predecessors

0

Implementation of SAP for Yes Chemist

117 days

Mon 10/15/18

Tue 3/26/19

 

1

   Discussion and Preliminary Planning of the Project

9 days

Mon 10/15/18

Thu 10/25/18

 

1.1

      Conduct a Meeting with the Main Stakeholders of the Organization

2 days

Mon 10/15/18

Tue 10/16/18

 

1.2

      Survey and Identify Major Operational Issues

2 days

Wed 10/17/18

Thu 10/18/18

2

1.3

      Consider Various Solutions and Check Feasibility

2 days

Fri 10/19/18

Mon 10/22/18

3

1.4

      Agree on SAP Implementation as the Best Possible Solution

1 day

Tue 10/23/18

Tue 10/23/18

4

1.5

      Consult with SAP Assistance Organization Regarding the Project

2 days

Wed 10/24/18

Thu 10/25/18

5

1.6

      Milestone 1: Provide Authorization for the Project

0 days

Thu 10/25/18

Thu 10/25/18

6

2

   Detailed Planning of the Project

30 days

Fri 10/26/18

Thu 12/6/18

 

2.1

      Initiate Full Planning for the Project

1 day

Fri 10/26/18

Fri 10/26/18

7

2.2

      Recruit SAP Implementation Team for the Project

2 days

Mon 10/29/18

Tue 10/30/18

9

2.3

      Meet the Team Regarding the Project Requirements

3 days

Wed 10/31/18

Fri 11/2/18

10

2.4

      Determine Possible Cost Benefit Margin Post the Project Implementation

2 days

Mon 11/5/18

Tue 11/6/18

11

2.5

      Analysis of Project Feasibility

3 days

Wed 11/7/18

Fri 11/9/18

12

2.6

      Finalize the Project Proposal Document

2 days

Mon 11/12/18

Tue 11/13/18

13

2.7

      Submit the Document for Approval

1 day

Wed 11/14/18

Wed 11/14/18

14

2.8

      Develop the Project Charter

4 days

Thu 11/15/18

Tue 11/20/18

15

2.9

      Determine Project Scope and Limitations

1 day

Wed 11/21/18

Wed 11/21/18

16

2.10

      Identify Project Goals

1 day

Thu 11/22/18

Thu 11/22/18

17

2.11

      Develop Schedule of the Project

1 day

Fri 11/23/18

Fri 11/23/18

18

2.12

      Estimate Budget for the Project

1 day

Mon 11/26/18

Mon 11/26/18

19

2.13

      Develop a List of Resources

1 day

Tue 11/27/18

Tue 11/27/18

20

2.14

      Assess Risks and Prepare Risk Management Plan

5 days

Wed 11/28/18

Tue 12/4/18

21

2.15

      Complete the Project Plan Document

2 days

Wed 12/5/18

Thu 12/6/18

22

2.16

      Milestone 2: Submit Project Plan and Get Project Approval

0 days

Thu 12/6/18

Thu 12/6/18

23

3

   Project Initiation Activities

12 days

Fri 12/7/18

Mon 12/24/18

 

3.1

      Contract Sponsor for Funding

2 days

Fri 12/7/18

Mon 12/10/18

24

3.2

      Allocate Project Roles to SAP Implementation Team

1 day

Tue 12/11/18

Tue 12/11/18

26

3.3

      Hire a Tester for System Review and Testing

2 days

Wed 12/12/18

Thu 12/13/18

27

3.4

      Finalize Roles for Stakeholders and Project Team Members

1 day

Fri 12/14/18

Fri 12/14/18

28

3.5

      Procure Funds for the Project

1 day

Mon 12/17/18

Mon 12/17/18

29

3.6

      Allocate the Funds to the Team as per Requirements

2 days

Tue 12/18/18

Wed 12/19/18

30

3.7

      Procure Project Resources

3 days

Thu 12/20/18

Mon 12/24/18

31

3.8

      Milestone 3: Resource and Budget Allocation Complete

0 days

Mon 12/24/18

Mon 12/24/18

32

4

   Execution and Development

58 days

Tue 12/25/18

Thu 3/14/19

 

4.1

      Initiate Technical Development

2 days

Tue 12/25/18

Wed 12/26/18

33

4.2

      Technical Upgrade of the Hardware

10 days

Thu 12/27/18

Wed 1/9/19

35

4.3

      Develop the Platform on which SAP will be developed

4 days

Thu 1/10/19

Tue 1/15/19

36

4.4

      Subscribe to Cloud Computing Services

2 days

Wed 1/16/19

Thu 1/17/19

37

4.5

      Develop and Install SAP System in the Platform

10 days

Fri 1/18/19

Thu 1/31/19

38

4.6

      Integrate SAP with the Main System

10 days

Fri 2/1/19

Thu 2/14/19

39

4.7

      Connect the System with the Cloud

3 days

Fri 2/15/19

Tue 2/19/19

40

4.8

      Conduct Review and Testing of the System

5 days

Wed 2/20/19

Tue 2/26/19

41

4.9

      Conduct Training Session for Employees regarding Use of SAP

12 days

Wed 2/27/19

Thu 3/14/19

42

4.10

      Milestone 4: Project Handover

0 days

Thu 3/14/19

Thu 3/14/19

43

5

   Project Closing Phase

8 days

Fri 3/15/19

Tue 3/26/19

 

5.1

      Prepare Documentation for the Project

3 days

Fri 3/15/19

Tue 3/19/19

44

5.2

      Review the Entire Project

2 days

Wed 3/20/19

Thu 3/21/19

46

5.3

      Conduct Appraisal

2 days

Fri 3/22/19

Mon 3/25/19

47

5.4

      Stakeholder Signoff

1 day

Tue 3/26/19

Tue 3/26/19

48

5.5

      Milestone 5: Project Officially Closed

0 days

Tue 3/26/19

Tue 3/26/19

49

In the above table, the schedule has been developed in which, the activities mentioned in bold are the project phases. The activities that follow the phases are the work packages and the activities at the end of each phase marked in bold italics are the milestones of the project.

The major project phases are Discussion and Preliminary Planning of the Project, Detailed Planning of the Project, Project Initiation Activities, Execution and Development and Project Closing Phase.

The resources used in the project are as follows.

Resource Name

Type

Initials

Max. Units

Std. Rate

Ovt. Rate

VUISC Project Manager

Work

V

100%

$150.00/hr

$0.00/hr

VUISC Analyst and Supervisor of IT

Work

V

100%

$115.00/hr

$0.00/hr

Sponsor of the Project

Work

S

100%

$0.00/hr

$0.00/hr

VUISC Finance Officer

Work

V

100%

$125.00/hr

$0.00/hr

SAP Developer

Work

S

100%

$75.00/hr

$0.00/hr

System Tester

Work

S

100%

$75.00/hr

$0.00/hr

Resource Procurement Manager

Work

R

100%

$75.00/hr

$0.00/hr

VUISC Project Supervisor

Work

V

100%

$110.00/hr

$0.00/hr

Content Developer

Work

C

100%

$75.00/hr

$0.00/hr

Hardware

Material

H

 

$15,000.00

 

Software

Material

S

 

$5,000.00

 

Other Resources

Material

O

 

$5,000.00

 

In the above table, the resources (both human and material) have been listed along with their costs. The costs of human resources are measured in $ per hour whereas the costs of the material resources are considered as one time costs.

The roles and responsibilities of the human resources are as follows.

Human Resource

Roles and Responsibilities

VUISC Project Manager

Manage, supervise, monitor and control the project

VUISC Analyst and Supervisor of IT

Survey and analyse IT requirements, suggest developments and technical upgrades

Sponsor of the Project

Provide funds for the project

VUISC Finance Officer

Manage funds available for the project

SAP Developer

Develop the necessary requirements in the system

System Tester

Review and test the system

Resource Procurement Manager

Procure necessary resources for the project

VUISC Project Supervisor

Supervise project progress

Content Developer

Prepare documentation of the project

Budget

The overall budget estimated for the project is shown in the following table.

Task Name

Resource Names

Cost

Implementation of SAP for Yes Chemist

 

$157, 520.00

   Discussion and Preliminary Planning of the Project

 

$33, 120.00

      Conduct a Meeting with the Main Stakeholders of the Organization

VUISC Finance Officer, Resource Procurement Manager, VUISC Project Manager, VUISC Project Supervisor

$7, 360.00

      Survey and Identify Major Operational Issues

VUISC Finance Officer, Resource Procurement Manager, VUISC Project Manager, VUISC Project Supervisor

$7, 360.00

      Consider Various Solutions and Check Feasibility

VUISC Finance Officer, Resource Procurement Manager, VUISC Project Manager, VUISC Project Supervisor

$7, 360.00

      Agree on SAP Implementation as the Best Possible Solution

VUISC Finance Officer, Resource Procurement Manager, VUISC Project Manager, VUISC Project Supervisor

$3, 680.00

      Consult with SAP Assistance Organization Regarding the Project

VUISC Finance Officer, Resource Procurement Manager, VUISC Project Manager, VUISC Project Supervisor

$7, 360.00

      Milestone 1: Provide Authorization for the Project

VUISC Project Manager

$0.00

   Detailed Planning of the Project

 

$43, 520.00

      Initiate Full Planning for the Project

VUISC Project Manager, VUISC Project Supervisor, VUISC Analyst and Supervisor of IT

$3, 000.00

      Recruit SAP Implementation Team for the Project

VUISC Project Manager, VUISC Project Supervisor

$4, 160.00

      Meet the Team Regarding the Project Requirements

VUISC Project Manager, VUISC Project Supervisor

$6, 240.00

      Determine Possible Cost Benefit Margin Post the Project Implementation

VUISC Project Supervisor, VUISC Analyst and Supervisor of IT, VUISC Finance Officer

$5, 600.00

      Analysis of Project Feasibility

VUISC Project Supervisor, VUISC Analyst and Supervisor of IT

$5, 400.00

      Finalize the Project Proposal Document

VUISC Project Supervisor

$1, 760.00

      Submit the Document for Approval

VUISC Project Manager

$1, 200.00

      Develop the Project Charter

Content Developer, VUISC Project Supervisor

$5, 920.00

      Determine Project Scope and Limitations

VUISC Project Supervisor

$880.00

      Identify Project Goals

VUISC Project Supervisor

$880.00

      Develop Schedule of the Project

VUISC Project Supervisor

$880.00

      Estimate Budget for the Project

VUISC Finance Officer

$1, 000.00

      Develop a List of Resources

VUISC Finance Officer

$1, 000.00

      Assess Risks and Prepare Risk Management Plan

VUISC Project Supervisor

$4, 400.00

      Complete the Project Plan Document

Content Developer

$1, 200.00

      Milestone 2: Submit Project Plan and Get Project Approval

VUISC Project Manager

$0.00

   Project Initiation Activities

 

$14, 280.00

      Contract Sponsor for Funding

VUISC Finance Officer

$2, 000.00

      Allocate Project Roles to SAP Implementation Team

VUISC Project Manager

$1, 200.00

      Hire a Tester for System Review and Testing

VUISC Project Manager

$2, 400.00

      Finalize Roles for Stakeholders and Project Team Members

VUISC Project Supervisor

$880.00

      Procure Funds for the Project

VUISC Finance Officer

$1, 000.00

      Allocate the Funds to the Team as per Requirements

Sponsor of the Project

$0.00

      Procure Project Resources

Resource Procurement Manager, Other Resources[1]

$6, 800.00

      Milestone 3: Resource and Budget Allocation Complete

VUISC Project Manager

$0.00

   Execution and Development

 

$54, 800.00

      Intiate Technical Development

SAP Developer

$1, 200.00

      Technical Upgrade of the Hardware

SAP Developer, Hardware[1]

$21, 000.00

      Develop the Platform on which SAP will be developed

SAP Developer, Software[1]

$7, 400.00

      Subscribe to Cloud Computing Services

SAP Developer

$1, 200.00

      Develop and Install SAP System in the Platform

SAP Developer

$6, 000.00

      Integrate SAP with the Main System

SAP Developer

$6, 000.00

      Connect the System with the Cloud

SAP Developer

$1, 800.00

      Conduct Review and Testing of the System

System Tester

$3, 000.00

      Conduct Training Session for Employees regarding Use of SAP

SAP Developer

$7, 200.00

      Milestone 4: Project Handover

SAP Developer, System Tester

$0.00

   Project Closing Phase

 

$11, 800.00

      Prepare Documentation for the Project

Content Developer

$1, 800.00

      Review the Entire Project

VUISC Project Manager, Sponsor of the Project

$2, 400.00

      Conduct Appraisal

VUISC Project Manager

$2, 400.00

      Stakeholder Signoff

Content Developer, VUISC Finance Officer, Resource Procurement Manager, VUISC Project Supervisor, VUISC Analyst and Supervisor of IT, SAP Developer, Sponsor of the Project, System Tester

$5, 200.00

      Milestone 5: Project Officially Closed

VUISC Project Manager

$0.00

Risk

A risk register is a table where the project risks are listed and quantified by their chances of occurrence and impact on the project. A risk register for this project is developed as follows.

Risk

Chance of Occurrence

Impact on Project

Mitigation Strategy

Technical risk, lack of technically updated hardware

Medium

High

Procure only the latest upgraded hardware from vendor

Cyber security risk

High

Extreme

Use anti-virus and firewalls in the system

Lack of appropriate system configuration

Medium

Medium

The system should be updated and configured as per required

Budget risk

High

High

Ensure keeping contingency budget for the project

Lack of technical expertise of the employees

Very High

High

Provide training session to the employees

Communication

A communication matrix is a table that highlights the communication requirements of the stakeholders and how they should be communicated.

The communication matrix for the project is shown as follows.

Stakeholder

Why?

When?

How?

VUISC Project Manager

Project updates, requirements and changes

Weekly

Project report document / email

VUISC Analyst and Supervisor of IT

IT related issues

Weekly

Face to face

Sponsor of the Project

Funding requirements

Once before project

Email

VUISC Finance Officer

Fund allocation

As required

Finance report document

SAP Developer

Proposed system requirements

As required

Face to face

System Tester

System configuration

At the end of development of the system

Face to face

Resource Procurement Manager

Resource requirements

At start of project

List of requirements

VUISC Project Supervisor

Project progress update

Daily

Face to face, project progress report

Content Developer

Documentation requirements

Weekly

Email / face to face

Summary

This project plan includes some major aspects of the project that need to be considered while executing the project. As per the assumptions, the project is expected to take 117 days for execution and will consume a total budget of $157,520.

Bibliography

Junnarkar, A.R. and Verma, A., 2017. Study on System Application Product (SAP)–An Important Enterprise Resource Planning Tool for Achievement of Organisational Vision, Mission and Operational Performance.

Umar, M., Khan, N., Agha, M.H. and Abbas, M., 2016. SAP-ERP implementation: Change management model using qualitative approach. International Journal of Computer Science and Network Security (IJCSNS), 16(9).


Buy Bco6656 Implementation Of Sap In Assessment Answers Online


Talk to our expert to get the help with Bco6656 Implementation Of Sap In Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.